HRA Tenanted Stock Landlord Compliance Quarterly Report (Quarter 2)
Water Hygiene Water Hygiene testing has now progressed with a more robust schedule of testing. Testing of tap temperatures at 21 properties from commencement of the contract was the only water hygiene testing being carried out until June 2020. SBC have now instructed Osborne to include the below testing to maximise the safety of our residents and ensure water the hygiene testing schedule remains robust. We are continuing to review the water testing regime and adding additional tasks to ensure that SBC remains compliant. Cold water storage tank testing Weekly flushing of little used outlets Point of use water heaters Descale of shower head and spray taps TMV fail safe and maintenance Calorifier inspection Water connections to outside services Mixer Units Hot Water Cylinders Expansion Vessel Disinfection Combination Water Heater Inspection Thermal Insulation Check Closed Water Systems Water sampling
2 yearly risk assessments have been completed in June 2020 and remedial works following the assessment commenced in October 2020. Remedial works are carried out site by site with 4 sites currently being done. SBC are currently 100% percent across all water testing.
Asbestos All annual re- inspection surveys have been completed to 491 blocks from 491. The re-inspection programme commenced in October 2020. Asbestos removal recommended in the loft space will commence shortly. In addition to the current Asbestos management, SBC are looking to implement Asbestos management surveys to be carried out at all domestic dwellings next year, providing a wide spread overview of asbestos across the HRA stock. SBC are currently 100% compliant across asbestos management and re-inspection surveys. Fire Risk Assessment The FRA programme continues to progress with various work steams currently underway including the below: Total properties where FRA were carried out is 507 and 45% of actions have been completed. Current actions to date resulting from FRA’s carried out is 12,484. Completed actions completed are 5,630 with 6,854 open actions to be completed. There are 1,378 actions outstanding (but not overdue) and 5,476 actions outstanding which are overdue. New programme of remedial works was issued to Osborne in October 2020 in order to complete the outstanding actions. Summary : De-designated schemes New fire door installations completed at Calstock House, Apsley House, Redwood House, Armstrong House, Allington Court, Seymour House, Kennedy House, Harrow Road & Primrose Hill. 5000 fire stopping actions completed across the de-designated schemes. Design requirements for the upgrade of Fire Alarms to the de-designated schemes have been approved and quotations for the final designs are being procured. All asbestos surveys and necessary removals have been carried out to the 9 schemes. Low Rise Blocks Residents store doors replaced to date : 211 EICR communal remedial works completed at 127 blocks Fire door safety signage : 162 blocks Electrical over boxes to 143 blocks 447 blocks from 491 for fire stopping complete 81 Blocks require the removal of asbestos including the removal of incinerators Boxing of gas pipes :63 boxing’s
SBC and OPSL meet once a week to discuss all matters relating to compliance, including fire safety group, regular contact with Royal Berkshire Fire Service and weekly meetings with housing people services staff relating to fire safety.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
HRA Tenanted Stock Landlord Compliance Quarterly Report (Quarter 2)Report | 75 KB | DownloadRead as text |
Follow Neighbourhoods and Community Services Scrutiny Panel at Slough and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 25 Feb 2021 | Minutes of the meetings held on 6th January 2021 and 9th February 2021Resolved - That the minutes of the meetings held on 6 th January 2021 and 9 th February 2021 be approved as a correct... | Approved | Open |
| 25 Feb 2021 | 2021 CensusResolved – That details of the presentation be noted. | Noted | Open |
| 25 Feb 2021 | HRA Tenanted Stock Landlord Statutory Compliance UpdateIt was agreed that this information would be circulated to the Panel. The Neighbourhood Contracts & Business Services... | Agreed | Open |
| 25 Feb 2021 | The Home Improvement AgencyIt was agreed that the information would be circulated to the Panel. Referring specifically to the audit recommendati... | Agreed | Open |
| 25 Feb 2021 | Forward Work Programme 2020/21Resolved – That details of the work programme be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.