Resolved
View the decision text for item 8.
Cabinet decided this item on Monday 27 June 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
View the decision text for item 8.
To inform the Cabinet about the progress that has been made so far in reviewing the Local Plan and the proposed next stages.
2 Recommendation(s)/Proposed Action
The Cabinet is requested to resolve that the report be noted.
3. The Slough Joint Wellbeing Strategy, the JSNA and the Five Year Plan The Slough Joint Wellbeing Strategy (SJWS) is the document that details the priorities agreed for Slough with partner organisations. The SJWS has been developed using a comprehensive evidence base that includes the Joint Strategic Needs Assessment (JSNA).
3a. Slough Joint Wellbeing Strategy Priorities
The review of the Local Plan is directly linked to the following priorities in the Slough Joint Wellbeing Strategy:
Health Economy and Skills Regeneration and Environment Housing Safer Communities
It will also contribute to Improving the image of the town.
3b Five Year Plan Outcomes
The Review of the Local Plan will contribute to the following Outcomes:
1 Slough will be the premier location in the South East for businesses of all sizes to locate, start, grow and stay. 2 There will be more homes in the borough with the quality improving across all tenures to support our ambition for Slough. 3 The centre of Slough will be vibrant, providing business, living and cultural opportunities. 4 Slough will be one of the safest places in the Thames Valley
4 Other Implications
(a) Financial
There are no financial implications of proposed action.
(b) Risk Management
Risk Mitigating action Opportunities Legal No risks identified Property No risks identified Human Rights No risks identified Health and Safety No risks identified Employment Issues No risks identified Equalities Issues No risks identified Community Support – A public consultation There will be a need strategy will be developed. for a formal public consultation exercise. Communications No risks identified Community Safety No risks identified Financial No risks identified Timetable for delivery Contingency plans for a – The review of the delay to the timetable can Local Plan is be put in place. dependent upon a number of external factors which could delay the time table. Project Capacity – A Project Plan for the The review of the plan Review of the Local plan will require additional has been produced and a resources. budget secured. Other
(c) Human Rights Act and Other Legal Implications
There are no legal or Human Rights Act implications.
(d) Equalities Impact Assessment
There is no identified need to complete an EIA at this stage of the plan preparation process. 5 Supporting Information
5.1In April 2015 it was agreed that work should start work on producing a new Local Plan to replace the Core Strategy (2008), Site Allocations Plan (2010) and the “saved” parts of the Local Plan for Slough (2004). The intention is that will set out the Planning Policy framework to 2036.
5.2The first phase of the work has involved working jointly with other authorities and the LEP to gather the evidence that we need to produce a new plan. We have also been active in commenting on the plans being produced by neighbouring authorities as part of our responsibilities under the Duty to Cooperate.
5.3A “Call for Sites” exercise was carried out at the beginning of the year which invited proposals that may accommodate future development or infrastructure needs from residents, developers and landowners. All of the 134 proposals that we received, together with some other ideas, are currently the subject of a public consultation exercise.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Progress Report on the Review of the Local Plan for SloughReport | 82 KB | DownloadRead as text |
Follow Cabinet at Slough and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 19 Oct 2026 | Declarations of InterestView the decision text for item 1. | Decided | Open |
| 19 Oct 2026 | Minutes of the Meeting held on 21st September 2026View the decision text for item 2. | Decided | Open |
| 19 Oct 2026 | 2026-27 Q1 Corporate Performance ReportView the decision text for item 3. | Decided | Open |
| 19 Oct 2026 | Slough Children First - Inspection of Local Authorities Children's Services (ILACS) 06 to 17 July 2026 outcomeView the decision text for item 4. | Decided | Open |
| 19 Oct 2026 | Regulation of Investigatory Powers Act (RIPA) record of use of powersView the decision text for item 5. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.