i) That it be noted that at the end of Quarter 1 (30 June 2017), the full year revenue forecast is a potential overspend of £6.790m; ii) That the impact of this on the Council’s General Fund balance be considered. iii) That it be noted that a budget virement, as detailed in Appendix 2, that had taken place at period 3 to allocate pay award funding had not been distributed at budget setting, due to the value of the pay award not having been agreed at that time. i) That it be noted that at the end of Quarter 1 (30 June 2017), the full year revenue forecast is a potential overspend of £6.790m; ii) That the impact of this on the Council’s General Fund balance be considered. iii) That it be noted that a budget virement, as detailed in Appendix 2, that had taken place at period 3 to allocate pay award funding had not been distributed at budget setting, due to the value of the pay award not having been agreed at that time.
Word for word from the decision Shropshire published for this meeting.Source: www.shropshire.gov.uk
1.1The report sets out the projected revenue expenditure for the whole of 2018/19 as at Quarter 1, and for capital sets out the expenditure up to the end of period Quarter 1. For capital, any budget increases and decreases and any re-profiling of budgets between 2018/19 and future years are also set out for decision making.
1.2The revenue monitoring within this report is based on financial information held for the first three months of the year, extrapolated to year end to produce an estimated outturn position. As the year progresses and further financial information becomes available, the quality of the estimates used within this report are expected to increase.
1.3Variances in the overall projected position for the Council do not yet reflect all management action that can be taken. Management action instigated as a result of the Q1 monitoring projections identified in this report will be reflected in the projected outturn reported within the Q2 Monitoring Report.
1.4The report identifies the current projections on delivery of revenue savings included within the forecast. To aid reporting of savings delivery the Council uses a RAG (Red, Amber, Green) rating to identify a rating for the delivery of savings proposals (more detail is provided in the report below). As at Quarter 1, evidence suggests that of the £15.541m of proposals to be delivered in 2018/19, £7.751m are rated as green – with a high degree of certainty of being delivered.
1.5The Quarter 1 position indicates that £2.559m of the £15.541m savings planned are categorised as red, and further work is required within service areas to ensure that the total value of savings proposals is fully deliverable within the financial year. Furthermore, additional ongoing service pressures totalling a net value of £7.188m are already being highlighted, which services will need to address alongside delivering their savings. These pressures have been partially offset by the identification of a number of one off savings in year.
1.6The key issues highlighted by this report are that: The projected revenue outturn is an overspend of £6.790m. Cabinet, 17th September 2018: Financial Monitoring Report – Quarter 1 2018/19
The projected General Fund balance as at 31 March 2019 is £8.521m, which is significantly below the recommended level. Management action is required to attempt to bring the budget back into balance, as far as possible. As described below, the variance is currently projected within the ‘red zone’ and thus above what would be considered a ‘reasonable’ variance. The projected capital outturn is £80.872m, in line with the current budget. This follows a net budget increase of £8.938m in Quarter 1. Current capital expenditure of £5.431m, representing 7% of the budget at Quarter 1, with 25% of the year elapsed.
Recommendations
It is recommended that Members: A. Note that at the end of Quarter 1 (30 June 2017), the full year revenue forecast is a potential overspend of £6.790m; B. Consider the impact of this on the Council’s General Fund balance. C. Note that a budget virement as detailed in Appendix 2 that has taken place at period 3 to allocate pay award funding that had not been distributed at budget setting, due to the value of the pay award not having been agreed at that time.
REPORT
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.