Resolved
That planning permission be granted as per the Officer’s recommendation subject to the Conditions as set out in Appendix 1 of the report to the 21 December 2017 Committee meeting.
Central Planning Committee decided this item on Thursday 15 February 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
That planning permission be granted as per the Officer’s recommendation subject to the Conditions as set out in Appendix 1 of the report to the 21 December 2017 Committee meeting.
Committee and date Item
Central Planning Committee 6 15 February 2018 Public
Development Management Report
Responsible Officer: Tim Rogers Email: [email protected] Tel: 01743 258773 Fax: 01743 252619 Summary of Application
Application Number: 17/00405/FUL Parish: Shrewsbury Town Council
Proposal: Removal of existing structures and construction of an A1 (retail) unit; all associated works including car park alterations, access, servicing and landscaping
Site Address: Proposed Retail Unit East Of Unit 8 Meole Brace Retail Park Shrewsbury Shropshire
Applicant: Coal Pension Properties Ltd
Case Officer: Tim Rogers/Karen email: [email protected] Townend
Grid Ref: 349294 – 310522
© Crown Copyright. All rights reserved. Shropshire Council 100049049. 2016 For reference purposes only. No further copies may be made. Central Planning Committee – 15 February 2018 Item 6 – East of Unit 8, Meole Brace Retail Park, Shrewsbury
SUPPLEMENTARY REPORT 1. The Central Planning Committee deferred a decision on this planning application at its 21st December 2017 meeting (Appendix 1 to this report). It asked for the following four matters to be considered further : • The estimated additional vehicle movements; • The timing of the traffic survey; • Access for emergency vehicles; and • The implementation of improvement works within the retail park approved under separate planning application. 2. The applicants have submitted two statements covering each of the four issues. This report the responses received on these four matters, provides an officer view and updates the Committee on any other matters raised in connection with this application since its 21st December 2017 meeting.
The estimated additional vehicle movements
3. Applicants comments The calculation of the additional traffic that is likely to be generated by the proposals is covered in Section 5 of the Transport Statement that accompanied the planning application. The traffic impact of the proposals has been agreed as being acceptable by highways officers at Shropshire Council. It is universally recognised within established best practice that with any extension of existing retail facilities, an increase in floor area will not result in a pro-rata increase in traffic flows. There is an extensive body of evidence for retail developments that the proportional increase in customers as a result of an extension is significantly less than the proportional increase in the size of the development. Recent surveys at Retail Parks demonstrated that increases in floor space resulted in a 12% to 13% pro-rata increase in traffic flows. This issue is covered in detail within Section 5 of the Transport Statement. Given the reasonably small size of the new unit the traffic generation is likely to be much lower than that considered within the Transport Statement. It is highly likely the unit will not be a destination in its own right and the vast majority of the customers will already be visiting the Retail Park and simply extend their stay a little longer to shop at the new unit. As such, the currently estimated peak hour traffic generation of 32 additional trips during the Weekday evening peak hour and 42 more two-way trips during the Saturday afternoon peak hour is a robust analysis of traffic impact in this case. Given the very low increases in traffic, no mitigation is required. Nevertheless, the applicant is aware of issues within the park and is proposing works to improve vehicle flow which in turn have benefits to the operation of the local highway network. These measures include works within the car park and the creation of a new exit lane at the Hereford Road roundabout (application ref 17/00369/FUL). Central Planning Committee – 15 February 2018 Item 6 – East of Unit 8, Meole Brace Retail Park, Shrewsbury
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Item 6 Appendix 1Appendix | 476 KB | Download |
PDF |
Proposed Retail Unit East Of Unit 8 Meole Brace Retail Park, Shrewsbury: 17/00405/FULReport | 368 KB | DownloadRead as text |
Follow Central Planning Committee at Shropshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 4 Jul 2019 | MinutesThat the of the meeting of the Central Planning Committee held on 6 th June 2019 be approved as a correct record and ... | Approved | Open |
| 4 Jul 2019 | Land North East of Kinton, Shrewsbury - 18/00130/EIAThat consideration of the application be deferred to a future meeting of this Committee at the request of the applicant. | Deferred | Open |
| 4 Jul 2019 | Land Off Manor Lane, Longden, Shrewsbury - 16/02395/FULThat authority be delegated to the Head of Planning Services to refuse planning permission subject to further consult... | Refused | Open |
| 4 Jul 2019 | School House Farm, Sheinton, Shrewsbury - 18/04266/FULThat planning permission be granted as per the Officer’s recommendation subject to the conditions set out in Appendix 2. | Decided | Open |
| 4 Jul 2019 | Maesbrook Nursing Home, Church Road, Shrewsbury - 19/01132/FULThat planning permission be granted as per the Officer’s recommendation subject to the conditions set out in Appendix 1. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.