AI summaryShropshire Cabinet approved the Local Nature Recovery Strategy, subject to Telford and Wrekin Council's parallel decision on 26th March 2026. The strategy sets 16 priorities and 51 actions for nature recovery and will then be notified to the Secretary of State.
Written from the decision and the officer reportPDF Pro
OutcomeNotedSubject to Telford and Wrekin Council approval
MoneyNot specifiedDefra grant funded development
What happens nextNotify Secretary of StateAfter Telford and Wrekin Council approval
Who it affectsLandowners, farmers, communitiesAcross Shropshire and Telford and Wrekin
What was decided
Cabinet approved the Local Nature Recovery Strategy, subject to parallel approval by Telford and Wrekin Council, and delegated to the Service Director for Strategy and Change the authority to make minor amendments, in consultation with the Portfolio Holder for Planning, before publication and notification to the Secretary of State. Report P12
Cabinet noted the work of the LNRS Steering Group and stakeholders in supporting coordinated biodiversity action to enable nature recovery across Shropshire. Report P12
Why
The strategy is a statutory requirement under section 104 of the Environment Act 2021, and Shropshire Council was appointed Responsible Authority by Defra to produce it. Report 2.2, 4.1
A Defra panel assessed the strategy on 17th December 2025, and Natural England confirmed in a letter on 22nd December 2025 that the strategy was sound, comprehensive and approved for publication subject to minor amendments, all of which have been made. Report 2.6, 7.12, 7.14
Public consultation from 6th August to 15th October 2025 received 3,782 comments, thought to be the largest response for any LNRS area in England. Report 2.5, 7.10
What happens next
Telford and Wrekin Council Cabinet will consider the strategy for approval on 26th March 2026. Report 2.6, 9.4
After parallel adoption, Shropshire Council, as the Responsible Authority, will notify the Secretary of State of the publication date. Report 2.7, P47
On publication the strategy enters its delivery phase, supported by Defra's emerging national monitoring framework and continued partnership working through the Steering Group. Report 8.2
Options considered
Chosen: Approve the LNRS subject to Telford and Wrekin Council's parallel approval and delegate minor amendments to the Service Director for Strategy and Change. Required by the Environment Act 2021; supported by Natural England's assessment and the Defra panel Report P12, 2.6, 7.14
Rejected: Do not approve the LNRS for publication at this stage. Risks delay to publication, lost funding opportunities and postponement of nature recovery work Report P18, 4.3
Implications
Legal: Adoption fulfils Shropshire Council's duties as Responsible Authority appointed by Defra under section 104 of the Environment Act 2021 and the 2023 Procedure Regulations. Report 4.1, 7.3, 7.4
Financial: A Defra grant covered the full costs of producing the strategy, and further funding for delivery has been announced through integrated settlements; future Section 31 grants are expected but details are awaited. Report 2.8, 5.1
Climate: The strategy supports the Council's Climate Change and Carbon Reduction work through carbon capture, local cooling, flood prevention, air and water quality improvements and water conservation. Report 6.2
Risk: Not publishing in a timely manner could move the strategy outside Defra's publication window, absorb officer time, and delay nature recovery and access to funding. Report 4.3, P18
Other: The strategy does not impose new obligations or designations on landowners; it is intended to focus funding and support, not to regulate land use or planning. Report 2.4, P21
Who and where
Landowners and farmers across Shropshire and Telford and Wrekin Report 2.4, P21, 7.7
Shropshire Council as the Responsible Authority appointed by Defra Report 2.2, 4.1, 7.4
Telford and Wrekin Council as a Supporting Authority Report 2.3, 7.4, 7.16
Natural England as a Supporting Authority Report 2.3, 7.4
Shropshire Wildlife Trust and Shropshire Hills National Landscape Report 2.3, 7.5
Environment Agency, Forestry Commission, Country Land and Business Association and National Farmers Union Report 2.3, 7.5
Timeline
September 2024: Stakeholder and public engagement events began across Shropshire Report 7.9
6th August 2025: Draft LNRS public consultation opened Report 2.5, 7.9
15th October 2025: Public consultation closed after receiving 3,782 comments Report 2.5, 7.10
17th December 2025: Updated LNRS presented to the Defra panel for assessment Report 2.6, 7.12
22nd December 2025: Natural England letter confirmed the strategy was approved for publication subject to minor amendments Report 2.6, 7.12
11th March 2026: Shropshire Council Cabinet approved the LNRS
26th March 2026: Telford and Wrekin Council Cabinet to consider the LNRS for approval Report 2.6, 9.4
Plain English for the jargon
LNRS: Local Nature Recovery Strategy, a statutory plan under the Environment Act 2021 setting out priorities for biodiversity and habitat restoration.
