CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Shropshire Council
Northern Planning Committee, Tuesday 17 February 2026 at 2.00pm

Proposed Residential Development Land on the West side of Ellesmere Road, Shrewsbury, Shropshire (22/01432/OUT)

Deferred Planning 1 paper

AI summaryShropshire Council's Northern Planning Committee defers a 450-home outline application on land west of Ellesmere Road, Shrewsbury, to get assurance on active travel and wider transport network impact.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDeferredPending further information on travel and transport
MoneyS106 contributions proposed£1,250 per dwelling, £25,000 per retail unit
What happens nextOfficers to seek clarificationOn active travel and Shrewsbury Moves Vision
Who it affectsNorth Shrewsbury areaLand west of Ellesmere Road, near Greenfields

What was decided

The committee deferred determining application 22/01432/OUT, against the officer recommendation to delegate approval subject to a Section 106 agreement and conditions. Report P13

The deferral is to seek assurance on active travel options, including how residents could access existing schools to the north of Shrewsbury.

The committee also asked for further clarification on the impact on the wider transport network, including pinch points and how the modelling fits with the Shrewsbury Moves Vision and Plan.

Why

Officers had recommended delegated approval, supported by the local highway authority's view that 450 dwellings could proceed before the North West Relief Road without significant transport impact. Report P13, P41, P42

Active Travel England had formally asked for deferral, citing shortcomings in the Transport Assessment, weak targets for walking, wheeling and cycling, and the need for off-site active travel upgrades. Report P67, P68, P69, P70

Shrewsbury Town Council and 114 of 116 public representations objected, with concerns including Ellesmere Road congestion, school and GP capacity, the Old River Bed SSSI, and uncertainty over the North West Relief Road. Report P78, P79, P80, P84, P88

What happens next

Officers will return to the committee with further information on active travel options and the scheme's fit with the Shrewsbury Moves Vision and Plan, including modelled pinch points on the wider network.

The application will be reconsidered at a future meeting of the Northern Planning Committee once the requested information is available.

The money

  • £1,250 per dwelling Section 106 transport contribution Report P229
  • £25,000 per retail unit Section 106 transport contribution Report P229
  • £1,500 per pole On-site transport infrastructure rate Report P230
  • £10,000 per bus shelter On-site transport infrastructure rate Report P230
  • £6,000 per real time display On-site transport infrastructure rate Report P230
  • £150 per dwelling Local interchange contribution Report P230

Options considered

  • Rejected: Delegate approval to officers, subject to Section 106 agreement and conditions (officer recommendation). Committee sought further information on active travel and transport network impact Report P13
  • Chosen: Defer to seek further clarification on active travel and wider transport impact. To address Active Travel England's deferral request and committee concerns on travel and network pinch points Report P67, P70

Implications

  • Risk: The local highway authority accepted 450 dwellings pre-North West Relief Road, but Active Travel England disagreed and the committee wants modelled pinch point evidence. Report P41, P42, P67, P68
  • Other: The site is outside the Shrewsbury development boundary and not allocated in the adopted plan; the council cannot demonstrate a five-year housing land supply, so the NPPF tilted balance applies. Report P118, P119, P122, P145
  • Equalities: Developer contributions are sought for education (SC Learning and Skills) and healthcare (Integrated Care Board, around 1,080 additional patients expected). Report P50, P55, P56, P57

Who and where

  • The applicant, Barwood Development Securities Ltd Report P9
  • Shrewsbury Town Council, which objected Report P77, P78
  • Existing residents of Greenfields and nearby streets including Ellesmere Road, Cedars Drive, Winney Hill View, Juniper Road and Hencote Lane Report P88, P90, P97, P179
  • Users of Public Rights of Way to the north and north-west of the site Report P180
  • Local schools, GP surgeries and bus passengers, given concerns about capacity Report P80, P91

Timeline

  • 2022: Application 22/01432/OUT submitted with original Transport Assessment and Travel Plan Report P40
  • June 2021: Screening Opinion issued confirming no Environmental Impact Assessment required Report 1.4, 1.5
  • October 2025: Technical Note 05707-T-002 submitted assessing full 450-dwelling build-out prior to the North West Relief Road Report P41
  • 17 February 2026: Northern Planning Committee defers the application for further information on active travel and transport impact

Plain English for the jargon

  • NWRR: North West Relief Road, a proposed road scheme for northern Shrewsbury
  • NPPF: National Planning Policy Framework
  • CIL: Community Infrastructure Levy
  • S106: Section 106 agreement, a planning obligation for developer contributions
  • BNG: Biodiversity Net Gain
  • SuDS: Sustainable Drainage Systems
  • SSSI: Site of Special Scientific Interest
  • LWS: Local Wildlife Site
  • ATE: Active Travel England, a government body promoting walking, wheeling and cycling
  • SAMDev: Site Allocations and Management of Development Plan, part of the Shropshire development plan
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item66

Resolved

That determination of the application be deferred: · To seek assurance in relation to active travel options, including options to access existing schools to the north of Shrewsbury; and · Further clarification on the impact on the wider transport network, including pinch points and how the modelling fits in with the Shrewsbury Moves Vision and Plan
Word for word from the decision Shropshire published for this meeting. Source: www.shropshire.gov.uk

Follow this further

Built from Shropshire's papers

What the report saysPro

Report to Northern Planning Committee

Committee and date

Northern Planning Committee

17th February 2025

Development Management Report Responsible Officer: Tim Collard, Service Director – Legal, Governance and Planning

Summary of Application

Application Number: 22/01432/OUT Parish: Shrewsbury Town Council

Proposal: Outline application for the residential development of up to 450 dwellings, strategic infrastructure to include: open space, drainage and engineering works with some matters (landscaping, appearance, layout, scale) reserved apart from strategic access.

