That Council a) Approves the delegation of programme development responsibility for the NWRR together with authority to spend up to an additional £ 16. 9 81m (as set out in more detail within the table at paragraph 5.9 below) so as to enable the completion of the Full Business Case submi ssion , to the Executive Director of Place in consultation with the Portfolio Holder for Highways and Transport , n oting that £6. 667 m of this will be funded by the DfT Large Local Majors Grant. The breakdown of this delegation , including contingency, is £ 16.499m advance works costs , £181,500 to deliver the FBC , and £300 ,000 to cover exceedance of current delegation. b) Confirms , for the avoidance of doubt, that the previous total combined delegation of £27.9m was comprised of £15m (NWRR) and £12.9m (OLR).
Word for word from the decision Shropshire published for this meeting.Source: www.shropshire.gov.uk
2.1The NWRR Scheme is a strategic transport project that aims to provide a new single carriageway road linking the northern and western parts of Shrewsbury, reducing congestion, improving air quality, and supporting economic growth and allocated housing delivery in the area. It will also act as an enabler to Shrewsbury Town Centre projects around Riverside, LUF2 and the provision of enhanced active Travel measures under the Big Town Plan Movement Strategy
Additional Forecast benefits include
Reducing congestion and journey times on the existing road network, especially in the town centre, by providing a new and more efficient route for local and strategic traffic. Full Council - 29 Feb 2024 - Shrewsbury North West Relief Road – Funding Delegation
Improving air quality and public health by reducing emissions and noise from traffic, and by encouraging the use of sustainable modes of transport, such as walking, cycling, and public transport. Supporting economic growth and regeneration by improving the accessibility and the connectivity of Shrewsbury and the surrounding areas, and by creating new opportunities for business, employment, housing, and tourism. Enhancing the quality of life and the well-being of the local community by reducing the negative impacts of traffic on the historic and natural environment, and by providing new green spaces and recreational facilities. As such, the project will align in part or fully with the Healthy Economy, People and Environment pillars within the Shropshire Plan.
2.2The full NWRR alignment comprises two discrete elements. The Oxon Link Road (OLR), funded in part by the Marches Local Enterprise (section from Churncote Roundabout, A5, to Holyhead Road), and the wider DfT part funded section (Holyhead Road to Battlefield Island).
2.3The budget for the Oxon Link Road section in isolation was approved by Council in 2016/17 at a total of £12.9m, funded from £4.2m LEP and £8.7m from Section 106 Developer Contributions. In 2019/20 Council approved a delegated budget of £15m for programme entry into the Department for Transport’s Large Local Majors funding for the NWRR section. Both projects remain in the Capital Programme as separately funded schemes due to the requirements of the funding partners.
2.4For the purposes of Planning and the Main Construction Contract, these two elements are managed as a single project, and referred to holistically as the NWRR.
2.5Since May 2019 (NWRR) and Feb 2017 (OLR), the NWRR has been in delivery, following Outline Business Case endorsements by both funders and budget requirements being built into the Council’s Capital Programme. Background Papers listed at the end of this report lay out the Council decisions and approvals that support this position.
2.6Previous financial delegations (below) cover activities across the whole NWRR alignment, particularly where activities (Environmental mitigation, advance works and Carbon assessments for example) are scheme wide.
NWRR £15.0m OLR £12.9m Total £27.9m
2.7The current delegation was set around the expected timetable to FBC for the NWRR to DfT and included the forecast costs around completion of other activities in parallel including, Planning Application, Advance Utility Works, Detailed Design and Main Contractor Procurement.
2.8Following the grant of Planning Permission (subject to finalisation of proposed Conditions and the signing of required S.106 agreements) on the 15th of
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.