Resolved
RESOLVED that the Budget Management Outturn for Q2 2023/24, be noted.
Corporate Improvement Scrutiny Committee noted this item on Tuesday 17 December 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the Budget Management Outturn for Q2 2023/24, be noted.
Slough Borough Council
REPORT TO: Corporate Improvement Scrutiny Committee
DATE: 17 Deceember 2024
SUBJECT: Budget Management Report Quarter 2
CHIEF OFFICER: Annabel Scholes, Executive Director, Finance and Commercial
CONTACT OFFICER: Dave McNamara, Director Financial Management
WARD(S): ALL
PORTFOLIO: Councillor Smith – Leader of the Council Councillor Chahal – Lead Member Financial Oversight
EXEMPT: NO
APPENDICES: A: Cabinet response to recommendations (section 1,2) B: Savings & Mitigations C: Capital Programme
1. SUMMARY and RECOMMENDATIONS
1.1This report sets out the Council’s current and forecast financial performance for the financial year 2024/25 as at the end of Quarter 2, 30 September. The report also contains relevant information relating to management controls and activity that support current financial resilience and longer-term financial sustainability.
1.2The report was put before Cabinet on 18 November 2024 with the following recommendations, their responses to which are set out in Appendix A
i. General Fund (Revenue) – A balanced outturn on an approved budget of £160.202m. This includes the £11.4m of mitigations identified during Quarter 1 that is now being proactively managed within services. Further action has been identified to contain pressures that have arisen during Q2 including the curtailment of a number of projects. The 24/25 Pay award has been settled within the £2.6m set aside for this and the balance of £1.228m has been used to offset pressures.
ii. Virements in accordance with the council’s constitution and includes mitigations agreed in Quarter 1 that require Cabinet approval. The values shown are the net impact on departments forecast allowing for offsetting underspends. These are funded through the Recovery Actions agreed at Q1, other underspends and further actions proposed for the second half of 2024/25.
iii. In addition to the virements in the table below, there are a further 2 virements required, as follows:
iv. A £250k saving on Fees and Charges across all directorates is held in contingency, and should be distributed; and
v. A £2.660m figure held in contingency in respect of the pay award needs distributing, noting this is offset by the saving on the pay award in the table below.
Temporary Cabinet Virements to approve (Revenue) £m or Permanent Operational Matters Supporting vulnerable young people through Temporary investment in EHCP processing, Educational 1.353 (addressed Psychologist and Home to School Transport in MTFS) Temporary Supporting increasing number of vulnerable 3.603 (addressed adults in MTFS) Temporary Temporary Accommodation 4.401 (addressed in MTFS) Procured additional external resources to fund the balance sheet review and interims to 0.600 Temporary deliver the backlog accounts Other Recovery Actions from Q1 -2.963 Temporary Reduction in Slough Children First contract -2.166 Temporary costs Reduction in Non-Departmental Cost and -3.735 Temporary Balance Sheet contributions Reduction in assumed use of 2024/25 Pay -1.228 Permanent Award (including SCF) Removal of historic saving in respect of the 0.235 Permanent integration of support services
Deferral of purchase of Library Stock -0.100 Temporary
TOTAL 0.000 vi. General Fund (GF) (Capital) – The revised capital budget is £35.428m with a projected outturn of £25.294m resulting in underspend of £10.134m. This compares to a £1.868m forecast underspend in Quarter 1. vii. Approve the following virement which require Cabinet approval in accordance with the council’s constitution.
Cabinet Virements to approve (Capital) £m Arbour Vale capital works – Release unused contingency from 0.500 the car park budget and increase the classroom budget
viii. Housing Revenue Account (HRA Revenue) – An underspend of £3.478m is forecast, in line with budget. This compares to a £3.734m forecast underspend in Quarter 1.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Budget Management Q2 OutturnReport | 274 KB | DownloadRead as text |
PDF |
Q2 AReport | 47 KB | Download |
PDF |
Q2 BReport | 115 KB | Download |
PDF |
Q2 CReport | 98 KB | Download |
Follow Corporate Improvement Scrutiny Committee at Slough and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 21 Jul 2026 | Minutes of the last meetingThat the minutes of the last meeting held on 30 June 2026 were approved as a true and correct record. | Approved | Open |
| 21 Jul 2026 | Youth Justice Improvement PlanThat the progress made within the service is acknowledged. 2. That the service develops the Improvement Plan to also ... | Decided | Open |
| 21 Jul 2026 | Budget TAF MembershipThat the committee appoint Councillors Instone, Mohammad and Qaseem to the Budget task and finish group. | Decided | Open |
| 30 Jun 2026 | Minutes of the last meeting - 28 April 2026that the minutes of the last meeting held on 28 April 2026 were approved as a true and accurate record. | Approved | Open |
| 30 Jun 2026 | Commissioning of the Budget Task and Finish Group for the 2026-27 municipal yearthat the Committee agreed to commission the Budget Task and Finish Group for 2026/27 municipal year and appoint Counc... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.