CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Shropshire Council
West Mercia Energy Joint Committee, Friday 20 September 2024 at 10.30am

Minutes

Approved Committee 1 paper

West Mercia Energy Joint Committee approved this item on Friday 20 September 2024. Below is the council's own wording, with the papers it was decided on.

Item82

Resolved

That the of the West Mercia Energy Joint Committee held on 22nd March 2024 be approved as a correct record.
Word for word from the decision Shropshire published for this meeting. Source: www.shropshire.gov.uk

Follow this further

Built from Shropshire's papers

What the report saysPro

Report to West Mercia Energy Joint Committee, 4 pages

Committee and Date

West Mercia Energy Joint Committee

20th September 2024

WEST MERCIA ENERGY JOINT COMMITTEE

Minutes of the meeting held on 22 March 2024 In the Wilfred Owen Room, Shirehall, Abbey Foregate, Shrewsbury, Shropshire, SY2 6ND 2.00 - 4.00 pm

Responsible Officer: Tim Ward Email: [email protected] Tel: 01743 257713

Present Councillors Gwilym Butler (Chairman), Lee Carter, Nathan England, Adam Kent and Adrian Hardman (Vice Chairman)

67 Apologies for Absence

Apologies for absence were received from Councillors Graham Biggs and Dean Carroll

Councillor Peter Stoddard joined the meeting remotely, taking no part in the voting on any of the items for consideration.

68 Minutes

RESOLVED:

That the Minutes of the West Mercia Energy Joint Committee held on 26 th September 2023 be approved as a correct record and signed by the Chairman.

69 Public Questions

No public questions had been received.

70 Disclosable Pecuniary Interests

There were no interests declared

71 Supplier contracts

The Director confirmed that there were no entries to report

72 External Audit Plan 2023/24

The Head of Finance and Billing introduced the report which set out the proposed external audit plan for 2023/24. Minutes of the West Mercia Energy Joint Committee held on 22 March 2024

John Fletcher, External Auditor took Members thought the report drawing their attention to the following points –

 Materiality had been determined using the benchmark figures set out in the table on page 10 of the pack and that the levels had been set to ensure that sufficient audit work was carried out.  2 significant risks identified in the plan are standard to all audits and the Committee should be satisfied that there are controls in place.

A Member raised the risk of loss of key personnel and business continuity. The External Auditor stated that this was considered as part of the “going concern” assumption.

RESOLVED:

That the Joint Committee

a) approve the draft audit plan for 2023/24 as presented by WR Partners attached at Appendix 1

b) approve the commissioning of WR Partners to undertake the audit in accordance with the audit plan.

73 Internal Audit Performance Reports to March 2024

The Auditor presented the report which provided an update on the work completed by Internal Audit against the approved Internal Audit Plan 2023/24. She advised Members that all planned audit work for 2023/24 had been completed, and that reviews attracting good assurance were Finance, Debtors, Corporate Governance including Risk Management and Procurement and that the review of the IT Strategy attracted a reasonable assurance.

RESOLVED:

That the Committee endorse the performance to date against the 2023/24 Audit Plan as set out in the report.

74 Internal Audit Strategic Plan 2024/25

The Auditor presented the report which set out the proposed programme of audit work for the year 2024/25.

RESOLVED

That the Committee endorse the proposed programme of audits for 2024/25.

75 Anti-Slavery and Human Trafficking Statement 2023/24

The Director presented the report which set out the draft transparency statement which was required as part of the Anti-Slavery and Human Trafficking Policy.

Contact: Shelley Davies on 01743 257717 2 Minutes of the West Mercia Energy Joint Committee held on 22 March 2024

RESOLVED

That the Joint Committee:

a) approve the draft WME Transparency Statement for 2023/24

b) delegate authority to the Director to finalise the WME Transparency Statement and publish it in accordance with section 54 of the Modern Slavery Act 2015.

76 Risk Management Update

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
MinutesMinutes 4 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Shropshire

Search all
  1. MinutesThis decision
  2. MinutesDecided
  3. MinutesDecided
  4. MinutesDecided
  5. MinutesDecided
  6. Minutes of the previous meetingApproved

More from Shropshire West Mercia Energy Joint Committee

All decisions
MeetingDecisionOutcome
25 Sep 2026 Statement of Accounts 2025/26 and Annual Governance Statement 2025/26That the finalised Statement of Accounts 2025/26 be signed by the Chairman and the Treasurer. That the Annual Governa... Noted Open
25 Sep 2026 External Audit - Audit findings report 2025/26That the contents of the audit findings report presented by WR Partners be considered and endorsed. Decided Open
25 Sep 2026 Distribution of SurplusThat the retention of accumulated surplus of £1.594 million be approved. That the distribution of accumulated surplus... Approved Open
25 Sep 2026 Risk Management UpdateThat the medium risks presented be considered and endorsed. Decided Open
25 Sep 2026 Anti-Slavery and Human Trafficking PolicyThat the WME Anti-Slavery and Human Trafficking Policy be approved. Approved Open