Better Care Fund 2015/16 - Quarter Two Report

Agreed Committee 1 paper

Slough Health & Wellbeing Board agreed this item on Wednesday 11 November 2015. Below is the council's own wording, with the papers it was decided on.

Item42

Resolved

It was agreed that the length of future reports would be reduced to avoid repetition of background information in quarterly reports and focus on risks and performance. As at the end of the second quarter, two schemes had been closed and money released to invest in other areas. These were £177k of Proactive Care funding and £179k from the closure of the post-acute reablement (PACE) service by Berkshire Healthcare Foundation Trust in May 2015. There had also been some slippage in planned expenditure of project activity and it been agreed to support several pilot or one-off activities including a Complex Case Management pilot, a Care Homes pilot and Responder Service pilot. The Board received a progress update on the priority areas of Proactive Care, Single Point of Access and Strengthening Community Capacity. The performance against key outcome measures was noted as follows: · Non-elective admissions – performance was close to plan for the first two quarters but the forecast was 17% above plan and the reasons were explained. The payment for performance element was therefore being held as contingency. · Delayed transfers of care – there had been significant variability with 30% below plan between January to March 2015 and 53% above plan between April to June. This spike was reported to be lower than other areas. The Quarter 2 figure was close to target as was the end of year forecast. · Care Home admissions – remained lower than plan. · Reablement – a very high proportion of people had been successfully reabled and remained at home 91 days after discharge. The Board noted that there were two areas where Slough was outside national conditions and the mitigating action was noted. The Quarter 2 return for BCF would need to be signed off by the SWB Chair for submission on 23 rd November to the NHS South Central team and 27 th November to the BCF support team. The Board considered progress generally in moving towards the BCF objectives to improve the integration of health and social care and whether the anticipated level of innovation was being met. The use of technology provided particular opportunities, for example on telehealth, and it was agreed to look at the emerging ideas and good practice from other areas. Resolved – That the Quarter Two Progress Report of the Better Care Fund Programme be noted.
Word for word from the decision Slough published for this meeting. Source: democracy.slough.gov.uk

Follow this further

Built from Slough's papers

What the report saysPro

Report to Slough Health & Wellbeing Board

Purpose of report

This report updates the Slough Wellbeing Board (SWB) on developments of the Better Care Fund (BCF). It outlines the mid-year position at the end of quarter two in delivery of the 2015/16 plan including the financial position and performance against BCF metrics.

The BCF plan was approved by the SWB on the 24th September 2014 and then also approved on 19th December 2014 following the NHS England National Consistent Review Process.

The Better Care Fund is managed through a Pooled Budget agreement between Slough Borough Council and Slough CCG.

2. Recommendation(s)/Proposed Action

The SWB is asked to note this progress report of the Better Care Programme for Slough.

3. The Slough Joint Wellbeing Strategy, the JSNA and the Five Year Plan

The Slough Joint Wellbeing Strategy (SJWS) is the document that details the priorities agreed for Slough with partner organisations. The SJWS has been developed using a comprehensive evidence base that includes the Joint Strategic Needs Assessment (JSNA).

3.1Slough Joint Wellbeing Strategy Priorities

The actions the local authority and CCG will take to address the requirements of the BCF, will aim to both improve, directly and indirectly, the wellbeing outcomes of the people of Slough against all the priorities of the strategy but especially the Health priority. 3.1.2 It will do this by promoting people’s wellbeing, enabling people and families to prevent and postpone the need for care and support, and putting people in control of their lives so they can pursue opportunities underpinned by the theme of civic responsibility.

3.1.3 The BCF plan addresses a range of activities which focus on diversion from A&E and increasing community based support services. These services improve health and wellbeing outcomes for people in Slough. The plan seeks to address key cross cutting themes such as prevention, early intervention and management of conditions which limit inclusion.

3.2Five Year Plan Outcomes

3.2.1 The Better Care programme will contribute towards the outcome of more people taking responsibility and managing their own health, care and support needs.

3.2.2 Working together with the CCG and provider partners there is a strong focus on a Proactive Care approach within the Slough BCF plan working with individuals and communities to identify and reduce risk of deterioration or repetition of episodes of ill health.

Proactive Care involves forecasting to anticipate what may happen to someone in the future, preparing for that change and putting a plan into action. It also puts the individual at the centre of their care so that NHS and social care staff work together with the person in planning and supporting them to manage their own care as well as help identify other sources of help. Slough’s BCF plan also extends to community respiratory care of Children and Young People which supports them to be healthy, resilient and have positive life chances.

3.2.3 The Better Care programme also covers the bringing together of a range of health and social care services that focus on recovery and reablement to work better and more effectively together to support people to regain and maximise their independence. Integrating these areas of joint working will bring efficiencies and benefits financially but also in avoiding duplication and delivering better outcomes for people in Slough.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Better Care Fund 2015/16: Quarter Two ReportReport 143 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 13 attended
RA
Councillor Robert AndersonCommittee Member, present
SH
Councillor Sabia HussainCommittee Member, present
NA
Naveed Ahmed Business representativeCommittee Member, apologies
RB
Ruth Bagley Chief Executive, Slough Borough CouncilCommittee Member, present
SB
Simon Bowden Thames Valley Police SloughCommittee Member, apologies, sent representative
RK
Ramesh Kukar Voluntary and Community SectorCommittee Member, present
LL
Lise Llewellyn Director of Public Health, BerkshireCommittee Member, present
JO
Dr Jim O'Donnell Clinical Commissioning Group, SloughCommittee Member, apologies, sent representative
LO
Les O'Gorman Business representativeCommittee Member, present
RP
Rachel PearceCommittee Member, absent
DP
Dave Phillips Head of Prevention and Protection, RBFRSCommittee Member, present
CP
Colin Pill Slough HealthwatchCommittee Member, present

All 13 on the meeting page

On this subject at Slough

Search all
  1. Better Care Fund 2015/16 - Quarter Two ReportThis decision
  2. Section 75 Agreement with the NHS Thames Valley Integrated Care Board to govern the delivery of the Better Care Fund 2026-2027Decided
  3. Better Care Fund 2024-25 Approval Information ReportNoted
  4. Better Care FundNoted
  5. Update on BCF (Better Care Fund)Noted
  6. Better Care FundNoted

More from Slough Slough Health & Wellbeing Board

All decisions
MeetingDecisionOutcome
16 Sep 2025 Appointment of Vice Chair of the Health & Wellbeing Boardthat [name removed], be appointed vice-chair for the 2025-26 Municipal Year. Decided Open
16 Sep 2025 Minutes of the last meeting held on 17 June 2025That the minutes of the last meeting held on 16 June 2025 were agreed to be a true and accurate record. Agreed Open
16 Sep 2025 Health Protection PartnershipResolved : that the report be noted. Noted Open
16 Sep 2025 Suicide Prevention Partnership Updatethatthe report be noted. Noted Open
16 Sep 2025 Slough Joint Local Health & Wellbeing Strategy - Draft & Consultation PlanResolved – that the draft Strategy be approved for a 6-week consultation. Approved Open