Shropshire Council
Cabinet, Monday 7 September 2020 at 1.00pm

Financial Monitoring Report Quarter 1 2020 - 2021

Noted Executive 1 paper

Cabinet noted this item on Monday 7 September 2020. Below is the council's own wording, with the papers it was decided on.

Item11

Resolved

RESOLVED To note that at the end of Quarter 1 (30 June 2020), the full year revenue forecast is a potential overspend of £1.925m; To consider the impact of this on the Council’s General Fund balance.
Word for word from the decision Shropshire published for this meeting. Source: www.shropshire.gov.uk

Follow this further

Built from Shropshire's papers

What the report saysPro

Report to Cabinet

Summary

1.1The report sets out the projected revenue expenditure for the whole of 2020/21 as at Quarter 1, and for capital sets out the expenditure up to the end of Quarter 1. For capital, any budget increases and decreases and any re-profiling of budgets between 2020/21 and future years are also set out for decision making.

1.2The revenue monitoring within this report is based on financial information held for the first three months of the year, extrapolated to year end to produce an estimated outturn position. As the year progresses and further financial information becomes available, the quality of the estimates used within this report are expected to increase.

1.3Variances in the overall projected position for the Council do not yet reflect all management action that can be taken. Management action instigated as a result of the Q1 monitoring projections identified in this report will be reflected in the projected outturn reported within the Q2 Monitoring Report.

1.4The report identifies the current projections on delivery of revenue savings included within the forecast. To aid reporting of savings delivery the Council uses a RAG (Red, Amber, Green) rating to identify a rating for the delivery of savings proposals (more detail is provided in the report below). As at Quarter 1, evidence suggests that of the £18.725m of proposals to be delivered in 2020/21, £5.619m are rated as green – with a high degree of certainty of being delivered.

1.5The Quarter 1 monitoring position suggests that £7.252m of the £18.725m savings planned are categorised as red, and further work is required within service areas to ensure that the total value of savings proposals is fully deliverable within the financial year. Furthermore, additional ongoing service pressures totalling a net value of £6.272m are already being highlighted, which service areas will need to address alongside delivering their savings.

1.6£20.350m non-ringfenced grant has been received by the Council from MHCLG to enable the Council to respond to coronavirus (Covid-19) pressures across all services. In addition to this, it is estimated that the Council may be able to claim approximately £5.447m additional un-ringfenced support from MHCLG to recompense the Council for a proportion of lost sales, fees and charges income that has not been received by the Council due to the pandemic, and also that Cabinet, 7th September 2020: Financial Monitoring Report – Quarter 1 2020/21

£0.442m will be received from HMRC through the Coronavirus Job Retention Scheme. The most recent data submission to MHCLG estimated that additional cost pressures and loss of income to the Council as a result of Covid-19 were £26.438m, resulting in an estimated budget pressure of £0.199m.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Financial Monitoring Report Quarter 1 2020: 2021Report 1.7 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 12 attended
PN
Peter NuttingLeader, present
SC
Steve CharmleyDeputy Leader, present
GB
Gwilym ButlerCommittee Member, present
DC
Dean CarrollCommittee Member, present
LC
Lee ChapmanCommittee Member, apologies
SD
Steve DavenportCommittee Member, apologies
RM
Robert MaceyCommittee Member, present
DM
David MinneryCommittee Member, present
LP
Lezley PictonCommittee Member, present
EP
Ed PotterCommittee Member, present
ML
Michele LeithOfficer, expected
JW
James WaltonOfficer, expected

On this subject at Shropshire

Search all
  1. Financial Monitoring Report Quarter 1 2020 - 2021This decision
  2. Financial Monitoring Report Quarter 2 2026/27Noted
  3. Financial Monitoring Report Quarter 1 2026/27Noted
  4. Financial Monitoring Period 11Noted
  5. Financial Monitoring Period 10Noted
  6. Financial Monitoring Report Quarter 3 2025/26Noted

More from Shropshire Cabinet

All decisions
MeetingDecisionOutcome
18 Nov 2026 MinutesThat the minutes of the meeting held on 14 October 2026 be confirmed as an accurate record. Decided Open
18 Nov 2026 Crisis & Resilience Fund – 6-month Progress UpdateThat Cabinet: 1. Endorsed the summary of the wider economic environment and the Council’s borrowings and investments ... Decided Open
18 Nov 2026 Council Tax Support - Proposed Changes 2027-28 Consultation ResponsesThat Cabinet: 1. Considered the responses received to the statutory consultation. 2. Agreed the following changes to ... Agreed Open
18 Nov 2026 Financial Monitoring Report Quarter 2 2026/27That Cabinet: A. Supported the Q2 favourable revenue outturn forecast of £0.051m. B. Supported the significant advers... Noted Open
18 Nov 2026 Treasury Management Update Quarter 2 2026/27That Cabinet: 1. Endorsed the summary of the wider economic environment and the Council’s borrowings and investments ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies