Resolved
Resolved – that the lessons of the communications relating to the bus station project have and were being learnt and improved for current and future regeneration projects.
Neighbourhoods and Community Services Scrutiny Panel decided this item on Thursday 10 January 2013. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved – that the lessons of the communications relating to the bus station project have and were being learnt and improved for current and future regeneration projects.
1.1Following a request for Review from Councillor Plenty, this report is designed to provide the Panel with the necessary information to conclude whether the communications relating to the bus station project were adequate in relation to:
a) how the public consultation was managed, and in particular the publicising of the outside nature of the design; b) the use of the Slough Citizen; and c) the dissemination of information to the elected members.
2 Recommendation(s)/Proposed Action
2.1That the Panel draw conclusions as to whether there are any lessons that can be learnt from how the communications were managed during the Bus Station project.
3 Sustainable Community Strategy Priorities
3.1Priorities:
• Regeneration and Environment
The development of the new Bus Station, as part of the Heart of Slough project, was aimed at the comprehensive regeneration of that part of the town centre. The public engagement and Communications Plan for this were all part of the process.
4 Other Implications
(a) Financial
There are no financial implications of proposed action. (b) Risk Management
Risk Mitigating action Opportunities Legal None None Property None None Human Rights None None Health and Safety None None Employment Issues None None Equalities Issues None None Community Support None None Communications None None Community Safety None None Financial None None Timetable for delivery None None Project Capacity None None Other None None
(c) Human Rights Act and Other Legal Implications
There are no legal or Human Rights Act Implications relating to the content of this report.
(d) Equalities Impact Assessment
There is no identified need for the completion of an EIA relating to this report.
5 Supporting Information
Consultation and outside nature of the Bus Station
5.1The new Bus Station was one of the first elements of the Heart of Slough project to be completed. Therefore, much of the information put into the public domain about the Bus Station had come through the Heart of Slough project.
5.2On 21 January 2008 the Cabinet, in a public meeting, approved the outline Heart of Slough Master Plan and development brief, with approval of further changes to be delegated to the Assistant Director, Property Services in consultation with the lead Commissioners (Resources, and Planning, Transportation and Legal & Democratic Services) if regarded as significant. This decision by Cabinet was taken following the Overview and Scrutiny Committee’s deliberations on the matter at its meeting on the17 January 2008, and its comments were taken into consideration by Cabinet in taking its decision.
5.3Following this, the Cabinet, again in a public meeting, approved the outline design of the new Bus Station at its meeting on the 4 December 2008, with the Overview and Scrutiny Committee considering the same report immediately preceding the Cabinet. This report included drawings of the proposed design from a number of different angles, including: View from A4 towards train station
Ground level view
5.4The Heart of Slough Master Plan was approved by the Planning Committee on the 9 July 2009, following extensive consultation which included: writing to 1,526 residents or businesses and 85 external consultees, and putting up 50 site notices. From this the council received two objections and one comment from members of the public to the proposals. This public consultation was in addition to work carried out by the applicant, in this instance English Partnerships.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Member Call-In: Bus Station CommunicationsReport | 208 KB | DownloadRead as text |
Follow Neighbourhoods and Community Services Scrutiny Panel at Slough and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 25 Feb 2021 | Minutes of the meetings held on 6th January 2021 and 9th February 2021Resolved - That the minutes of the meetings held on 6 th January 2021 and 9 th February 2021 be approved as a correct... | Approved | Open |
| 25 Feb 2021 | 2021 CensusResolved – That details of the presentation be noted. | Noted | Open |
| 25 Feb 2021 | HRA Tenanted Stock Landlord Statutory Compliance UpdateIt was agreed that this information would be circulated to the Panel. The Neighbourhood Contracts & Business Services... | Agreed | Open |
| 25 Feb 2021 | The Home Improvement AgencyIt was agreed that the information would be circulated to the Panel. Referring specifically to the audit recommendati... | Agreed | Open |
| 25 Feb 2021 | Forward Work Programme 2020/21Resolved – That details of the work programme be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.