a. That the 2018/19 budget of £582.151m outlined in the Budget Book at Appendix 7, including the savings proposals outlined in Appendix 4 be approved. b. That the changes required to the 2018/19 budget as a result of the Final Local Government Settlement and revised business rates and collection fund estimates be noted. c. That the changes required to future years budgets as a result of the Local Government Settlement be noted. d. That the revised funding gap for the years 2019/20 to 2022/23 be noted. e. That the revised Capital Programme as set out in the report and detailed at section 8 and Appendix 8 be approved. f. That the continued use of the Policy for Flexibility around the use of Capital Receipts be noted. g. That the Statement of Chief Financial Officer on the Robustness of the Estimates and Adequacy of Reserves 2017-23 as set out in Appendix 9, noting the Council’s general fund balance over this period be approved. h. That the Pay and Rewards Policy for all Council staff for 2018/19 as set out in Appendix 10 be approved.
Word for word from the decision Shropshire published for this meeting.Source: www.shropshire.gov.uk
This report sets out the financial strategy for the Council over the next five years, enabling a balanced budget to be set for the years 2018/19 to 2019/20 and considers the potential to set a sustainable and balanced budget in the years beyond.
This Financial Strategy report takes into account previous reports considered by Cabinet over the current financial year; most recently on February 14th, 2018. The report provides information and recommendations on the Council’s proposals to manage its financial position over the next five years and to meet its statutory obligations to set a legal budget for 2018/19.
Following an extensive exercise to model growth in costs over the summer period, and a review of available resources, the first financial strategy report of the financial year was approved by Cabinet on 18 October 2017 and set out the projected funding gap over the current parliamentary period.
The Financial Strategy approved by Cabinet on 10th January 2018 proposed a combination of approaches to close this funding gap. These included raising more Council Tax as a result of new freedoms, putting forward further and extensive savings plans and the continued use of one off grants and reserves. These proposals for savings and council tax income have now been rolled into the projected expenditure and resources position. This has the effect of changing the presentation of the funding gap when compared to the earlier reports considered by Cabinet.
In addition, changes to the value of the funding gap arise as a result of improved information including establishing final taxbase figures and collection fund outturns as well as changes brought about by the Provisional Local Government Settlement announced in December 2017 and the Final Settlement which was announced on 6th February 2018.
Table 1 below summarises the movement between the funding gap announced in October and the current position, and where these changes are presentational or as a result of fundamental change. This results in the remaining structural funding gap for the Council, which needs to be resolved. Council 22nd February 2018: FINANCIAL STRATEGY 2018/19 – 2022/23
Table 1: Projected Funding Gap Movement - Summary
2018/19 (£) 2019/20 (£) 2020/21 (£) 2021/22 (£) 2022/23 (£) Funding Gap as 36,467,901 43,962,531 48,558,987 53,668,794 59,270,364 reported through to Jan 10th 2018 Presentational -14,323,636 -29,997,269 -25,583,824 -31,229,362 -34,003,377 Changes (impact of proposals approved on 10 January 2018) Revised Values -1,942,933 -46,857 673,337 2,015,117 1,960,531 (impact of changes since 10 January 2018) Remaining Funding 20,201,332 13,918,405 20,648,500 24,454,549 27,227,518 Gap as at Feb 14th 2018 (Structural Gap)
This report summarises the work completed to date to close the original funding gap. As outlined in October, the approach to address the funding gap was built on four key pillars; innovate, raise income, cut services and use reserves to smooth delivery.
This approach has generated a large number of proposals front loaded, where possible, to 2018/19 and 2019/20. It is projected that these proposals, in total, will deliver over £43m of savings in base-budget by 2022/23. Details of the individual proposals are provided in Appendix 4.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.