Resolved
View the decision text for item 33.
Cabinet decided this item on Monday 18 July 2011. Below is the council's own wording, with the papers it was decided on.
Resolved
View the decision text for item 33.
Since Cabinet considered highway changes in Chalvey on 31st May Members and Officers have met with representatives of the Chalvey community, including individuals and residents’ groups.
It has not been possible to achieve a consensus on a preferred option, as was anticipated by Cabinet on 31st May. Responses to the options have varied considerably among different groups and individuals.
The purpose of this report is to seek authority to implement all the options on an experimental basis, and to outline a proposed programme of works.
2 Recommendation(s)/Proposed Action
The Cabinet is requested to resolve:
a) To authorise the Head of Transport, after consultation with the Commissioner, to implement a number of Experimental Traffic Regulation Orders under the Road Traffic Regulation Act 1984: i. Full closure of Chalvey Road West; ii. One-way operation of Chalvey Road West eastbound; iii. One-way operation of Chalvey Road West westbound; iv. One-way operation of Ledgers Road northbound; v. One-way operation of Ragstone Road southbound; vi. One-way operation of Chalvey Road East westbound; vii. One-way operation of Martin Road southbound; viii. Parking measures as necessary to compliment the experimental road layouts; b) That the programme of experimental measures be based on the programme outlined in Annex B; c) That the detailed design for the experimental measures be based on the plans shown in Annex C; [To Follow] d) To authorise the Head of Transport, after consultation with the Commissioner, to modify and manage the programme of experimental measures, to be able to respond appropriately to both the impact on the Highway network, and any representations made; e) To authorise the Head of Transport, after consultation with the Commissioner, to modify and manage the detail of the experimental measures, including modifications to the experimental orders where appropriate, to be able to respond appropriately to both the impact on the Highway network, and any representations made; f) That the final decision on any permanent measures rests with Cabinet; g) That an update on progress be reported to Cabinet at it’s next meeting.
3 Community Strategy Priorities
Adding years to Life and Life to years Regeneration in Chalvey is the Council’s response to the identified needs of the area, which suffers from high levels of deprivation ranking amongst the 10% most deprived in the South East Region. Significant progress has already been made on regeneration, with the former Thames Valley Community Centre refurbished on a design and build basis to house a new Early Years Centre which gives young children a good start in life, and builds education and wellbeing into their lives at an early age. The new community hub currently under construction will provide a number of new community facilities including a library and adult learning facilities which address the needs of the local community.
Being Safe, Feeling Safe A number of accidents involving pedestrians have been recorded over the past 3 years, including on designated crossing points and near to local schools. Standing traffic increases the difficulty of pedestrians to cross busy road junctions, and by working to address these issues the safety and wellbeing of residents can be supported while the environmental quality of the area, both aesthetically and in terms of pollution can be improved.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Cabinet 18.07.11 Highway Changes in Chalvey: Annex CAppendix | 5.6 MB | Download |
PDF |
Cabinet 18.07.11 Highway Changes in Chalvey Annex B: Outline Programme of Experimental MeasuresAppendix | 48 KB | Download |
PDF |
Cabinet 18.07.11 Highway changes in Chalvey Annex A: Options for consultation v2Appendix | 667 KB | Download |
PDF |
Highway Changes in ChalveyReport | 121 KB | DownloadRead as text |
Follow Cabinet at Slough and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 19 Oct 2026 | Declarations of InterestView the decision text for item 1. | Decided | Open |
| 19 Oct 2026 | Minutes of the Meeting held on 21st September 2026View the decision text for item 2. | Decided | Open |
| 19 Oct 2026 | 2026-27 Q1 Corporate Performance ReportView the decision text for item 3. | Decided | Open |
| 19 Oct 2026 | Slough Children First - Inspection of Local Authorities Children's Services (ILACS) 06 to 17 July 2026 outcomeView the decision text for item 4. | Decided | Open |
| 19 Oct 2026 | Regulation of Investigatory Powers Act (RIPA) record of use of powersView the decision text for item 5. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.