1.1To present to members the business case for the redevelopment of land in Trelawney Avenue and Meadow Road which is the former location of the Merrymakers Public House.
1.2The report seeks approval to agree Heads of Terms (“HoTs”) with Karter Developments Limited (“KDL”) for the disposal of the freehold interest of the site in order to develop new healthcare/commercial facilities and housing and to seek in- principle approval to enter into a Development Agreement with KDL to build Council facilities including a new Council Hub, 4 houses and subject to planning at least 5 apartments.
2 Recommendation(s)/Proposed Action
Cabinet is requested to:
a) Subject to planning requirements and highways restrictions associated with car parking spaces, note that the eventual use of the proposed third floor of the SBC element could be either 350m2 of office space or 5 residential apartments;
b) Agree to the disposal of the freehold interest in land in Trelawney Avenue (as outlined in red on the plan in Appendix C and described as the “development site”) to Karter Developments Limited, subject to planning, for a sum to be agreed between parties based on independent valuations carried out February 2018 as set out in the Heads of Terms (attached as Confidential Appendix B);
c) Note that a new Council Hub, healthcare facilities and housing will be built on the site by KDL;
d) Delegate authority to the Director of Regeneration to appropriate the development site from the HRA for a sum to be agreed once the sale price is finalised;
e) Subject to approval of (a) and (b), delegate authority to the Director of Regeneration following consultation with the Leader of the Council and the s151 Officer to agree the final configuration of the building, all financial and non-financial terms of the HoTs and the Building Agreement, agree the final red line plan for disposal and the final value of investment by the Council;
f) Delegate authority to the Director of Regeneration to approve all financial and non-financial terms in relation to the disposal of the 4 houses funded by the Council which will be offered to the HRA and thereafter to James Elliman Homes. In the event that neither party is interested, the fall back position will be an open market sale;
g) Delegate authority to the Director of Regeneration to approve all financial and non-financial terms in relation to the proposed purchase and subsequent disposal of the apartments above the SBC freehold site;
h) Delegate authority to the Director of Regeneration, acting in consultation with the s151 Officer and the Leader of the Council to introduce, approve and agree a project contingency of up to 15% of the total project cost for the SBC element (as set out in the associated Part II report), provided such an increase does not impact on the viability of the project or the Council’s short- term financial plan;
i) Any profit after the land transactions in (a) and (f) will be reinvested into construction of the Council element of the new Hub and 4 houses with the balance funded by the Council;
j) To note that officers will continue to explore options to collocate the library within the SBC hub.
3. The Slough Joint Wellbeing Strategy, the JSNA and the Five Year Plan
The proposal to build a combination of housing and Hub containing health and community facilities on the Trelawney Avenue site will meet the strategic requirements of both Slough Borough Council (“SBC” or “the Council”) and East Berkshire Clinical Commissioning Group (“ the CCG”).
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Red line plan showing the whole development site and proposed disposal areaAppendix C | 1.3 MB | Download |
PDF |
Trelawney Avenue Redevelopment and HubReport | 113 KB | DownloadRead as text |
Follow Cabinet at Slough and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 19 Oct 2026 | Declarations of InterestView the decision text for item 1. | Decided | Open |
| 19 Oct 2026 | Minutes of the Meeting held on 21st September 2026View the decision text for item 2. | Decided | Open |
| 19 Oct 2026 | 2026-27 Q1 Corporate Performance ReportView the decision text for item 3. | Decided | Open |
| 19 Oct 2026 | Slough Children First - Inspection of Local Authorities Children's Services (ILACS) 06 to 17 July 2026 outcomeView the decision text for item 4. | Decided | Open |
| 19 Oct 2026 | Regulation of Investigatory Powers Act (RIPA) record of use of powersView the decision text for item 5. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.