Resolved
That the report be noted.
Neighbourhoods and Community Services Scrutiny Panel noted this item on Thursday 28 November 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
That the report be noted.
The purpose of this report is to provide Members with an update on the progress being made in reviewing the Local Plan for Slough which includes an update on the current housing supply position in Slough.
2. Recommendation(s)/Proposed Action
The Panel is requested to comment on the progress made in reviewing the Local Plan for Slough.
3. The Slough Joint Wellbeing Strategy, the JSNA and the Five Year Plan
3a. Slough Joint Wellbeing Strategy Priorities
The review of the Local Plan is directly linked to the following priorities in the Slough Joint Wellbeing Strategy:
Housing
3b. Five Year Plan Outcomes
The Local Plan will help deliver the following Five Year Plan outcomes:
Slough will be an attractive place where people choose to live, work and stay Our residents will live in good quality homes 4. Other Implications
(a) Financial
There are no financial implications to this report.
(b) Risk Management
There are no risk management implications arising from this report.
(c) Human Rights Act and Other Legal Implications
There are no Human Rights Act Implications as a result of this report.
(d) Equalities Impact Assessment
There are no equality impact issues
5. Supporting Information
5.1The progress on the review of the Local Plan was last reported to this Panel in January this year. This included an update on the Preferred Spatial Strategy.
5.2Since then there have been a number of developments which directly or indirectly affect the preparation of the Local Plan. These include the publication of the Interim Planning Framework for the Centre of Slough, Heathrow’s Airport Expansion consultation and the submission of the Chiltern South Bucks Local Plan.
5.3There has also been a significant deterioration in Slough housing supply which means that we have failed the Housing Delivery Test and no longer have a five year housing land supply.
5.4The implications of all of these for the Local Plan are explained are explained below.
5.5The overall strategy for the Review of the Local Plan is to deliver balanced cohesive growth which meets local needs as far as possible given all of the constraints to development. Our ambition is for Slough to become a place where people want to “live, work, rest, play and stay”.
5.6The main conclusion from the Issues and Options consultation was that there are no reasonable spatial options or combination of options that would allow Slough to meet all of its identified housing and employment needs within its boundaries.
5.7As a result we have prepared the emerging Preferred Spatial Strategy in accordance with the Local Plan Objective of meeting housing needs either within the Borough or as close as possible to where the need arises within a balanced housing market.
Emerging Preferred Spatial Strategy
5.8The emerging Preferred Spatial Strategy has been developed using some basic guiding principles which include locating development in the most accessible location, regenerating previously developed land, minimising the impact upon the environment and ensuring that development is both sustainable and deliverable.
5.9As a result the emerging Preferred Spatial Strategy has the following five key elements:
Delivering major comprehensive redevelopment within the “Centre of Slough”;
Selecting other key locations for appropriate development;
Protecting the built and natural environment of Slough including the suburbs;
Accommodating the proposed third runway at Heathrow and mitigating the impact;
Promoting the northern expansion of Slough in the form of a “Garden Suburb”;
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Local Plan UpdateReport | 3.6 MB | DownloadRead as text |
Follow Neighbourhoods and Community Services Scrutiny Panel at Slough and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 25 Feb 2021 | Minutes of the meetings held on 6th January 2021 and 9th February 2021Resolved - That the minutes of the meetings held on 6 th January 2021 and 9 th February 2021 be approved as a correct... | Approved | Open |
| 25 Feb 2021 | 2021 CensusResolved – That details of the presentation be noted. | Noted | Open |
| 25 Feb 2021 | HRA Tenanted Stock Landlord Statutory Compliance UpdateIt was agreed that this information would be circulated to the Panel. The Neighbourhood Contracts & Business Services... | Agreed | Open |
| 25 Feb 2021 | The Home Improvement AgencyIt was agreed that the information would be circulated to the Panel. Referring specifically to the audit recommendati... | Agreed | Open |
| 25 Feb 2021 | Forward Work Programme 2020/21Resolved – That details of the work programme be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.