Resolved
1) That a further update is provided to the panel after the next Voids workshop which is scheduled for mid September 2014. 2) That the results of the second benchmarking exercise be shared with the Panel.
Neighbourhoods and Community Services Scrutiny Panel decided this item on Thursday 3 July 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
1) That a further update is provided to the panel after the next Voids workshop which is scheduled for mid September 2014. 2) That the results of the second benchmarking exercise be shared with the Panel.
Appendix 1 Interserve (IFS) Void Analysis Report Author Paul Blizzard - General Manager: Interserve (Facilities Services- Slough) Ltd
1. Interserve void property services include all major and minor housing repairs and maintenance, we also provide void management from the moment a tenant notifies their landlord that they are vacating the property, until the property is re-let. This can enable Interserve to perform any agreed repairs prior to the tenant vacating.
2. This helps our clients to minimise turnaround times for empty properties so they can maximise rental income and reduce cost of void service. It also enables robust and clear voids management and tracking.
3. The Interserve philosophy recognises that housing availability and maximised property rental income are critical elements of successful partnerships. So our clearly structured voids process plans organises empty property management and repairs and maintenance works to achieve optimum delivery and turnaround, within budget and agreed timescales.
4. Every aspect of this strategic process is designed to achieve tangible results by reducing the procedural timeline – without compromising on quality – while also strengthening communication to make sure everyone involved knows what they are doing, when and how.
5. Our specialist approach includes pre-works surveys, including works if agreed by Slough Borough Council (hereafter referred to as SBC), which saves our client time and eliminates any time lag between survey, specification and work commencement. We programme void works according to the scope and nature of the work required, rather than simply job value to improve workflow visibility and enable more accurate projected timescales. And careful planning and management of void works is programmed using an Optitime Appointments System, which enables instant progress monitoring and on-demand status reporting
6. It has been identified that the monitoring process which SBC use to measure void performance includes the lifecycle of the voids in its entirety. The moment the resident terminates their tenancy to the time when the void property has been re-let. This measurement doesn’t allow informed scrutiny of the Interserve void process. It is recognised also that the data on voids needs further development to ensure that Housing can easily interrogate this and this is to be incorporated in the action plan.
7.The void priority times are set by SBC, since the last scrutiny meeting the priority times have been amended. The new priority times are;
Value of Works Priority Times 0 -3k 10 Days 3 – 5k 15 days 5k+ LTV (planned target)
8. These priority times were changed in February 2014, since this date no void has over run and the KPI’s are running at 100%. The table below identifies that improvements have been made as the average number of the days Interserve has taken to turnaround Void properties has reduced.
Routine Voids Average Month Received days Feb-13 10 12 Mar-13 25 12 Apr-13 25 12 May-13 20 12 Jun-13 35 12 Jul-13 29 13 Aug-13 19 11 Sep-13 15 9 Oct-13 18 12 Nov-13 21 11 Dec-13 19 13 Jan-14 18 8 Feb-14 19 9 Mar-14 21 9
9. Unfortunately, the above KPI information relate to routine voids and do not include voids with decent homes works. The Voids which have decent homes works undertaken take longer to complete, this is in part due to utilising the same operatives to perform all the works to the property in their entirety. Measures are in place to reduce this number, including the possibility of increasing the volume of tradesmen performing the work and devising a new process in collaboration with SBC. We have recently had the process for delivering the repairs service mapped, the new process is in its embryonic stages, however, it’s been a positive start and we will remap the voids process with SBC in order to drive efficient working and reduce the key to key times for these properties.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Report: Voids App1Report | 64 KB | DownloadRead as text |
PDF |
Voids Contract PerformanceReport | 86 KB | Download |
Follow Neighbourhoods and Community Services Scrutiny Panel at Slough and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 25 Feb 2021 | Minutes of the meetings held on 6th January 2021 and 9th February 2021Resolved - That the minutes of the meetings held on 6 th January 2021 and 9 th February 2021 be approved as a correct... | Approved | Open |
| 25 Feb 2021 | 2021 CensusResolved – That details of the presentation be noted. | Noted | Open |
| 25 Feb 2021 | HRA Tenanted Stock Landlord Statutory Compliance UpdateIt was agreed that this information would be circulated to the Panel. The Neighbourhood Contracts & Business Services... | Agreed | Open |
| 25 Feb 2021 | The Home Improvement AgencyIt was agreed that the information would be circulated to the Panel. Referring specifically to the audit recommendati... | Agreed | Open |
| 25 Feb 2021 | Forward Work Programme 2020/21Resolved – That details of the work programme be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.