Site Address: Proposed Residential Development Land on the West side of Ellesmere Road, Shrewsbury, Shropshire

Applicant: Barwood Development Securities Ltd

Case Officer: Ollie Thomas email: [email protected]

Grid Ref: 349164 - 314609

© Crown Copy right. All rights reserv ed. Shropshire Council AC0000808715. 2025 For ref erence purposes only . No f urther copies may be made. Northern Planning Committee – 17 February 2026 Proposed Residential Development Land On The West Side Of

Recommendation: - That delegated authority is given to Officers to grant planning permission subject to the completion of a Section 106 agreement and the conditions in Appendix 1 and for any minor changes to conditions as required.

REPORT

1.0THE PROPOSAL

1.1This application is seeking outline planning permission with access matters only to be considered concurrently (layout, scale, appearance and landscaping reserved for subsequent approval) and is supported by an Illustrative Framework Masterplan (‘the Masterplan’) to demonstrate how the proposed development could be delivered and responding to the site’s constraints, whilst meeting policy requirements. The Masterplan shows the development as providing:

- Up to 450 residential dwellings – ranging from 2-bed to 5-bed; - 10% affordable housing - A Local Centre measuring 0.25 hectares - Vehicle, pedestrian and cycle provisions - Green infrastructure, including play areas and landscaping. Northern Planning Committee – 17 February 2026 Proposed Residential Development Land On The West Side Of

The Illustrative Masterplan will be delivered across two phases: Phase 1 – 150 dwellings at approx. 35 dwellings per hectare (dph); and, Phase 2 – 300 dwellings at 35dph.

1.2As this application is submitted in Outline with access only, the submitted Design and Access Statement demonstrates that an appropriate and policy-compliant design framework can be achieved at Reserved Matters stage. The Masterplan shows that the development can be sensitively designed within the settlement edge, with a permeable street hierarchy, a legible movement network, and substantial green infrastructure that responds to site constraints including topography, existing vegetation, flood zones and proximity of the Old River Bed.

1.3The application site was identified as a draft allocation (SHR173) in the former Draft Northern Planning Committee – 17 February 2026 Proposed Residential Development Land On The West Side Of

Local Plan, which sought to deliver a comprehensive sustainable residential development for 450 dwellings, with access off Ellesmere Road and subject to an agreed Masterplan that reflects the objectives of the Big Town Plan. The Draft Local Plan has since been withdrawn from Examination and is no longer a material consideration. However, the evidence base underpinning remains a material consideration at a weight to be applied by the decision-maker and relevant to the merits of the application.

1.4The proposed development has been subject to a Screening Opinion (Ref: 21/02537/SCR), whereby it is the opinion of the LPA that having taken into account the scale, nature and location of the development it will not result in likely significant environmental effects and therefore does not need to be dealt with through the Environmental Impact Assessment (EIA) Regulations.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Proposed Residential Development Land on the West side of Ellesmere Road, Shrewsbury, Shropshire (22/01432/OUT)Report 962 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 12 attended
JD
Julian DeanChairman, present
MO
Mark OwenVice Chairman, present
AD
Andy DavisCommittee Member, present
RD
Rosemary DartnallCommittee Member, present
GE
Greg EbbsCommittee Member, present
BE
Brian EvansCommittee Member, apologies, sent representative
AF
Adam FejferCommittee Member, present
GG
Gary GrovesCommittee Member, present
EP
Ed PotterCommittee Member, apologies
RR
Rosie RadfordCommittee Member, apologies
CR
Carl RowleyCommittee Member, present
BM
Brendan MallonSubstitute, apologies, sent representative

On this subject at Shropshire

Search all
  1. Proposed Residential Development Land on the West side of Ellesmere Road, Shrewsbury, Shropshire (22/01432/OUT)This decision
  2. Proposed Residential Development Land Between Aston Road and Church Lane, Wem, Shropshire. (25/02775/OUT)Deferred
  3. Proposed Residential Development Land To The West Of Crosemere Crescent Cockshutt Shropshire (25/04083/FUL)Decided
  4. Proposed Residential Development NW Of Kingfisher Way Morda Shropshire (26/00772/FUL)Decided
  5. Proposed Residential Development Land East of Ford Shrewsbury Shropshire (25/04301/FUL)Refused
  6. Proposed Residential Development Land Off Benthall Lane And Bridge Bank Benthall Broseley Shropshire (25/03946/OUT)Decided

More from Shropshire Northern Planning Committee

All decisions
MeetingDecisionOutcome
21 Jul 2026 MinutesThat the of the meeting of the North Planning Committee held on 21 st April and 14 th May 2026 be approved as a corre... Approved Open
21 Jul 2026 Proposed Residential Development Land Between Aston Road and Church Lane, Wem, Shropshire. (25/02775/OUT)Deferred by the Development Manager, in consultation with Legal, under 17.4 of the Local Protocol for Councillors and... Deferred Open
21 Jul 2026 Proposed Residential Development Land To The West Of Crosemere Crescent Cockshutt Shropshire (25/04083/FUL)To delegate authority to officers to grant planning permission, subject to further investigation for options to impro... Decided Open
21 Jul 2026 Proposed Residential Development NW Of Kingfisher Way Morda Shropshire (26/00772/FUL)That Planning Permission be granted subject to the conditions set out in Appendix 1 of the report Decided Open
21 Jul 2026 Application to Register The Glebelands, Bayston Hill as a Village GreenThat an independent barrister be appointed to act as an Inspector to undertake, if necessary, a non-statutory public ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies