Resolved
That the minutes of the meeting held on 26 June 2025 be approved as a true record and signed by the Chairman.
Audit Committee approved this item on Wednesday 16 July 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
That the minutes of the meeting held on 26 June 2025 be approved as a true record and signed by the Chairman.
1 Committee and Date
Audit Committee
16 July 2025
MINUTES OF THE AUDIT COMMITTEE MEETING HELD ON 26 JUNE 2025 10.00 AM - 12.50 PM
Responsible Officer: Michelle Dulson Email: [email protected] Tel: 01743 257719
Present Councillor Duncan Kerr (Chairman) Councillors Kate Halliday (Vice Chairman), Alan Holford and Carl Rowley
Independent Member: Jim Arnold
The Chairman thanked the previous members of the Audit Committee, and in particular the Chair, Brian Williams for his service to the Council. He requested that a letter of thanks be sent to former Councillor, Brian Williams from the new Committee for his long years of service to the Council.
5 Apologies for Absence / Notification of Substitutes
An apology was received from Councillor Myles-Hook. Councillor Holford substituted for him.
6 Disclosable Pecuniary Interests
Members were reminded that they must not participate in the discussion or voting on any matter in which they have a Disclosable Pecuniary Interest and should leave the room prior to the commencement of the debate.
7 Minutes of the previous meetings held on the 6 February 2025 and 22 May 2025
RESOLVED:
That the Minutes of the meetings of the Audit Committee held on the 6 February and 22nd May 2025 be approved as a true record and signed by the Chairman.
8 Public Questions
A public question had been received from [name removed]. [name removed] read his question, and the Executive Director of Resources (Section 151 Officer) provided the response on behalf of the Committee.
A full copy of the question and response provided are attached to the web page for the meeting. Minutes of Audit Committee held on 26 June 2025
9 Member Questions
There were no questions from members.
10 First line assurance: NWRR Management Update
The Committee received the report of the Assistant Director of Growth and Infrastructure which provided an update on actions taken to address the recommendations contained in the Internal Audit report and the review by the Council’s External Auditors, Grant Thornton.
The Assistant Director of Growth and Infrastructure reported that since the Audit Committee meeting in February 2025, 13 of the 18 recommendations had been fully implemented, 3 were partially implemented and only 2 remained outstanding. The outstanding recommendations related to project delivery/project plan. These had been considered in the current context of the project, which was currently paused, with appropriate action agreed to address them (set out in paragraph 7 of the report), depending on the outcome of the project. In conclusion, he reported that there had been a significant shift away from where the project had been in terms of governance and assurance and that there was a rationale around the outstanding recommendations.
In response to a query, the Assistant Director of Growth and Infrastructure confirmed that all scenarios were being considered, and risk assessed for all eventualities so there would be no detrimental impact on the project whether it went ahead or not. In response to a further query, the Assistant Director of Growth and Infrastructure explained the activities that were ongoing whilst the project was paused which included some very basic testing. The Section 151 Officer explained that expenditure for these activities was capped at just under £40m up until the 30 June and although these activities could continue beyond that date, the associated cost was significantly below that cap. All other costs associated with the project had stopped.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Minutes of the previous meeting held on the 26 June 2025Minutes | 277 KB | DownloadRead as text |
Follow Audit Committee at Shropshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Jul 2025 | Third line assurance: Internal Audit Plan 2025/26That the Committee considered and endorsed, with appropriate comment, the approach taken to create the proposed Inter... | Approved | Open |
| 16 Jul 2025 | Third line assurance: Pension Fund Audit Plan 2024/25That the contents of the report be noted. | Noted | Open |
| 16 Jul 2025 | Third line assurance: Annual review of Internal Audit, Quality Assurance and Improvement Programme (QAIP) 2024/25That the Committee considered and endorsed with appropriate comment, the conclusion that the Council employs an effec... | Agreed | Open |
| 16 Jul 2025 | Second line assurance: Annual Whistleblowing reportThat the contents of the report were considered and approved. | Approved | Open |
| 16 Jul 2025 | Second line assurance: Annual Treasury Reporti) To approve the actual 2024/25 prudential and treasury indicators in the report. ii) To note the annual treasury ma... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.