Annual Treasury Report 2025/26

Approved Executive 4 papers

AI summaryShropshire Council Cabinet approved the 2025/26 prudential and treasury indicators, noting that treasury investments returned 4.19% and delivered £2.409 million in income, marginally below benchmark.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedAlso noted annual treasury management report and EFS borrowing
Money£2.409 millionInvestment income delivered in 2025/26
What happens nextContinued quarterly reportingNext round of treasury management updates to Cabinet
Who it affectsCouncil borrowing and investmentsManages cashflow, security and risk of public funds

What was decided

Cabinet approved the actual 2025/26 prudential and treasury indicators set out in the report. Report 2.1

Cabinet noted the annual treasury management report for 2025/26. Report 2.1

Cabinet noted the inclusion of EFS borrowing in the 2025/26 position. Report 2.2

Why

The Council is required by regulations under the Local Government Act 2003 to produce an annual treasury management review and the actual prudential and treasury indicators. Report 3.1, 9.1

The Council complied with its legislative and regulatory requirements during 2025/26, with treasury activities within approved indicators and the Treasury Strategy. Report 4.1, 4.4

Managing cashflow, investments and borrowing efficiently is needed to support a financially sustainable council and generate additional income. Report 7.1

What happens next

Cabinet will continue to receive quarterly treasury management update reports during 2026/27. Report P8

Future reporting will follow the CIPFA Code of Practice on Treasury Management and the Prudential Code, supported by the Council's Treasury Management Practices. Report 3.1, 3.3, 6.1

The money

  • £2.409 million Investment income delivered in 2025/26, reflected in the Financial Outturn report Report 8.2
  • 4.19% Return achieved on treasury investments during 2025/26 Report 4.2
  • -0.14% Shortfall of investment returns against benchmark during 2025/26 Report 4.2

Options considered

  • Rejected: Alternative options. Not applicable Report 5.1

Implications

  • Financial: Investment income of £2.409 million has been reflected in the 2025/26 Financial Outturn report. Report 8.2
  • Legal: The report meets the requirements of the Local Government Act 2003, the CIPFA Code of Practice on Treasury Management and the Prudential Code. Report 3.1, 9.1
  • Risk: Compliance with the CIPFA Code, the Treasury Policy Statement and Treasury Management Practices, alongside internal controls, is intended to manage the risk of financial loss on treasury activities. Report 6.1

Who and where

  • Shropshire Council's overall cashflow, borrowing and investment position Report 3.3, 7.1
  • The Council's revenue and capital activities, which depend on adequate liquidity and security of investments Report 3.3

Timeline

  • 27 February 2025: Council approved the Treasury Strategy 2025/26 Report P33
  • 10 September 2025: Cabinet received Treasury Management Update Quarter 1 2025/26 Report P34
  • 3 December 2025: Cabinet received Treasury Management Update Quarter 2 2025/26 and the mid-year review Report P35, P36
  • 11 February 2026: Cabinet received Treasury Management Update Quarter 3 2025/26 Report P37
  • 10 June 2026: Cabinet received Treasury Management Update Quarter 4 2025/26 Report P38
  • 8 July 2026: Cabinet approved the Annual Treasury Report 2025/26

Plain English for the jargon

  • Prudential indicators: Measures set under the Prudential Code to show the impact of capital expenditure activities, compared here against the targets in the Treasury Strategy.
  • Treasury management: The organisation of the Council's borrowing, investments and cash to ensure liquidity, security and risk management.
  • EFS borrowing: Not defined in the supplied papers; appears as a category of borrowing included in the 2025/26 position.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item204

Resolved

That Cabinet: 1. Approved the actual 2025/26 prudential and treasury indicators in this report. 2. Noted the annual treasury management report for 2025/26. 3. Noted the inclusion of EFS borrowing in the 2025/26 position That Cabinet: 1. Approved the actual 2025/26 prudential and treasury indicators in this report. 2. Noted the annual treasury management report for 2025/26. 3. Noted the inclusion of EFS borrowing in the 2025/26 position
Word for word from the decision Shropshire published for this meeting. Source: www.shropshire.gov.uk

Follow this further

Built from Shropshire's papers

What the report saysPro

Report to Cabinet

Recommendations

Members are asked to: -

2.1Approve the actual 2025/26 prudential and treasury indicators in this report.

2.1Note the annual treasury management report for 2025/26.

