That planning permission be granted, in accordance with the Officer’s recommendation subject to: • The conditions as set out in Appendix 1 and any modification to these conditions as considered necessary by the Head of Service; and • The additional condition in relation to the protection of Great Crested Newt as detailed in the Schedule of Additional Letters.
Word for word from the decision Shropshire published for this meeting.Source: www.shropshire.gov.uk
Proposal: Hybrid Planning Application for: Full planning permission - formation of a 360m spine road; two 3.5m wide foot and cycleways; one 2m wide footpath; one electricity substation; supporting utilities infrastructure; drainage system; landscaping and ancillary works; Outline planning permission - 10 plots to be delivered in four phases, providing: - a hotel (use class C1) up to 30,000sq. ft; - three units providing up to 6,000sq. ft of hospitality and up to 3000sq. ft of services; - five mixed use units providing general industry with ancillary office (B2 & E) providing up to 180,000sq. ft; - one office unit (use class E) providing up to 15,000sq. ft; - one light industrial unit (use class E) providing up to 63,000sq. ft; - two mixed use units providing storage/distribution with ancillary office (B8 & E) providing up to 200,000sq. ft; - the provision of green infrastructure and all ancillary works.
Site Address: Land Off Mile End Roundabout Oswestry Shropshire
Recommendation:- subject to the conditions set out in Appendix 1.
REPORT
Recommendation: Approval subject to the conditions as set out in appendix 1 attached to this report and any modification to these conditions as considered necessary by the Head of Service.
1.0THE PROPOSAL
1.1The application is a 'Hybrid Planning Application' for: Full planning permission - formation of a 360m spine road; two 3.5m wide foot and cycleways; one 2m wide footpath; one electricity substation; supporting utilities infrastructure; drainage system; landscaping and ancillary works; Outline planning permission - 10 plots to be delivered in four phases, providing: - a hotel (use class C1) up to 30,000sq. ft; - three units providing up to 6,000sq. ft of hospitality and up to 3000sq. ft of services; - five mixed use units providing general industry with ancillary office (B2 & E) providing up to 180,000sq. ft; - one office unit (use class E) providing up to 15,000sq. ft; - one light industrial unit (use class E) providing up to 63,000sq. ft; - two mixed use units providing storage/distribution with ancillary office (B8 & E) providing up to 200,000sq. ft; - the provision of green infrastructure and all ancillary works.
on land at Land off Mile End Roundabout, Oswestry.
1.2The application is accompanied by a site master plan, phasing plan, (outline), site plan, (full), location plan, substation elevations and floor plan, landscape master plan, planning Agenda Item 8 - Land Off Mile End Roundabout Northern Planning Committee – 7th July 2021 Oswestry
statement, design and access statement, and forming the 'Environmental Statement is detail in relation to soils/land reports, noise reports, archaeology report, biodiversity reports, cultural reports, historic environment report, construction assessment, cumulative impact assessment, waste management strategy, tree report, landscape and visual impact assessments, surface water and flood risk assessment, economic benefits report, transport assessment, travel plan and a statement of community involvement.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.