3.1. To note that the position set out in the report reflects the best information available after the first 4 weeks of the year and hence considerable uncertainty in these early estimates. 3.2. To note that at the end of Period 1 (30th April 2024), the indicative level of savings delivery is £24.974m (42%), resulting in a projected spend over budget of £13.884m for 2025/26. 3.3. To note the control corridor that the Council will be working to for 2025/26 is as follows: Adverse £39.700m overspend Central £13.884m overspend Favourable £1.422m overspend 3.4. To note the projected General Fund Balance of £0.393m for 31 March 2026 if the projected spend over budget is realised 3.1. To note that the position set out in the report reflects the best information available after the first 4 weeks of the year and hence considerable uncertainty in these early estimates. 3.2. To note that at the end of Period 1 (30th April 2024), the indicative level of savings delivery is £24.974m (42%), resulting in a projected spend over budget of £13.884m for 2025/26. 3.3. To note the control corridor that the Council will be working to for 2025/26 is as follows: Adverse £39.700m overspend Central £13.884m overspend Favourable £1.422m overspend 3.4. To note the projected General Fund Balance of £0.393m for 31 March 2026 if the projected spend over budget is realised
Word for word from the decision Shropshire published for this meeting.Source: www.shropshire.gov.uk
2.1The Council is producing a Financial Monitoring Report for Period 1 to provide an early view of the financial position that Shropshire Council will be managing this year, given the new budgetary savings in 2025/26, in addition to savings still to be delivered as part of a second year of delivery from 2024/25.
2.2The practicalities of producing a meaningful monitoring report from data up to 30 April requires a risk assessed approach to be taken with a focus on high level, material, and impactful financial information. Management action over periods 1 and 2 is listed below, ahead of a detailed quarter 1 (period 3) report being produced in the familiar format.
2.3The Period 1 Monitor cannot, of course, provide certainty. Its fundamental aim is to provide an early insight into whether the unprecedented actions being undertaken by the Council this year have the potential to secure financial survival, initially, and
Contact: James Walton [email protected] 1 Transformation & Improvement Scrutiny 9th June 2025; Cabinet 11th June 2025: Financial Monitoring Period 2025/26
then a path to financial sustainability.
2.4The key financial issues highlighted by this report are:
a) Savings of almost £60m are deliverable in-year including £7.7m of new proposals and £11m of demand mitigation measures across Social Care, both approved in the 2025 MTFS, and the balance of savings carried forward into year two of delivery from 2024/25. b) Projected savings delivery is currently estimated at £24.974m (42%) with a further £20.713m having at least indicative plans in place. c) A contingency, built into the General Fund Balance to mitigate against delayed delivery of savings and demand pressures in Adults and Children’s services of £20m. d) A resulting forecast spend variance over budget, taking into account savings delivery, contingency and other variances anticipated at Period 1, of £13.884m. e) An initial General Fund Balance of £34.277m (by combining the brought forward balance of £4.822m with the budgeted contribution to balances of £29.455m) less the assumed mitigation of £20m referred to above leaves a balance of £14.277m – close to the £15m MTFS planned balance. f) The initial forecast spend variance of £13.884m, however, could result in a general fund balance at the end of the year of £0.394m.
3. Recommendations It is recommended that Cabinet Members:
3.1Note that the position set out in the report reflects the best information available after the first 4 weeks of the year and hence considerable uncertainty in these early estimates.
3.2Note that at the end of Period 1 (30th April 2024), the indicative level of savings delivery is £24.974m (42%), resulting in a projected spend over budget of £13.884m for 2025/26.
3.3Note the control corridor that the Council will be working to for 2025/26 is as follows: Adverse £39.700m overspend Central £13.884m overspend Favourable £1.422m overspend
3.4Note the projected General Fund Balance of £0.393m for 31 March 2026 if the projected spend over budget is realised.
Contact: James Walton [email protected] 2 Transformation & Improvement Scrutiny 9th June 2025; Cabinet 11th June 2025: Financial Monitoring Period 2025/26
Report 4. Risk Assessment and Opportunities Appraisal
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.