2.2Note the inclusion of EFS borrowing in the 2025/26 position

Background

3.1The Council is required by regulations issued under the Local Government Act 2003 to produce an annual treasury management review of activities and the actual prudential and treasury indicators for 2025/26. This report meets the requirements of both the CIPFA Code of Practice on Treasury Management, (the Code), and the CIPFA Prudential Code for Capital Finance in Local Authorities, (the Prudential Code).

3.2During 2025/26 the minimum reporting requirements were that the full Council should receive the following reports:

• an annual treasury strategy in advance of the year • a mid-year treasury update report • an annual review following the end of the year describing the activity compared to the strategy, (this report)

In addition, Cabinet has received quarterly treasury management update reports during the year.

3.3The Council’s treasury management debt and investment position is organised by the finance team to ensure adequate liquidity for revenue and capital activities, security for investments and to manage risks within all treasury management activities. Procedures and controls to achieve these objectives are well established both through member reporting detailed in the summary, and through officer activity detailed in the Council’s Treasury Management Practices. Assurance on liquidity is taken from detailed cashflow planning which is amended day by day and reviewed to identify issues and address them. Cash flow plans extend out 24 months. Day to day cash flow plans inform short term investment and borrowing planning, as well as supporting the planning for longer term investments and borrowings. 4. Summary of Main Proposals

4.1During 2025/26, the Council complied with its legislative and regulatory requirements. The key actual prudential and treasury indicators detailing the impact of capital expenditure activities during the year, with comparison to the target set in the Treasury Strategy, are detailed in Appendix C.

4.2The returns on investment were marginally short of the benchmark (-0.14%), achieving a return of 4.19%. As cash balances held are low due to a reduced level of balances held, the Council needs to ensure cash balances are highly liquid, resulting in lower interest rates on short term deals. Whilst returns on investment are important, as we strive to achieve the best investment we can, the Council’s priority is always to ensure security of funds and ensure we hold sufficient liquid balances. This will often mean that we cannot secure the higher rate investments as these are offered to longer term deals.

4.3The Council does receive benchmarking analysis of its investments in relation to its comparative group and throughout 2025/26, its performance on investment were considered in line with the other organisations.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
20260706 APPENDIX A: Borrowing Strategy and Outturn 2025-26Appendix 442 KB Download
PDF
20260706 APPENDIX B: Investment Strategy and Outturn 2025-26Appendix 303 KB Download
PDF
20260706 APPENDIX C: Prudential Indicators 2025-26Appendix 199 KB Download
PDF
Annual Treasury Report 2025/26Report 168 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 13 attended
HK
Heather KiddCommittee Member, apologies
AW
Alex WagnerCommittee Member, present
RE
Roger EvansCommittee Member, present
AH
Andy HallCommittee Member, present
RH
Ruth HoughtonCommittee Member, present
JO
James OwenCommittee Member, present
RW
Rob WilsonCommittee Member, present
DV
David VasmerCommittee Member, present
DW
David WalkerCommittee Member, present
SM
Sarah MarstonCommittee Member, apologies
RD
Rosemary DartnallGuest, present
DH
Dawn HusemannGuest, in attendance

All 13 on the meeting page

On this subject at Shropshire

Search all
  1. Annual Treasury Report 2025/26This decision
  2. Treasury Management Update Quarter 2 2026/27Decided
  3. Treasury Management Update Quarter 1 2026/27Noted
  4. Second line assurance: Annual Treasury ReportApproved
  5. Treasury Management Update Quarter 4 2025/26Noted
  6. Treasury Strategy 2026/27Approved

More from Shropshire Cabinet

All decisions
MeetingDecisionOutcome
18 Nov 2026 MinutesThat the minutes of the meeting held on 14 October 2026 be confirmed as an accurate record. Decided Open
18 Nov 2026 Crisis & Resilience Fund – 6-month Progress UpdateThat Cabinet: 1. Endorsed the summary of the wider economic environment and the Council’s borrowings and investments ... Decided Open
18 Nov 2026 Council Tax Support - Proposed Changes 2027-28 Consultation ResponsesThat Cabinet: 1. Considered the responses received to the statutory consultation. 2. Agreed the following changes to ... Agreed Open
18 Nov 2026 Financial Monitoring Report Quarter 2 2026/27That Cabinet: A. Supported the Q2 favourable revenue outturn forecast of £0.051m. B. Supported the significant advers... Noted Open
18 Nov 2026 Treasury Management Update Quarter 2 2026/27That Cabinet: 1. Endorsed the summary of the wider economic environment and the Council’s borrowings and investments ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies