Improvement Plan

Decided Executive 2 papers

AI summaryShropshire Cabinet recommended the draft Improvement Plan and its governance to Council for consideration, with transformation resources aligned to the Medium Term Financial Strategy. [D]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedGovernance and resources aligned to the MTFS were recommended. [D]
MoneyNot stated
What happens nextCouncil consideration [D]The recommendations are for Council to consider. [D]
Who it affectsNot stated

What was decided

Cabinet reviewed and commented on the draft Improvement Plan and recommended it to Council.

Cabinet recommended the Plan governance arrangements to Council.

Cabinet recommended aligning the capacity and resources needed for transformation with the MTFS.

Why

The Council needed to respond to a financial emergency and forecast year end overspend that current resources could not mitigate. Report P11

The Plan links financial recovery with clear priorities, financial sustainability and the future shape of the Council. Report P25, P27, P34, P37

It also supports workforce excellence, customer service, good governance and continuous improvement. Report P20, P26, P40, P44

What happens next

Council will consider the recommended Plan, governance arrangements and resource alignment.

Delivery will use nine priority programmes, regular reporting, external challenge and committee scrutiny. Report P27, P44, P45, P47

Work includes a proposed balanced budget for 2026/27 and a revised Medium Term Financial Strategy. Report P53, P55

Options considered

  • Chosen: Recommend the draft Improvement Plan to Council. Cabinet reviewed and commented on the draft before recommending it.
  • Chosen: Recommend the Plan governance arrangements to Council. The Plan defines accountability, reporting, assurance and external challenge for delivery. Report P44, P45, P47
  • Chosen: Align transformation capacity and resources with the MTFS. This connects transformation support with medium term financial planning. Report P15, P49

Implications

  • Financial: The Plan seeks a balanced 2026/27 budget and a long term route away from Exceptional Financial Support. Report P24, P31, P55
  • Financial: Delivery may require existing activity to be reprioritised, savings capacity redeployed, or additional resources identified. Report P44
  • Governance: Cabinet recommended the Plan for Council consideration, while Overview and Scrutiny and Audit and Governance committees provide oversight. Report P45
  • Risk: Risks, interdependencies and impacts on residents will be monitored, with consultation where relevant. Report P44, P45
  • Equalities: Equality Impact Assessments are required for new policies, strategies and major service changes. Report P44
  • Staffing: The People Plan seeks better staff satisfaction, engagement, attendance, retention, training and performance. Report P40, P42
  • Legal: The Plan supports the Council's best value duty, statutory standards and compliance. Report P11, P20
  • Climate: Local Government Outcomes expected from April 2026 will cover climate and environment. Report P21

Who and where

  • Shropshire Council and its workforce Report P3, P26
  • Residents of Shropshire Report P3, P6
  • Customers and service users Report P20, P42
  • Elected members and councillors Report P11, P45
  • Partners, town and parish councils and communities Report P19, P21
  • Children and families Report P11, P21
  • Adult social care Report P16
  • People using temporary accommodation Report P16

Timeline

  • July 2025: The LGA Corporate Peer Challenge took place. Report P11
  • Sept 2025 to Mar 2026: Stringent financial management and discretionary spending oversight began. Report P53
  • 10th September 2025: Cabinet declared a financial emergency. Report P11
  • Oct 2025 to Feb 2026: Work to develop a proposed balanced budget for 2026/27 was scheduled. Report P53
  • 10th November 2025: The Improvement Board held its first meeting. Report P13
  • Dec 2025 to Mar 2026: Completion of the revised MTFS was scheduled. Report P55
  • Dec 2025 to Mar 2027: A pathway to reduce and exit EFS was scheduled. Report P55
  • 03/12/25: The draft was prepared for Cabinet consideration. Report P2

Plain English for the jargon

  • MTFS: The Medium Term Financial Strategy covering forecasts, pressures, risks, priorities and how those priorities are funded. [P15]
  • EFS: Exceptional Financial Support, used temporarily while the Council develops a route to financial stability. [P33][P55]
  • BOSS: Budget Oversight and Spend Strategy meetings used to review actual and forecast spending and savings. [P17][P53]
  • PMO: The Corporate Programme Management Office, covering monitoring, delivery support and programme standards. [P47]
  • KPI: A Key Performance Indicator used to show progress against the Plan's aims. [P9][P44]
  • SAO: Senior Accountable Officer, accountable for the outcomes of programmes within an improvement aim. [P45]
  • RDL: Responsible Delivery Lead, responsible for day to day delivery of programmes and projects. [P45]
  • Improvement Board: An externally chaired board providing advice, challenge and oversight of Plan delivery. [P13][P45]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8

Resolved

RESOLVED 3.1 To review, comment on, and recommend the draft (Appendix 1) to Council. 3.2 To recommend to Council the governance arrangements set out in the Plan. 3.3 To recommend to Council that the capacity and resources to support the delivery of transformation required through this plan will be aligned to the MTFS.
Word for word from the decision Shropshire published for this meeting. Source: www.shropshire.gov.uk

Follow this further

Built from Shropshire's papers

What the report saysPro

Report to Cabinet, 45 pages

APPENDIX 1

Draft for consideration by Cabinet 03/12/25

Improvement Plan Our Plan to become a financially sustainable council with clear priorities and a high performing workforce for the benefit of Shropshire and its residents

November 2025

Draft Foreword from the Leader and Interim Chief Executive

The Council needs to improve. And we need to demonstrate to our residents, partners, and the Government that we are doing so with urgency. To deliver, enable and influence for the county, the Council needs to quickly get better at managing its finances, be clearer on its priorities, and continue to support our workforce to excel. This Plan sets out how we will do that. It shows our commitment to address immediate challenges, while ensuring a focus on the future and how the Council will need to look, feel, and operate to best serve the needs of the county and its residents, and being aware of changes in national policy. ​We have a serious financial position to address. There is an immediate focus on that. But improvement is not just about fixing problems; it is about creating opportunities. Through this Plan, we will also strengthen our culture, invest in our people, and embed practices that drive continuous improvement. In doing so we will be better equipped to deliver our commitments to residents. Our ambition is to be a council that is modern, efficient and sustainable —one that operates effectively, works in partnership, stays focused on residents, and is clear on its role and purpose. This Plan provides the framework for achieving that ambition. It outlines the priorities we will focus on, the changes we need to make, and the governance and assurance arrangements that will keep us on track. We will measure progress transparently, manage risks proactively, and ensure resources are aligned to deliver the outcomes our communities need and expect. An Improvement Board, supported by the Local Government Association (LGA), will provide expert peer challenge and support, while holding us to account for delivery of the Plan. Delivering the Plan will be a collective effort. Success will depend on collaboration across teams and with partners, strong leadership, and a shared determination to make a positive difference. Together we will build a council that is not only better than today but ready for the challenges and opportunities of tomorrow. Sitting alongside a new Corporate Plan 2026-30, Shropshire 2050 Plan, and Medium-Term Financial Strategy, it forms part of our overall Shropshire Plan that sets out the strategic priorities and purpose of the Council, and the improvement and resources needed to achieve those.

Councillor Heather Kidd Tanya Miles Leader of Shropshire Council Interim Chief Executive, Shropshire Council Contents

Section Purpose Page 1. Introduction This section explains the purpose of the Plan, sets out the context for the Council’s improvement, and the 4 relationship between this Plan and other strategic documents such as the Corporate Plan. 2. Our Future Council This section summarises how the Council continues to change how it looks, feels and operates, so that 9 improvement is focused on the future council and context as well as responding to current challenges and issues. 3. Our Improvement Aims and Priorities This section sets out our overall aims and priorities for improvement, and the outcomes and benefits we 13 are looking to achieve. It provides the structure used to organise our improvement activities, governance and reporting. 4. Making sure we deliver: This section provides a summary of the arrangements that provide assurance we are delivering the Plan. 19 • Governance & Assurance It sets out how the Council will support the delivery of the Plan and summarises the engagement and • Enabling & Supporting communications that has helped to shape the Plan’s development and delivery. • Engagement and Communications

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Improvement PlanReport 45 pages DownloadRead as text
PDF
Improvement Plan-03112025 1107Report 10 pages Download

At this meeting

Whole meeting

On this subject at Shropshire

Search all
  1. Improvement PlanThis decision
  2. Improvement Plan - Progress ReportNoted
  3. Improvement PlanAgreed
  4. Children's Social Care Improvement PlanApproved
  5. Air Quality Action Plan review and improvement interventionsDeferred
  6. Shifnal Town Centre Improvement and Transport PlanApproved

More from Shropshire Cabinet

All decisions
MeetingDecisionOutcome
18 Nov 2026 MinutesThat the minutes of the meeting held on 14 October 2026 be confirmed as an accurate record. Decided Open
18 Nov 2026 Crisis & Resilience Fund – 6-month Progress UpdateThat Cabinet: 1. Endorsed the summary of the wider economic environment and the Council’s borrowings and investments ... Decided Open
18 Nov 2026 Council Tax Support - Proposed Changes 2027-28 Consultation ResponsesThat Cabinet: 1. Considered the responses received to the statutory consultation. 2. Agreed the following changes to ... Agreed Open
18 Nov 2026 Financial Monitoring Report Quarter 2 2026/27That Cabinet: A. Supported the Q2 favourable revenue outturn forecast of £0.051m. B. Supported the significant advers... Noted Open
18 Nov 2026 Treasury Management Update Quarter 2 2026/27That Cabinet: 1. Endorsed the summary of the wider economic environment and the Council’s borrowings and investments ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies