i) Work be ceased on the project which involves the full refurbishment of the Shirehall building. ii) Delegated authority be granted to the Executive Director of Place, in consultation with the Portfolio Holder for Assets, Economic Growth and Regeneration , to provide a full evaluation of potential civic centre locations in Shrewsbury town centre along with outline costs and benefits. iii) Delegated authority be granted to the Executive Director of Place, in consultation with the Portfolio Holder for Assets, Economic Growth and Regeneration , to work on a potential disposal strategy for the Shirehall. iv) A report covering the work in ii and iii be provided to Performance Management Scrutiny Committee prior to consideration by Council.
Word for word from the decision Shropshire published for this meeting.Source: www.shropshire.gov.uk
1.1This report sets out the proposal to stop the Shirehall redevelopment project and take a different approach which involves relocating the council’s headquarters to Shrewsbury town centre. This is informed by the way services have been delivered as a result of the COVID19 pandemic and provides greater scope to significantly reduce building related costs and carbon emissions. This in turn will allow the council to spend more on people and less on buildings.
1.2The report seeks Members’ approval to undertake more detailed work to consider options for a new civic centre, which also demonstrates to potential investors and local businesses that the council is creating additional footfall in the town centre and supporting growth in the county’s economy.
1.3The report considered by Council on 13 December 2018 resolved:
i. That the refurbishment of the entire Shirehall building be approved in principle, subject to a further report to be considered by Cabinet with a final business case, developed designs and final project budget.
ii. That the addition of £1.15m to the capital programme to support Stage 3 of the project with delegation to the Director of Place to oversee the production of the final business case be approved. Further option appraisal work be undertaken by officers, at no additional cost and in parallel with the procurement of the design consultants, to ensure that the best value option is secured for the Council.
iii. Delegates to the Director of Place, in consultation with the Portfolio Holder for Corporate and Commercial Support, the development of the procurement strategy for stage 3 Design stage process with developed designs brought back to Cabinet and Council for approval together with the final project budget be approved.
iv. Further reports be considered by the appropriate overview and scrutiny committee prior to consideration by Council
1|Page 1.4 In spring 2019, officers undertook further option appraisal work for a civic centre location in Shrewsbury at no additional cost, the timing of which aligned with work being undertaken as part of the Big Town Plan. The purpose was to identify alternative locations for the Council’s base which had the potential to accommodate other public sector partners and produce additional footfall for Shrewsbury town centre.
1.5In Autumn 2019, officers paused further work on the Shirehall project to ensure that the future requirements for a civic centre involved a more thorough assessment of environmental and economic factors. The Council also needed to review its financial strategy in light of further pressures at this time.
1.6Subsequently as a result of COVID19 pandemic; there has been a fundamental change in the way that staff have been working. Over 95% of staff who work at the Shirehall before the pandemic have been working from home and from other locations during the lockdown period.
1.7A Council staff survey was undertaken in June 2020 in which 90% of staff who responded said they want to work from home, or a mixture of working from home and the office in the future. Embracing this positive response from staff to working differently has enabled the opportunity for the Council to rethink its accommodation requirements and to question the need for a large amount of office space for staff to be based in Shrewsbury.
1.8This report seeks approval for a much smaller amount of investment in the Shirehall building to allow for essential repair, maintenance works and agreed re-alignment of working areas for a period of up to three years to 31 March 2023.
Recommendations
It is recommended that Council:
A. Stop work on the project which involves the full refurbishment of the Shirehall building.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.