Cambrian Railway Building Oswestry - Request for Capital Funding to Match UKSPF Grant Offer

Agreed Executive 4 papers

Cabinet agreed this item on Wednesday 17 January 2024. Below is the council's own wording, with the papers it was decided on.

Item103

Resolved

That Cabinet: 1. Delegated authority to the Executive Director for Resources to enter into an Agreement with the UKSPF to restore the exterior of the building and to secure £630,250 in grant aid. 2. Approved match funding of £270,107 of capital to be financed through borrowing. 3. Provided Authority to Proceed with the project to restore the exterior of the Cambrian Railway Building in Oswestry and requested that the capital programme is updated to reflect Cabinet approval of this report, within the capital programme being approved by Council on 29 February 2024. 4. Delegated authority to the Executive Director for Place to proceed with the delivery of the exterior restoration including listed building consent, detailed design, tendering of works and construction. 5. Once the Conservation Management Plan and surveys are complete a business case for the re-use of the Cambrian Building is brought back to the Cabinet for review and consideration of any additional investment required to restore the interior of the building and make it suitable for re-use. That Cabinet: 1. Delegated authority to the Executive Director for Resources to enter into an Agreement with the UKSPF to restore the exterior of the building and to secure £630,250 in grant aid. 2. Approved match funding of £270,107 of capital to be financed through borrowing. 3. Provided Authority to Proceed with the project to restore the exterior of the Cambrian Railway Building in Oswestry and requested that the capital programme is updated to reflect Cabinet approval of this report, within the capital programme being approved by Council on 29 February 2024. 4. Delegated authority to the Executive Director for Place to proceed with the delivery of the exterior restoration including listed building consent, detailed design, tendering of works and construction. 5. Once the Conservation Management Plan and surveys are complete a business case for the re-use of the Cambrian Building is brought back to the Cabinet for review and consideration of any additional investment required to restore the interior of the building and make it suitable for re-use.
Word for word from the decision Shropshire published for this meeting. Source: www.shropshire.gov.uk

Follow this further

Built from Shropshire's papers

What the report saysPro

Report to Cabinet

Meeting date and Report Title

Cabinet – 17th January Item 2024

Public

Cambrian Railway Building Oswestry – Request for capital funding to match UKSPF grant offer Responsible Officer: Steve Law

email: [email protected] Tel: 01743 281017

Cabinet Member (Portfolio Holder): Dean Carroll

1. Synopsis This report is seeking authority to proceed with a capital project to restore the exterior of the Cambrian Railway Building in Oswestry, a Grade 2 listed building in the ownership of the Council. The cost is estimated at £900,357 and a UKSPF bid has secured an offer of 70% but now requires 30% match funding from the Council’s capital programme.

2. Executive Summary 2.1. The Cambrian Railway Building is a Grade 2 listed building in the ownership of Shropshire Council. The building dates from 1866 and was both the headquarters of the Cambrian Railway and Oswestry Station until it’s closure in 1975. The building is listed by Historic England because it is a good example of a Victorian regional railway headquarters building and a notable feature is the row of ornate corbels (cement molded carvings) which surround the building which were installed under the roof eaves.

2.2Over the passage of time, the fittings holding the corbels in place have become corroded and weathered. Following a heavy storm in 2022 a number of corbels became lose and as a safety precaution scaffolding has been placed around the building to prevent any corbels or pieces of masonry falling on pedestrians or building visitors.

Contact: Name and phone numb er of author 1 Meeting date and Report Title

Iron pin corrosion and decay of stringer course poses risk of corbels falling

2.3Inspection by the Council’s conservation team and building surveyors has also identified that at some time in the past 40 years, the original slates from the roof have been removed and replaced with tiles made of a ceramic composite which includes asbestos. These tiles have now become weathered, and the asbestos fibres are now exposed requiring their replacement.

2.4It is now imperative that the exterior of the building undergoes a restoration to replace the corroded roof tiles and restore and secure the corbels. This together with repainting of the building and repairs of the guttering, soffits and drain-pipes is an essential first step to removing the scaffolding and making the building safe to enable it to be re-used and support the regeneration of this part of Oswestry.

2.5In the latest review of the capital strategy discussed at Cabinet on 6th Sept 2023 and Full Council on 21st Sept 2023, the Cambrian Railway Building was added to the List of Priority Schemes Schedule -Appendix B, with an indicative restoration cost of £1.47 million. This is the initial estimate for restoring both the exterior and interior of the building. The estimated costs of this proposed external restoration are £900,357 of capital spend.

2.6In October 2023, the UK Shared Prosperity Fund (UKSPF) in Shropshire announced that there was funding available for the restoration of historic buildings in Shropshire, and the Council team submitted a proposal for these works. On 27 th November the Council was notified that the bid had been successful and was being offered 70% of the required funding, amounting to £630,550. However, this grant offer requires 30% match funding to be made available from the Council’s capital programme at a cost of £270,107. The terms of the grant require the works to be completed by the end of March 2025.

2.7This grant funding offer is a significant opportunity for the Council to realise one of their capital proprieties and therefore this report is seeking Cabinet approval to proceed with the project and assign the match funding through the capital programme. This initiative fits well with the Shropshire Plan meeting objectives in the area of Healthy Economy by bringing a largely disused and poor condition landmark building back into use as a major community and business asset.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Shropshire Council Cambrian Railway Notification Letter November 2023Appendix 1 174 KB Download
PDF
Cambrian Cost ModelAppendix 2 760 KB Download
PDF
Cambrian Building BriefingAppendix 3 4.1 MB Download
PDF
Cambrian Railway Building Oswestry: Request for Capital Funding to Match UKSPF Grant OfferReport 1.2 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 20 attended
LP
Lezley PictonLeader, present
CM
Cecilia MotleyCommittee Member, present
IN
Ian NellinsCommittee Member, present
RM
Robert MaceyCommittee Member, present
GB
Gwilym ButlerCommittee Member, present
DC
Dean CarrollCommittee Member, present
KH
Kirstie Hurst-KnightCommittee Member, present
MJ
Mark JonesCommittee Member, present
DM
Dan MorrisCommittee Member, present
CS
Chris SchofieldCommittee Member, present
AB
Andy BegleyOfficer, expected
JW
James WaltonOfficer, expected

All 20 on the meeting page

More from Shropshire Cabinet

All decisions
MeetingDecisionOutcome
18 Nov 2026 MinutesThat the minutes of the meeting held on 14 October 2026 be confirmed as an accurate record. Decided Open
18 Nov 2026 Crisis & Resilience Fund – 6-month Progress UpdateThat Cabinet: 1. Endorsed the summary of the wider economic environment and the Council’s borrowings and investments ... Decided Open
18 Nov 2026 Council Tax Support - Proposed Changes 2027-28 Consultation ResponsesThat Cabinet: 1. Considered the responses received to the statutory consultation. 2. Agreed the following changes to ... Agreed Open
18 Nov 2026 Financial Monitoring Report Quarter 2 2026/27That Cabinet: A. Supported the Q2 favourable revenue outturn forecast of £0.051m. B. Supported the significant advers... Noted Open
18 Nov 2026 Treasury Management Update Quarter 2 2026/27That Cabinet: 1. Endorsed the summary of the wider economic environment and the Council’s borrowings and investments ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies