Repairs Maintenance and Investment (RMI) Contract Update
AgreedScrutiny5 papers
Neighbourhoods and Community Services Scrutiny Panel agreed this item on Monday 22 June 2020. Below is the council's own wording, with the papers it was decided on.
It was agreed that the 2018/19 Star Survey results be circulated to the Panel. The Chair thanked the Service Lead, Housing Development and Contracts for the report and welcomed the opportunity to hear from an Osborne representative at the next Panel meeting. Resolved – (a) That the report be noted. (b) That the Panel noted the requirement for Osborne to present the 2020/21 Annual Report to the Neighbourhoods and Community Services Scrutiny Panel. (c) That the Panel noted the requirement for Osborne to offer the Panel the outline of the program of service improvements, service innovations, and the intended outputs Osborne had agreed to commit to for delivery during the financial year 2020/21. (d) That the co-opted member Trevor Pollard be requested to forward an invite to a Resident Board meeting to the Chair and any other interested Panel Members. (e) That the Service Lead, Housing (People) Services be requested to re-circulate the Resident Satisfaction Survey, 2019, presented to the Panel in January 2020.
Word for word from the decision Slough published for this meeting.Source: democracy.slough.gov.uk
1st December 2017 – 30th November 2018 End of Year Report Dec 2017 – Nov 2018 __________________________________________________________________________________________
Contents
Executive Summary Pages 3 – 7
Service Delivery Customer Experience Repairs Voids Pages 8 – 16 Statutory Compliance Caretaking & Cleaning Capital Investment Cyclical Maintenance IT supporting Service Delivery People Skills Training & Investment Pages 16 – 18 Osborne Restructure Supply Chain Health & Safety RMI Plus (additional work) Page 18
Forward Plan Pages 19 – 20
2|P a g e End of Year Report Dec 2017 – Nov 2018 __________________________________________________________________________________________
1. Executive Summary 1.1 Following the fulfilment of a 16½ year Repairs and Maintenance contract with Interserve, the Council took the opportunity to review the way its repairs, maintenance, compliance and investment services for its housing stock were delivered. After detailed consultation, consideration and review of options, Cabinet agreed to consolidate the services into a unique single contract to deliver its repairs, maintenance and investment (RMI) services to the HRA (Housing Revenue Account) stock. A comprehensive and robust OJEU compliant, procurement exercise followed which included two stages of competitive dialogue. Osborne Property Services Limited were selected as the council’s preferred Contractor and in June 2017 a £100m contract was signed for an initial 7 year period from 1st December 2017 (with the option to extend for a maximum of a further 3 years).
1.2Industry best practice recognises the benefits of co-location and working closely in partnership enables swifter resolution of issues and fosters an open transparent partnership. The partnership is operational from Hawker House where both Osborne and the SBC client team are co-located to proactively support partnership working arrangements. This makes for a robust, swift, joined up and responsive service. Currently a number of other SBC teams are also co-located at Hawker House, including the East Neighbourhood Team, Information and Participation, Resilience and Enforcement, Adult Social Care East Locality Team, ASC Occupational Therapy Long Term Team and Hestia, the council’s independent domestic violence advocacy service.
1.3A year on in the contract it is timely to provide Members with contextual information about the contract during its first year, including the bedding in period (1.12.17 – 31.3.18). This report outlines challenges which have arisen, areas where improvements have been made, statistical performance information collated for the first year of the partnership, together with the Partnership’s forward plan for delivery and enhancements of services. Performance is measured by Key Delivery Indicators (KDIs) which have targets set within the contract. All of which provide the Partnership with the requirements necessary to understand, develop, learn and enhance the service throughout the term of the contract. A summary of service delivery performance is given in part 2 of this report. It should be noted that the client has made deductions of £70k against failure to meet performance in accordance with contractual requirements in the first 6 months of 2018/19. This will be subject to review in March 2019 in accordance with the contract and pending enhancement of service delivery necessary payments may be made.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Neighbourhoods and Community Services Scrutiny Panel at Slough and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.