Shropshire Council
Cabinet, Wednesday 12 February 2025 at 10.30am

Whitchurch Civic Centre - Options Appraisal

Agreed Executive 4 papers

Cabinet agreed this item on Wednesday 12 February 2025. Below is the council's own wording, with the papers it was decided on.

Item256

Resolved

3.1 Based on the outline feasibility investigations and assessments, Cabinet agreed that the RAAC affected areas of the Civic building and Library continue to remain permanently closed due to its critical condition and delegated the following: I. To the Executive Director of Resources to amend the capital strategy to reflect the revised implications set out within the report, to incorporate £4 million into the capital strategy to provide for the following: a. Should central government funding or other external funding be secured this would form the Council’s match funding (if required) for Option 2 – construction of a new replacement facility based on the findings of a needs assessment. b. Should external funding not be secured then the proposed £4 million would be considered for Option 1 - replacement of the structural RAAC roof, consequential works, and priority capital condition improvements II. To the Head of Property and Development to oversee appropriate funding bids and the production of a detailed strategic needs assessment and analysis to establish the need of the people of Whitchurch for facilities at WCC so the future configuration of WCC is best suited to the needs of the town and its surrounding area. Subject to recommendations in 3.1 I and II and the successful confirmation of appropriate funds to bring a further report back to full Council with a final recommendation 3.1 Based on the outline feasibility investigations and assessments, Cabinet agreed that the RAAC affected areas of the Civic building and Library continue to remain permanently closed due to its critical condition and delegated the following: I. To the Executive Director of Resources to amend the capital strategy to reflect the revised implications set out within the report, to incorporate £4 million into the capital strategy to provide for the following: a. Should central government funding or other external funding be secured this would form the Council’s match funding (if required) for Option 2 – construction of a new replacement facility based on the findings of a needs assessment. b. Should external funding not be secured then the proposed £4 million would be considered for Option 1 - replacement of the structural RAAC roof, consequential works, and priority capital condition improvements II. To the Head of Property and Development to oversee appropriate funding bids and the production of a detailed strategic needs assessment and analysis to establish the need of the people of Whitchurch for facilities at WCC so the future configuration of WCC is best suited to the needs of the town and its surrounding area. Subject to recommendations in 3.1 I and II and the successful confirmation of appropriate funds to bring a further report back to full Council with a final recommendation
Word for word from the decision Shropshire published for this meeting. Source: www.shropshire.gov.uk

Follow this further

Built from Shropshire's papers

What the report saysPro

Report to Cabinet

Executive summary

2.1Reinforced Autoclaved Aerated Concrete (RAAC) was discovered at Whitchurch Civic Centre Complex and Library during ongoing repair and maintenance activities leading to subsequent assessments. These detailed investigations have determined that the RAAC within the Civic and Library buildings is in critical condition. Consequently, as per the Cabinet decision dated Wednesday, 17th January 2024, the building has been decommissioned, secured, and closed. 12/02/2025: Whitchurch Civic Centre & Library Reinforced Autoclave Aerated Concrete (RAAC)

2.2The report provides an update on the actions taken to address issues related to the RAAC following the decision to decommission and close most of the complex for safety reasons. It outlines subsequent steps and recommendations based on further evaluations and work to date.

2.3RAAC, a lightweight concrete, was used in UK construction from the 1950s to the 1980s for roofs, floors, cladding, and walls. Initially known for its durability, recent findings indicate more serious issues. The Local Government Association urges public authorities to urgently inspect buildings for RAAC components.

2.4This report acknowledges that leaving the RAAC to remain in situ poses significant technical, financial, and public liability challenges due to its categorised critical condition, plus factors such as operational confidence. Therefore, this option is not considered viable. Options for mitigation by either replacing the structural roof or redeveloping the site have been evaluated through an initial outline feasibility assessment.

Following the Cabinet meeting on 17th January 2024, it was confirmed that due to significant issues, including the presence of RAAC, the Civic Centre is beyond economic repair. Authority was delegated to the Assistant Director of Commercial Services to:

 Decommission and permanently close the building.  Establish a Working Group with Shropshire Council officers, local members, and Whitchurch Town Council to finalise the options appraisal for further approval by Cabinet/Council.  Provide interim solutions for library and community services and develop business cases for future library and customer service transformations in Whitchurch.  Collaborate with Whitchurch Town Council to find new civic accommodation.  Consult with Whitchurch Town Council and the local community before final decisions on the site's future are made.

It is recognised the facility provided many public services from Library to Civic and Community functions and contributed to the Healthy Economy of a vibrant destination and local infrastructure.

Contact: [email protected] 2 12/02/2025: Whitchurch Civic Centre & Library Reinforced Autoclave Aerated Concrete (RAAC)

2.5Following the public consultation outcomes provided to the Working Group and initial outline feasibility assessment the preferred options in the remediation of the RAAC are as follows:

Option 1 – Replacement of the structural RAAC roof, consequential works, and priority capital condition improvements – circa £4m.

Following the outline feasibility and further initial survey assessments confirmed the potential for replacement of the structural RAAC roof together with priority condition improvements needed to provide longevity and compliance. Further detailed design would be required to inform formal procurement, statutory permissions, and construction delivery of approximately twenty-four months from the date of approval and funding.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Whitchurch-Civic-Centre-consultation-report July 2024Appendix A 966 KB Download
PDF
Whitchurch Library & Civic Centre: Technical Overview and recommendationsAppendix B 11 MB Download
PDF
Whitchurch Library & Civic Centre: Feasibility Options Cabinet Nov 2024 rev.1Appendix C 9.6 MB Download
PDF
Whitchurch Civic Centre: Options AppraisalReport 906 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 19 attended
LP
Lezley PictonLeader, present
CM
Cecilia MotleyCommittee Member, present
IN
Ian NellinsDeputy Leader, present
RM
Robert MaceyCommittee Member, present
GB
Gwilym ButlerCommittee Member, present
DC
Dean CarrollCommittee Member, present
KH
Kirstie Hurst-KnightCommittee Member, present
MJ
Mark JonesCommittee Member, present
DM
Dan MorrisCommittee Member, apologies
CS
Chris SchofieldCommittee Member, present
AB
Andy BegleyOfficer, expected
JW
James WaltonOfficer, expected

All 19 on the meeting page

On this subject at Shropshire

Search all
  1. Whitchurch Civic Centre - Options AppraisalThis decision
  2. Whitchurch Civic Centre & Library - Asset DecisionApproved
  3. Whitchurch Civic Centre and Library - RAACNoted
  4. Whitchurch Civic Centre Asset TransferAgreed

More from Shropshire Cabinet

All decisions
MeetingDecisionOutcome
18 Nov 2026 MinutesThat the minutes of the meeting held on 14 October 2026 be confirmed as an accurate record. Decided Open
18 Nov 2026 Crisis & Resilience Fund – 6-month Progress UpdateThat Cabinet: 1. Endorsed the summary of the wider economic environment and the Council’s borrowings and investments ... Decided Open
18 Nov 2026 Council Tax Support - Proposed Changes 2027-28 Consultation ResponsesThat Cabinet: 1. Considered the responses received to the statutory consultation. 2. Agreed the following changes to ... Agreed Open
18 Nov 2026 Financial Monitoring Report Quarter 2 2026/27That Cabinet: A. Supported the Q2 favourable revenue outturn forecast of £0.051m. B. Supported the significant advers... Noted Open
18 Nov 2026 Treasury Management Update Quarter 2 2026/27That Cabinet: 1. Endorsed the summary of the wider economic environment and the Council’s borrowings and investments ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies