i) That the 2020/21 budget of £575.462m outlined in the Budget Book at Appendix 2, including the savings proposals outlined in section 4.5 of the Medium Term Financial Strategy (MTFS) at Appendix 1 be approved. ii) That the changes required to the 2020/21 budget as a result of the Provisional and Final Local Government Finance Settlement and revised business rates and collection fund estimates be noted. iii) That the revised funding gap for the years 2021/22 to 2024/25 be noted iv) That the Statement of Chief Financial Officer on the Robustness of Estimates and Adequacy of Reserves as set out in sections 6.1 – 6.3 of the MTFS at Appendix 1, noting the Council’s general fund balance over this period be noted. v) That the continued use of the Policy for Flexibility around the use of Capital Receipts as detailed in section 8.1 of the MTFS be noted. vi) That the Pay and Rewards Policy for all Council staff for 2020/21 as set out in Appendix 3 be agreed.
Word for word from the decision Shropshire published for this meeting.Source: www.shropshire.gov.uk
1.1The Financial Strategy report sets out the financial plans for Shropshire Council for the planning period 2020/21 through to 2024/25. The key focus of this document, however, is the setting of the 2020/21 budget. The Government decided to delay the implementation of the Fair Funding Review and a four year Spending Round for a further year so that it would take place in 2021/22. As a result, the bulk of Government funding has remained at consistent levels to that provided in 2019/20. This funding settlement has not bridged the gap in funding arising year on year due to the increase in social care costs and the need to continually reduce other service budgets to ensure that this statutory service can be provided.
1.2There is considerable uncertainty surrounding the 2020/21 Financial Year, and beyond, due to the following changes in local government finance previously timetabled for introduction from 1 April 2020:
1.2.1 Fair Funding implementation – a fundamental re-evaluation of local government finance resulting in a redistribution of government and locally raised funding across local authorities based on needs and demand. 1.2.2 Business Rates Retention – an expected shift from 50% local retention of business rates to 75% retention, with an equivalent reduction in grant funding and as yet unknown responsibility changes 1.2.3 Full Business Rates reset – establishing a new baseline for business rates retention, reallocating growth since the previous reset in 2013. 1.2.4 Comprehensive Spending Review – a process undertaken by HM Treasury to set expenditure limits across government departments and the wider public sector. The impact of this process has the potential to outweigh all other proposed changes. 1.2.5 A potential further review or removal of the New Homes Bonus system, a mechanism that has helped deliver additional, albeit time-limited, funding for the Council to help offset the additional costs associated with housing growth across the county. The latest update on the items raised in 1.2.1 to 1.2.5 is provided in section 2.2 of the Medium Term Financial Strategy.
Recommendations
2.1It is recommended that members:
A. Approve the 2020/21 budget of £575.462m outlined in the Budget Book at Appendix 2, including the savings proposals outlined in section 4.5 of the Medium Term Financial Strategy (MTFS) at Appendix 1. B. Note the changes required to the 2020/21 budget as a result of the Provisional and Final Local Government Finance Settlement and revised business rates and collection fund estimates. C. Note the revised funding gap for the years 2021/22 to 2024/25. D. Note the Statement of Chief Financial Officer on the Robustness of Estimates and Adequacy of Reserves as set out in sections 6.1 – 6.3 of the MTFS at Appendix 1, noting the Council’s general fund balance over this period. E. Note the continued use of the Policy for Flexibility around the use of Capital Receipts as detailed in section 8.1 of the MTFS. F. Agree the Pay and Rewards Policy for all Council staff for 2020/21 as set out in Appendix 3.
REPORT
3. Risk Assessment and Opportunities Appraisal
3.1The development and delivery of the Council’s Financial Strategy is the key process in managing many of the Council’s strategic risks. The opportunities and risks arising are assessed each time the document is refreshed for Cabinet consideration. The Council’s Strategic Risks are reported separately, but the Financial Strategy makes specific reference to the Council’s ability to set a sustainable budget (the highest of the Council’s key strategic risks).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies