That Cabinet: · Noted the progress made since the approval of The Shropshire Plan by Council, driving the fundamental transformation of the Authority around the vision ‘Shropshire Living the Best Life’. · Approved the appointment of a Strategic Transformation Partner to provide capacity and capability in the delivery of the extensive transformation programme required to deliver The Shropshire Plan within the projected funding envelope over the period of the Medium Term Financial Strategy That Cabinet: · Noted the progress made since the approval of The Shropshire Plan by Council, driving the fundamental transformation of the Authority around the vision ‘Shropshire Living the Best Life’. · Approved the appointment of a Strategic Transformation Partner to provide capacity and capability in the delivery of the extensive transformation programme required to deliver The Shropshire Plan within the projected funding envelope over the period of the Medium Term Financial Strategy
Word for word from the decision Shropshire published for this meeting.Source: www.shropshire.gov.uk
Cabinet Member (Portfolio Holder): Lezley Picton, Leader
1. Synopsis The Shropshire Plan was formally agreed by Shropshire Council in May 2022. This report sets out the significant progress made by Cabinet and Officers over the intervening 9 months and outlines next steps for the authority.
2. Executive Summary 2.1. Commencing in 2021, the Council’s Cabinet and the Senior Leadership Team have embarked on a programme of work to optimise performance across Shropshire Council in a measured but transformative approach. The start of this process was to agree a strategic plan for the Council (i.e. The Shropshire Plan) and this was approved by Full Council in May 2022 incorporating the Vision ‘Shropshire Living the Best Life’.
2.2This report updates Members on the significant progress undertaken in the intervening nine months, providing a robust framework for next steps over the coming years. Key details are set out in Section 7 and Appendix A of the report including the procurement of a Strategic Transformation Partner to provide capacity and capability in the delivery of the Council’s Target Operating Model (“TOM”) and Medium Term Financial Strategy (“MTFS”) and ultimately to deliver the Council’s strategic outcomes as set out in The Shropshire Plan.
Contact: James Walton on 01743 258915 1 Cabinet 15 th February 2023; The Shropshire Plan Update
3. Recommendations That Cabinet:
3.1Notes the progress made since the approval of The Shropshire Plan by Council, driving the fundamental transformation of the Authority around the vision ‘Shropshire Living the Best Life’.
3.2Approves the appointment of a Strategic Transformation Partner to provide capacity and capability in the delivery of the extensive transformation programme required to deliver The Shropshire Plan within the projected funding envelope over the period of the Medium Term Financial Strategy.
Report 4. Risk Assessment and Opportunities Appraisal 4.1. The Shropshire Plan (“TSP”) sets out the Council’s priorities and Strategic Objectives. The Council is currently arranged to deliver the proposed outcomes of TSP, but with some examples of sub-optimal performance and interventions that are not sustainable within the expected financial envelope. The Council’s strategic risks are a source of focus in determining how best to deliver TSP in practice. Furthermore, aligning our resources to the outcomes of TSP reduces the risk of overspends and the risks of non- delivery of expected outcomes. There are risks, however, that predominantly fall within financial year 2023/24 under two themes; the scale of the spending reduction needed for the Council to fall within the expected funding envelope in 2023/24 and in the tight timescales within which to deliver the expected outcomes. These risks exist at an organisational level and, to different degrees, within individual projects, be they as part of the MTFS, TOM or Service Delivery Planning.
4.2To manage the highest levels of risk identified above the following mitigations have been applied:
4.2.1. A single project management approach is being adopted for all transformational work regardless of its origin or current status. 4.2.2. High level project plans have been identified for all delivery projects 4.2.3. Realtime reporting on delivery milestones is being developed within and alongside the developing performance management framework 4.2.4. Procurement of a Strategic Transformation Partner will provide additional capacity and capability for the overall programme 4.2.5. A better-than-expected Provisional Settlement has provided for the following opportunities: De-risking of the transformation programme by reviewing the highest risk projects and providing more time and/or resource to deliver the expected outcomes
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.