Shropshire Council
Audit & Governance Committee, Friday 26 September 2025 at 10.00am

Third line assurance: Internal Audit Performance Report and revised Annual Audit Plan 2025/26

Deferred Finance 1 paper

Audit & Governance Committee deferred this item on Friday 26 September 2025. Below is the council's own wording, with the papers it was decided on.

Item51

Resolved

To endorse the performance of Internal Audit against the 2025/26 Audit Plan. In response to the low assurance levels and fundamental recommendations, Members requested updates for the next meeting in relation to Short Breaks and Deferred payments.
Word for word from the decision Shropshire published for this meeting. Source: www.shropshire.gov.uk

Follow this further

Built from Shropshire's papers

What the report saysPro

Report to Audit & Governance Committee

Executive summary

2.1This report provides members with an update of work undertaken by Internal Audit in the first five and a half months of the approved internal audit plan for 2025/26.

2.2Nine reasonable, 12 limited and five unsatisfactory assurance opinions have been issued. The 26 final reports contained 175 recommendations, one of which was fundamental.

2.3This report proposes revisions in the coverage of planned activity for Shropshire Council, with an increase of 64 days from 1,208 days as reported in July 2025 to 1,272 days. Changes to the planned activity are required due to a successful recruitment campaign with a Senior Auditor joining the team from 21st July 2025 and a member of the team being on long term sick leave. Revisions to the plan are targeted to provide enough activity to inform an end of year opinion. The recruitment of an additional Senior Auditor has enabled the three audits requested

Contact: [email protected] 1 Audit and Governance Committee 26th September 2025; Internal Audit Performance 2025/26

at the July Committee meeting to be added to the plan, however due to overruns on audits and the long term absence of one team member additional work cannot be added at this time. Results of all audit works undertaken will be reported to the Audit Committee following completion and will contribute directly to the CAE year end opinion.

2.4Internal Audit continues to add value to the Council in its delivery of bespoke pieces of work, including sharing best practice and providing advice on system developments.

Recommendations

3.1The Committee is asked to consider and endorse, with appropriate comment: a) the performance of Internal Audit against the 2025/26 Audit Plan. b) Identify any action(s) it wishes to take in response to any low assurance levels and fundamental recommendations, brought to Members’ attention, especially where they are repeated.

Report 4. Risk Assessment and Opportunities Appraisal

4.1Delivery of a risk-based audit Internal Audit Plan is essential to ensuring the probity and soundness of the Council’s control, financial, risk management systems and governance procedures. Areas to be audited are identified following a risk assessment process which considers the Council’s risk register information and involves discussions with managers concerning their key risks. These are refreshed throughout the period of the plan as the environment (delivery risks) changes. In delivering the plan, the adequacy of control environments is examined, evaluated and reported on independently and objectively by Internal Audit. This contributes to the proper, economic, efficient and effective use of resources. It provides assurances on the internal control systems, by identifying potential weaknesses and areas for improvement, and engaging with management to address these in respect of current systems and during system design. Without this, failure to maintain robust internal control, risk and governance procedures creates an environment where poor performance, fraud, irregularity and inefficiency can go undetected, leading to financial loss and reputational damage.

4.2Provision of the Internal Audit Annual Plan satisfies the Accounts and Audit Regulations 2015, part 2, section 5(1) in relation to internal audit. These state that:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Third line assurance: Internal Audit Performance Report and revised Annual Audit Plan 2025/26Report 1.3 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 14 attended
DK
Duncan KerrCommittee Member, present
MM
Malcolm Myles-HookCommittee Member, present
RG
Rhys GrattonCommittee Member, apologies
MO
Mark OwenCommittee Member, present
DB
Duncan BorrowmanCommittee Member, present
CR
Carl RowleyCommittee Member, present
SR
Sharon Ritchie-SimmonsCommittee Member, apologies
KH
Kate HallidayCommittee Member, present
NL
Nigel LumbyCommittee Member, present
JA
Jim ArnoldCommittee Member, apologies
MD
Michelle DulsonDS Officer, present
BH
Barry HansonOfficer, present

All 14 on the meeting page

On this subject at Shropshire

Search all
  1. Third line assurance: Internal Audit Performance Report and revised Annual Audit Plan 2025/26This decision
  2. Third line assurance: Annual Assurance report of the Audit and Governance Committee to Council 2025/26Decided
  3. Third line assurance: External Audit, Shropshire Council and Shropshire County Pension Fund Audit PlansNoted
  4. Third line assurance: Internal Audit Performance ReportDecided
  5. Third line assurance: Report of the Internal Audit Review of Risk ManagementNoted
  6. Third line assurance: Internal Audit Performance Report and Revised Annual Audit Plan 2025/26Decided

More from Shropshire Audit & Governance Committee

All decisions
MeetingDecisionOutcome
15 Jul 2026 Minutes of the previous meeting held on the 25 June 2026That the Minutes of the meeting of the Audit & Governance Committee held on the 25 June 2026 be approved as a true re... Approved Open
15 Jul 2026 Second line assurance: Annual Treasury ReportTo approve the actual 2025/26 prudential and treasury indicators in this report. 2. To note the annual treasury manag... Approved Open
15 Jul 2026 Overall assurance: Annual Governance Statement and Code of Corporate Governance 2025/26to note the Draft Annual Governance Statement 2025/26 and Code of Corporate Governance. to request that external audi... Noted Open
15 Jul 2026 Second line assurance: Approval of the Council's Draft Statement of Accounts 2025/26To approve the draft Statement of Accounts. Approved Open
15 Jul 2026 Exclusion of Press and PublicThat in accordance with the provision of Schedule 12A of the Local Government Act 1972, Section 5 of the Local Author... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies