That Cabinet approve the following:
1. General Fund (Revenue) – A balanced outturn on an approved budget of £160.202m. This includes the £11.4m of mitigations identified during Quarter 1 that is now being proactively managed within services. Further action has been identified to contain pressures that have arisen during Q2 including the curtailment of a number of projects. The 24/25 Pay award has been settled within the £2.6m set aside for this and the balance of £1.228m has been used to offset pressures. 2. Virements in accordance with the council’s constitution and includes mitigations agreed in Quarter 1 that require Cabinet approval. The values shown are the net impact on departments forecast allowing for offsetting underspends. These are funded through the Recovery Actions agreed at Q1, other underspends and further actions proposed for the second half of 2024/25.
3. In addition to the virements in the table below, there are a further 2 virements required, as follows:
• A £250k saving on Fees and Charges across all directorates is held in contingency, and should be distributed; and • A £2.660m figure held in contingency in respect of the pay award needs distributing, noting this is offset by the saving on the pay award in the table below.
Temporary or Cabinet Virements to approve (Revenue) £m Permanent Operational Matters Supporting vulnerable young people through Temporary investment in EHCP processing, Educational 1.353 (addressed in Psychologist and Home to School Transport MTFS) Temporary Supporting increasing number of vulnerable 3.603 (addressed in adults MTFS) Temporary Temporary Accommodation 4.401 (addressed in MTFS) Procured additional external resources to fund the balance sheet review and interims to 0.600 Temporary deliver the backlog accounts Other Recovery Actions from Q1 -2.963 Temporary Reduction in Slough Children First contract -2.166 Temporary costs Reduction in Non-Departmental Cost and -3.735 Temporary Balance Sheet contributions Reduction in assumed use of 2024/25 Pay -1.228 Permanent Award (including SCF) Removal of historic saving in respect of the 0.235 Permanent integration of support services
Deferral of purchase of Library Stock -0.100 Temporary
TOTAL 0.000 4. General Fund (GF) (Capital) – The revised capital budget is £35.428m with a projected outturn of £25.294m resulting in underspend of £10.134m. This compares to a £1.868m forecast underspend in Quarter 1.
5. Approve the following virement which require Cabinet approval in accordance with the council’s constitution.
Cabinet Virements to approve (Capital) £m Arbour Vale capital works – Release unused contingency from the 0.500 car park budget and increase the classroom budget
6. Housing Revenue Account (HRA Revenue) – An underspend of £3.478m is forecast, in line with budget. This compares to a £3.734m forecast underspend in Quarter 1.
7. Housing Revenue Account (HRA Capital) – The revised capital budget is £25.003m with a projected outturn of £19.641m resulting in an underspend of £5.362m. This compares to a £8.062m forecast underspend in Quarter 1.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Budget Management Report Quarter 2Report | 342 KB | DownloadRead as text |
Follow Cabinet at Slough and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 19 Oct 2026 | Declarations of InterestView the decision text for item 1. | Decided | Open |
| 19 Oct 2026 | Minutes of the Meeting held on 21st September 2026View the decision text for item 2. | Decided | Open |
| 19 Oct 2026 | 2026-27 Q1 Corporate Performance ReportView the decision text for item 3. | Decided | Open |
| 19 Oct 2026 | Slough Children First - Inspection of Local Authorities Children's Services (ILACS) 06 to 17 July 2026 outcomeView the decision text for item 4. | Decided | Open |
| 19 Oct 2026 | Regulation of Investigatory Powers Act (RIPA) record of use of powersView the decision text for item 5. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.