1 Summary and Recommendations
1.1This report sets out:
➢ the forecast monitoring position as at month 9 2022/23, covering revenue (including DSG and schools, Treasury Management (including asset sales) and Pensions) and capital for both the General Fund and the HRA (Sections 2 to 13) ➢ risks, mitigations and caveats/requirements associated with the information
1.2In respect of the above it should be noted that:
1.2.1 The Council’s forecast revenue and capital outturn positions for 2022/23 as at period 9 (P9, 31 December 2022) are noted along with a number of risks associated with this and how these have been mitigated to deliver a balanced forecast at this stage in the year. This is subject to ongoing and complete delivery of all savings as projected by all Executive Directors, assumed asset sales and closed and audited accounts for all years. 1.2.2 The projected forecast, variances and service level budgets are ongoing work in progress and reflect the work and investigations able to be undertaken up to this point in time. There has been substantial ongoing work and cleansing required to date in order to get the budgets at a service level to approach the standard normally expected, this is necessitated because of the inherited inaccuracies such as under or overstated budgets on grants, rental income and expenditure and recharges to capital or the HRA. Corrections have been factored into the Capitalisation Direction (CD) adjustments in the 2022/23 budgets to support the Council with historical budgeting issues, but further refinement will be needed on an ongoing basis to ensure the budget sits precisely where needed.
Overall Capitalisation Direction
1.2.3 A key element of the Council’s financial recovery plan set out in September 2021, the Council’s Treasury Management Strategy (TMS) approved in March 2022 and the SUR disposals strategy approved in July 2022 is to reduce the Council’s historic over-reliance on temporary borrowing in order to reduce interest rate risk and to reduce the annual level of Minimum Revenue Provision (MRP) charges. The debt reduction strategy is predicated on a programme of generating capital receipts which can then be applied to repay temporary borrowing and reduce the Council’s Capital Financing Requirement (CFR), which determines the amount of MRP payable. The disposals profiling is based on a set of assumptions regarding: ➢ the assets considered to be surplus to requirements, ➢ the timing and value of these, and ➢ progress along a pipeline of work required to get them ready for disposal.
1.2.4 The list and profiling is reviewed and updated on a regular basis based on: ➢ progress, ➢ potential issues that could delay, and ➢ governance requirements.
1.2.5 Progress in 2022/23 is principally arising from the work on the accounts identifying accessible receipts, the review of the companies including SUR and the disposal of assets. Currently the benefits of this work combined with the output of elements of the Council’s financial recovery strategy which was to: ➢ address the identified problem, this began in July 2021 ➢ sell assets to reduce borrowings and thus reduce MRP/interest costs and finance the CD – agreed September 2021 ➢ reduce net revenue expenditure – ongoing since July 2021 ➢ produce and have audited high quality accounts – ongoing since July 2021
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
GF Revenue Forecast: P9Appendix Ai | 69 KB | Download |
PDF |
GF Revenue YTD P9Appendix Aii | 58 KB | Download |
PDF |
Savings Tracker: P9Appendix Bi | 147 KB | Download |
PDF |
Savings Tracker: P9Appendix Bii | 148 KB | Download |
PDF |
General Fund Capital Programme: P9Appendix Ci | 145 KB | Download |
PDF |
Financial Update Report: P9 2022/23Report | 312 KB | DownloadRead as text |
Follow Cabinet at Slough and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 19 Oct 2026 | Declarations of InterestView the decision text for item 1. | Decided | Open |
| 19 Oct 2026 | Minutes of the Meeting held on 21st September 2026View the decision text for item 2. | Decided | Open |
| 19 Oct 2026 | 2026-27 Q1 Corporate Performance ReportView the decision text for item 3. | Decided | Open |
| 19 Oct 2026 | Slough Children First - Inspection of Local Authorities Children's Services (ILACS) 06 to 17 July 2026 outcomeView the decision text for item 4. | Decided | Open |
| 19 Oct 2026 | Regulation of Investigatory Powers Act (RIPA) record of use of powersView the decision text for item 5. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.