Responsible Authority: The council appointed by the Secretary of State to prepare and publish the LNRS, here Shropshire Council.
Supporting Authority: Bodies designated under the 2023 Procedure Regulations to support the Responsible Authority, here Telford and Wrekin Council and Natural England.
Defra: Department for Environment, Food and Rural Affairs, the UK government department responsible for the LNRS programme.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item148
Resolved
That Cabinet: a. Noted the work of the (LNRS) Steering Group and stakeholders in supporting co-ordinated biodiversity action, to enable nature recovery across Shropshire. b. Approved the LNRS Strategy (subject to parallel approval by Telford and Wrekin Council) and delegated to the Service Director for Strategy & Change, the authority to make minor amendments to the Strategy, in consultation with the Portfolio Holder for Planning, prior to publication and notification to the Secretary of State as required. That Cabinet: a. Noted the work of the ( LNRS ) Steering Group and stakeholders in supporting co-ordinated biodiversity action, to enable nature recovery across Shropshire. b. Approved the LNRS Strategy (subject to parallel approval by Telford and Wrekin Council) and delegated to the Service Director for Strategy & Change, the authority to make minor amendments to the Strategy, in consultation with the Portfolio Holder for Planning, prior to publication and notification to the Secretary of State as required.
Word for word from the decision Shropshire published for this meeting.Source: www.shropshire.gov.uk
Contact: Matthew Farmer [email protected] 1 Cabinet 11th March 2026 - Local Nature Recovery Strategy
2.1The Shropshire and Telford & Wrekin Local Nature Recovery Strategy (LNRS) comprise two core components: a written strategy and a spatial map identifying both the existing nature network and the opportunity network. Both components identify priorities for the restoration of biodiversity across the historic county of Salop.
2.2The LNRS is a requirement of the Environment Act 2021 and Shropshire Council was appointed the Responsible Authority by Defra to produce this. A Steering Group has guided its development and significant stakeholder engagement has shaped its formation and contents.
2.3The Steering Group comprises Shropshire Council, Telford & Wrekin Council, Natural England, Country Land and Business Association (CLA), Environment Agency, Forestry Commission, National Farmers Union, Shropshire Wildlife Trust, Shropshire Hills National Landscape. Many local species experts sat on the species sub-group.
2.4The purpose of the LNRS is to help focus funds and resources for nature recovery action. It is not obligating action, and it does not bring additional protections to land. Using ecological evidence, the LNRS identifies 16 local priorities and 51 actions to restore habitats, enhance ecological connectivity, and safeguard species to achieve a “more, bigger, better and better connected” ecological network.
2.5The draft LNRS went to public consultation from the 6 th August to 15th October 2025. This Pre-publication document presented at Appendix 3 has been informed by public consultation, which saw and 3,782 comments being received.
2.6Supporting authorities (Telford & Wrekin Council and Natural England) have the option to object to its publication on grounds of either not being justified by the consultation or being materially deficient. Natural England, wholeheartedly supports the LNRS and following examination by the Defra panel on the 17th December 2025, the panel approved the LNRS for publication subject to minor amendments (which have been made). The LNRS is being taken to Telford & Wrekin Cabinet on 26th March 2026 seeking approval and adoption from its members.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.