Council, Thursday 11 December 2025 at 10.00am

Shirehall Strategic Review

Approved Committee 1 paper

AI summaryShropshire Council will pursue mixed use outline planning for Shirehall, target an application in early 2026 and seek to extend the Certificate of Immunity [D]. It will also complete masterplan options and a business case; best case holding costs are £374,650 per annum [5.3].

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedOutline permission, engagement, business case and Certificate of Immunity extension [D]
MoneyHolding costs £374,650 per annum [5.3]Best case scenario [5.3]
What happens nextApplication targeted for early 2026 [D]Public engagement, business case, immunity request and site review [D]
Who it affectsNot stated

What was decided

The Council amended its December 2023 direction. It will instead pursue Option 11, progress a mixed use outline planning application, initiate public engagement and submit the application in early 2026.

Further masterplan work will cover healthcare, affordable supported living, commercial and residential elements. A business case will be prepared and finalised for a future Council meeting. Report 3.2

The Council approved seeking an extension to the Certificate of Immunity and delegated progress on items 1 to 3 to the Head of Property and Development, in consultation with the Portfolio Holder for Finance and the Portfolio Holder for Transport and Economic Growth. It also set up a Task and Finish Group to consider all options for the site. Report 3.3, 3.4

Why

The review said refurbishment appeared unfeasible because of high capital costs, restricted funding, structural issues, asbestos, building inefficiencies and limited demand for office space. The 2025 estimate was £54.561 million. Report 2.14, 5.6

Cabinet declared a financial emergency on 10th September 2025, requiring significant expenditure reductions and difficult choices. Shirehall was substantially vacant, with final document archives being cleared, and incurred significant annual costs, so savings and financial returns were important to the choice. Report 2.7, 2.9

The review judged Option 11 to address acute housing and care needs, support economic activity and align with local and national policy. Outline planning would preserve a fully residential fallback if mixed use proved unviable, and the flexible approach could support external funding. Report 2.9, 2.18, 2.20

What happens next

Progress the mixed use outline planning application, initiate public engagement and submit the application in early 2026. Report 2.19, 3.1

Complete additional masterplan options, and prepare and finalise a business case for consideration at a future Council meeting. Report 3.2, 7.11

Submit the request to extend the Certificate of Immunity, with proactive liaison with Historic England. The Task and Finish Group will consider all options for the site. Report 3.3, 4.5

The money

  • £54.561 million Estimated 2025 cost of refurbishing Shirehall to modern standards Report 5.6
  • £374,650 per annum (£31,220.83 per month) Best case scenario holding costs Report 5.3
  • £695,415 per annum Business rates Report 5.3
  • £348,660pa Business rates after mitigation Report 5.3
  • £8,240 per annum Insurance Report 5.3
  • £17,750 per annum Limited ongoing services Report 5.3
  • £530,000pa Budgeted Guildhall running costs Report 5.4
  • £400,000 Approximate combined annual savings from Guildhall running costs and Shirehall holding costs Report 5.4

Options considered

  • Chosen: Option 11. Demolish Shirehall for a mixed tenure housing scheme, extra care facilities and commercial space. It had no listed disadvantages and was judged to address acute housing and care needs. Report 2.9, 7.6, P74
  • Rejected: Option 10. Demolish Shirehall for a mixed tenure housing scheme. It was shortlisted and had no listed disadvantages, but the Council selected the broader mixed use option. Report 7.6, P72
  • Rejected: Options 3 to 5. Refurbish Shirehall for commercial or leisure uses. High capital costs, restricted funding, structural issues, asbestos, inefficient design, weak tenant demand and poor strategic fit ruled these out. Report P70
  • Rejected: Option 6. Convert Shirehall to residential accommodation. Extremely high costs, restricted funding, design challenges and fewer units than a new build made it undeliverable. Report P70, P72
  • Rejected: Options 7 to 9. Demolish Shirehall for new office, leisure or retail space. High capital costs, restricted funding, uncertain demand and strategic fit concerns led to rejection. Report P72
  • Rejected: Option 1. Do nothing and leave the site undeveloped. Ongoing security and maintenance costs, lost short term economic opportunities and antisocial behaviour risks led to rejection. Report P68
  • Rejected: Option 2. Sell the building and site in its existing condition. Although it could produce an immediate capital receipt, it offered less control, uncertain buyer availability and possible conflict with the Council's strategic aims. Report P68

