That authority to grant planning permission be delegated to the Head of Planning Services subject to: • The conditions recommended in appendix 1 and any minor modifications to these conditions deemed necessary; and • The signing of a Section 106 agreement to secure a contribution towards flood maintenance.
Word for word from the decision Shropshire published for this meeting.Source: www.shropshire.gov.uk
Recommendation: - Recommend approval subject to the conditions set out in Appendix 1.
REPORT
1.0THE PROPOSAL
1.1The proposal is for proposed refurbishment, extension and conversion of the Stew into 7No apartments, office, spa/leisure, coffee shop and garages
1.2The original plans have been amended following discussions with the agent and applicant. In addition Viability Assessments have been submitted by the applicant and have been analysed by the District Valuation Service.
2.0SITE LOCATION/DESCRIPTION
2.1The Stew lies adjacent to the River Severn at Frankwell Quay side of Shrewsbury within Flood Zone 3. The building is unlisted but is nevertheless considered to be a non-designated heritage asset and it sits in the Frankwell Central Planning Committee – 9 May 2019 Item 5 – The Stew, Frankwell, Shrewsbury
Quay part of the Shrewsbury Town Conservation Area fronting onto the river. The building has a south/south east orientation and is adjacent to the northern edge of the Frankwell Car Park. Beyond the car park is a Pumping Station and protective flood defence wall in front of the river with a boat yard beyond. To the east of this part of the car park and eastern end of the Guildhall is a pedestrian bridge across the river. 2.2 To the east of the building is a narrow lane which also abuts the Guildhall a modern building which provides accommodation for the University Centre Shrewsbury (part of the University of Chester). To the west and beyond the car park exit route is the historic three storey building of the Glen (The Maltings) and beyond this is the Theatre Severn. Immediately to the north of the Glen is the Theatre’s Loading Bay which operates over a 24 hour period. To the north of the Stew building is a roundabout providing access to the loading bay, the Frankwell Car Park and Guildhall underground car park and a public car park. 2.3 The Stew comprises of a part three storey/ part two and half storey and two storey building that is made up to a former ‘Merchants House’ taking up the northern western element with a warehouse on the back and a warehouse is also attached to the southern end too with a smaller wing facing east. The building clearly shows signs of being extensively altered in the past both internally and externally 3.0 REASON FOR COMMITTEE DERMINATION OF APPLICATION
3.1This is a building of historic interest/significance within the town and substantial objections received.
4.0Community Representations
4.1- Consultee Comments SC Conservation & SC Archaeology A joint consultation response for conservation and archaeology has been provided. Amended plans have been submitted that will retain and restore the majority of the former house and southern warehouse ranges including the majority of their roofs whilst adding a four storey extension with a contemporary design.
However the success of the restoration of the historic ranges will be dependent on the use of appropriate materials, building techniques and detailing which will need to be secured by way of pre-commencement conditions.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.