That Council agree to : 1. Approve the acceptance of the Levelling Up Fund Grant award from the Department for Levelling Up, Housing and Communities (DLUHC) , and instruct officers to pro gress the associated projects. 2. Approve financing of the Council’s cash match funding requirement of £3.793m from borrowing with an associated annual revenue impact of £0.269m 3. Approve the inclusion of enabling and infrastructure works associated to the Levelling Up Fund Award, within the planning application(s) for the demolition of the Riverside Shopping Centre and the former Riverside medical practice, as recommendation 3.2 approved in the Council report titled ‘Shrewsbury Town Centre Redevelopment Phase One’ 16 February 2022 . 4. Delegate to the Executive Director of Place in consultation with the Section 151 officer and the Portfolio Holder for Economic Growth, Regeneration and Planning to: 4.1. proceed with compiling the full financial details and business case for the two projects summarised in item 2.2 of the report, for inclusion in a further report for consideration by Council. 4.2. progress a procurement and delivery strategy for the two projects summarised in items 2.2 of the report.
Word for word from the decision Shropshire published for this meeting.Source: www.shropshire.gov.uk
1. Synopsis To recommend to Council to accept the successful bid award from DLUHC Levelling Up Fund Round 2, to accelerate enabling and infrastructure works for the Smithfield Riverside Redevelopment Programme and deliver the Transforming Movement and Public Spaces project in Shrewsbury.
2. Executive Summary 2.1. Further to recommendations approved in the report to Cabinet on 8 June 2022, titled ‘Levelling up for Shropshire’, officers submitted bids to the Department for Levelling Up, Housing and Communities (DLUHC), under the UK Levelling Up Fund Round 2 (LUF2), for Shrewsbury, Oswestry and Craven Arms, as well as a county-wide transport bid.
2.2The Shrewsbury bid was successful with a LUF2 award of £18.701m to support two packages of work as follows:
2.2.1. Smithfield Riverside Redevelopment Programme (Project 1): demolition, site remediation and associated enabling works, necessary to facilitate the future regeneration of the former Riverside shopping centre with high quality mixed-use development, including a diverse range of commercial office, leisure, hospitality, and food and beverage uses with associated public realm alongside the River Severn.
2.2.2. Transforming Movement and Public Spaces in Shrewsbury (Project 2): public realm improvements adjacent to the town’s rail station and Northern Corridor improving a key gateway into the town, improving resident and visitor safety, air quality and enjoyment of these areas through improved connectivity. 6 July 2023 Levelling Up Award for Shrewsb ury
2.3It was agreed at Cabinet on 19 April 2023 (report title ‘Levelling Up for Shrewsbury’) to seek Council approval to the recommendations contained within this report.
2.4The Shropshire Plan’s Healthy Economy strand highlights the importance of investment in key strategic locations and assets including Smithfield Riverside to drive economic activity. Investment from the LUF2 award can be directly linked and attributed to the Shropshire Plan.
3. Recommendations That Council agree to:
3.1Approve the acceptance of the Levelling Up Fund Grant award from the Department for Levelling Up, Housing and Communities (DLUHC), and instruct officers to progress the associated projects.
3.2Approve financing of the Council’s cash match funding requirement of £3.793m from borrowing with an associated annual revenue impact of £0.269m
3.3Approve the inclusion of enabling and infrastructure works associated to the Levelling Up Fund Award, within the planning application(s) for the demolition of the Riverside Shopping Centre and the former Riverside medical practice, as recommendation 3.2 approved in the Council report titled ‘Shrewsbury Town Centre Redevelopment Phase One’ 16 February 2022.
3.4Delegate to the Executive Director of Place in consultation with the Section 151 officer and the Portfolio Holder for Economic Growth, Regeneration and Planning to:
3.4.1. proceed with compiling the full financial details and business case for the two projects summarised in item 2.2 above, for inclusion in a further report for consideration by Council.
3.4.2. progress a procurement and delivery strategy for the two projects summarised in items 2.2 above.
Report 4. Risk Assessment and Opportunities Appraisal 4.1. Risk management will inform the basis of any reporting, deep dives and assurance provision. The risk management processes we have in place are extremely robust against any challenge and the project teams in place are thoroughly engaged in the process.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.