Implications

  • Financial: The business case will assess the capital receipt and possible long term income against likely investment and borrowing. A disposal receipt is included in the Council's capital receipts projections for 2026/27. Report 7.11, 5.5
  • Legal: The existing Certificate of Immunity expires on 16 September 2026, and failure to secure an extension could restrict redevelopment options. Report 4.5
  • Risk: Planning delays could increase costs and heritage listing risk, while market and construction cost uncertainty could affect viability. Insufficient engagement could create opposition and reputational risk. Report 4.2, 4.3, 4.4
  • Equalities: The scheme includes affordable and specialist extra care units, which the report says support an ageing population, housing shortages, downsizing and better living standards for residents moving from substandard accommodation. Report 2.10, P72, P74
  • Climate: The masterplan is expected to use modern efficient design, renewable energy, carbon mitigation, sustainable drainage, flood risk management and resilient landscaping. Report 6.1, 6.2, 6.3, 6.4
  • Staffing: The final archive relocation phase may require further financial and people resources and allocation of Council records to an alternative location. Report P44
  • Other: Cornovii Development Limited is paying all associated planning and masterplanning costs. It may later bid for the site through an open market sales process after planning consent is obtained. Report 2.3, 7.4

Who and where

  • Shropshire Council
  • The Shirehall building and site Report P8
  • People needing affordable or specialist homes Report 2.10
  • Older people needing extra care Report 2.10, 7.10
  • The NHS and prospective GP practices Report 2.17, 8.2
  • Local businesses and workers Report 2.10
  • Telecommunications operators and people relying on mobile coverage Report 5.7
  • Cornovii Development Limited Report 2.3, 7.4

Timeline

  • September 2021: The current Certificate of Immunity was granted.
  • December 2023: The Council decided to seek full residential planning permission for the site. Report 3.1
  • September 2024: The Council vacated Shirehall and relocated to the Guildhall. Report 2.3, 7.3
  • July 2025: Cabinet paused the redevelopment process for a review of available options. Report 2.4, 7.5
  • 10th September 2025: Cabinet declared a financial emergency.
  • December 11th 2025: Council approved the revised Shirehall strategy. Report P3
  • early 2026: The mixed use planning application is targeted for submission. Report 3.1
  • 16 September 2026: The current Certificate of Immunity is due to expire.

Plain English for the jargon

  • Certificate of Immunity (COI): A status that prevents the building being designated as a heritage asset, with the current certificate due to expire on 16 September 2026 [8.1].
  • Option 11: Demolition of Shirehall for a mixed tenure housing, extra care and commercial development [7.6] [P74].
  • Outline planning permission: Consent for the broad form of a development while keeping the final design flexible [2.16] [2.20].
  • Mixed tenure: Residential accommodation described as mixed tenure, including affordable and specialist extra care units [2.10].
  • Extra care: A care facility for older people, with a possible 100 bed model considered [7.10].
  • Mixed use: A development combining office, medical practice, mixed tenure residential and commercial uses [2.16].
  • Task and Finish Group: A group set up to consider all options for the Shirehall site [D].
  • Financial emergency: A declaration that constrained decision making and required significant expenditure reductions [2.1] [5.1].
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item68

Resolved

RESOLVED That Council 1. Amend their previous decision (December 2023) to seek full residential planning permission. Instead, pursue Option 11, progress a mixed-use outline planning permission, initiate public engagement, and submit the application in early 2026. 2. Completes additional masterplan options for a mixed-use development incorporating healthcare, affordable supported living, commercial, and residential elements. Prepare and finalise a business case for consideration by Council at a future meeting. 3. Approves the submission of a request to extend the Certificate of Immunity from Listing for the Shirehall site. 4. Delegates authority to the Head of Property and Development to progress items 1 to 3 in consultation with the Portfolio Holder for Finance and the Portfolio Holder for Transport & Economic Growth 5. Sets up a Task and Finish Group to consider all options for the site
Word for word from the decision Shropshire published for this meeting. Source: www.shropshire.gov.uk

Follow this further

Built from Shropshire's papers

What the report saysPro

Report to Council, 14 pages

December 11 th, 2025, | Shirehall Strategic Review

Council Item

December 11th 2025

Public

Shirehall Strategic Review Responsible Officer: Richard MacDonald Steve Law

email: [email protected] Tel: 01743 252 736 [email protected] 01743 281 017

Cabinet Member (Portfolio Holder): Councillor Roger Evans

1. Synopsis This paper presents the strategic review of the Shirehall site, Abbey Foregate, Shrewsbury. The review evaluates future options for the now vacant Shirehall building and site, with the objective of transforming a costly liability into a sustainable, high-value asset for the benefit of Shropshire’s residents. Due to Shropshire Council's financial emergency declared in September 2025, all cost-cutting options that reduce revenue burden are under review. The recommended way forward is to pursue a mixed-use redevelopment, maximising public value and aligning with both local needs and national policy.

2. Executive Summary 2.1. On 10th September 2025, Cabinet declared a financial emergency. This has placed significant constraints on future decision making and means very difficult choices are required by the authority. This has a direct bearing on considering the options set out within this report. The Council needs to reduce expenditure and deliver the best options for income and/or return on capital.

2.2The Council has put in place an Improvement Board the purpose of which is to provide independent advice, challenge, and assurance on the Council’s improvement and transformation journey following the declaration of a financial emergency. Its core objectives are to oversee and monitor the delivery of the Improvement Plan, ensuring that actions are implemented at pace and have the intended impact. Contact: [email protected] | [email protected] 1 December 11 th, 2025, | Shirehall Strategic Review

2.3The Shirehall redevelopment aligns with The Shropshire Plan’s healthy priorities, supporting regeneration, community wellbeing, and sustainable development. Shropshire Council has vacated the Shirehall due to operational and safety concerns, appointed Cornovii Development Limited (CDL) to support planning, and lead master planning for the site as was approved in the previous Council report dated December 2023. The Council’s decision to vacate the building was made at full Council in September 2024.

2.4This report presents the findings and recommendations of the Shirehall Strategic Review, undertaken to determine the optimal future use of the Shirehall and the site, following a pause in July 2025 to give Cabinet the opportunity to review the process and preferred outcomes.

2.5In addition to this report an exempt report has been put forward for consideration in the exempt session of the Council meeting.

2.6Commercial information has been withheld from this report in accordance with paragraph 10.4, Category 3 of the Council’s Access to Information Procedure Rules, to protect sensitive business interests, avoid distorting the market, and prevent any disadvantage to the financial interests of the authority.

2.7Following the Council’s decision to vacate the building in September 2024, Shirehall now stands as a substantially vacant asset (with final document archives currently being cleared) incurring significant annual costs and presenting both challenges and opportunities for Shropshire Council.

2.8A comprehensive options appraisal has been conducted, considering a range of scenarios including retention, refurbishment, sale, and redevelopment for various uses. The appraisal was guided by three core objectives: to meet the needs of the local population, to minimise environmental impact, and to maximise public value.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Shirehall Strategic ReviewReport 14 pages DownloadRead as text

More from Shropshire Council

All decisions
MeetingDecisionOutcome
14 May 2026 Election of ChairmanRESOLVED that Councillor Duncan Barrowman be elected as Chairman of Shropshire Council to hold office until the Annua... Decided Open
14 May 2026 Appointment of Vice ChairmanRESOLVED that Councillor Gary Groves be appointed as Vice-Chairman of Shropshire Council to hold office until the Ann... Decided Open
14 May 2026 MinutesThat the of the meeting held on 26 February 2026, as circulated with the agenda papers, be approved and signed as a c... Approved Open
14 May 2026 Scrutiny Reorganisation/Housing Supervisory BoardThat the Housing Supervisory Board be removed from the Constitution. 2. That the Scrutiny Committees and their terms ... Approved Open
14 May 2026 Constitution of Committees and Allocation of Seats to Political GroupsThat the Council confirms the constitution of committees and the allocation of seats to each of the political groups ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies