What was decided
Cabinet agreed to recommend a 4.8% rise in social and affordable dwelling rents, tenant service charges and garage rents from 6 April 2026, in line with CPI plus 1%. [P2, P3, P4, 1.5] Report P2, P3, P4, 1.5
Cabinet agreed to recommend approval to full Council of the 30-year HRA business plan, the 2026/27 HRA revenue budget, the 5-year capital programme and to note the draft 5-year reserves. [P6, P7, P8, P9, 1.6] Report P6, P7, P8, P9, 1.6
The decision fulfils the Council's legal duty to set a balanced HRA budget for 2026/27 before the start of the financial year, with Commissioners content with the recommendations. [P14, P16, P17] Report P14, P16, P17
Why
The HRA is a ringfenced landlord account under the Local Government and Housing Act 1989, and the Council must set a budget that avoids a debit balance and sets rents within the social housing rent standard. [1.7, 1.8, 1.9, 3.1] Report 1.7, 1.8, 1.9, 3.1
The 4.8% rise is the maximum allowed under the rent regulation (September CPI of 3.8% plus 1%), and service charges are being phased up to full cost recovery by 2027/28. [4.4, 8.6] Report 4.4, 8.6
The plan funds new burdens including fire safety works, damp and mould responses under Awaab's Law, decarbonisation, and service improvements following a C3 consumer grading from the Regulator of Social Housing. [5.2, 5.3, 5.4, 5.8, 5.9, 5.10, 5.12] Report 5.2, 5.3, 5.4, 5.8, 5.9, 5.10, 5.12
What happens next
Recommendations will go to full Council for approval in March 2026, after which statutory rent variation notices of at least 28 days will be issued to tenants. [1.8, 12.2, 1.6] Report 1.8, 12.2, 1.6
Officers will refresh the 30-year business plan in consultation with tenants, leaseholders and under-represented groups, including scenario and sensitivity testing. [P16, 15.3, 15.4] Report P16, 15.3
Re-procurement of the Repairs and Maintenance contract begins in April 2026, and a soft market test for the NEC Housing IT system is underway. [5.6, 5.7] Report 5.6, 5.7
The money
- 4.8% Increase in social and affordable dwelling rents, tenant service charges and garage rents from 6 April 2026 Report P2, P3, P4
- £136.97 New average weekly social rent from 6 April 2026, up from £130.70 Report 8.2
- £6.27 Average weekly rent rise per social dwelling Report 8.2
- £1.945m Net increase in dwelling rent income in 2026/27, a 4.8% rise Report 8.3
- £267.08 New average weekly affordable rent from 6 April 2026, up from £254.85 Report 8.3
- £14.23 New average weekly tenant service charge, up from £13.58 Report 8.8
- £2.083m Estimated net tenant service charge income in 2026/27 Report 8.8
- £0.148m Remaining service charge recovery gap after 2026/27, to be cleared by 2027/28 Report 8.9
- £12.51 New average weekly garage rent, up from £11.94 Report 8.14
- £14.687m Repairs and maintenance budget for 2026/27 Report 9.1
- £9.738m Supervision and management budget for 2026/27 Report 9.2
- £122m HRA external debt as at 1 April 2026, with no additional borrowing planned over 30 years Report 9.6, 10.8
- £25m HRA capital investment requirement in 2026/27 Report 10.5
- £117m Total HRA capital investment over the 5-year programme Report 10.5
- £775m HRA investment in maintaining, improving and developing stock over 30 years Report 10.5
- £6.173m Annual provision for decarbonisation, uplifted by inflation over 5 years Report 10.3
- £157m Provision for new affordable housing stock over 30 years Report 10.4
- £10.4m Indicative LAHF Round 4 grant for Slough over 4 years (44% of costs) Report 5.13
- £26m HRA provision over 5 years for new affordable homes including LAHF match Report 5.13
- £0.901m Projected HRA interest income on balances for 2026/27
- £34.864m Projected HRA general reserve balance at end of 5-year period Report P115
- £1.284m Projected Major Repairs Reserve balance at end of 5-year period Report P117
Options considered
- Chosen: Apply maximum 4.8% rent increase (CPI + 1%). Aligns with current national rent setting formula and supports HRA financial sustainability Report P2, 4.4, 1.8
- Rejected: Apply lower rent increase, freeze or reduce rents. Draft 2026 Rent Standard allows discretion but plan needs full cost recovery Report 4.3
- Chosen: Increase service charges by 4.8% to phase in full cost recovery by 2027/28. Closes the £0.223m cumulative recovery gap while keeping charges affordable Report P3, 8.6, 8.9
- Chosen: Continue disposal of HRA garages, shops and other non-residential assets. Part of long-term estate strategy; capital receipts shared with General Fund under no detriment principle Report 8.12, 8.13, 8.15, 8.16
Implications
- Financial: Average social rent rises by £6.27 per week and net dwelling rent income grows by £1.945m; HRA is planned to deliver surplus budgets in each of the next five years. [8.2, 8.3, 9.7, 11.2] Report 8.2, 8.3, 9.7, 11.2
- Legal: Council must issue at least 28 days' written notice of rent variations under Section 103 of the Housing Act 1985, and comply with the social housing Rent Standard. [1.8, 12.1, 12.2] Report 1.8, 12.1, 12.2
- Equalities: Around 67% of social tenants receive Housing Benefit or Universal Credit housing element, so should see HB/UC rise with rent; others may be signposted to Discretionary Housing Payments and a new Crisis and Resilience Fund from April 2026. [8.4, 15.3, 15.4, 15.5] Report 8.4, 15.3
- Climate: The plan provides £6.173m a year for decarbonisation and over £195m over 30 years, supported by a £6.331m Warm Homes Social Housing Warm Fund grant. [5.5, 10.3] Report 5.5, 10.3
- Risk: Key risks include inflation above assumed levels, RTB sales rising, welfare reform impacts on rent collection, and the cost of achieving net zero. [13.1] Report 13.1
- Staffing: The Competence and Conduct Standard from October 2026 will require training and qualifications such as CIH Level 4, with £0.300m provided in the plan. [5.10, 5.12] Report 5.10, 5.12
- Other: Regulator of Social Housing inspection in April 2025 rated the housing service C3; a Service Improvement Plan is in place with bimonthly Regulator monitoring. [5.8, 5.9] Report 5.8, 5.9
Who and where
- Council tenants in around 5,948 tenanted homes, including those on Housing Benefit or Universal Credit Report 3.3, 8.4
- Leaseholders in around 1,424 leasehold homes, who pay service charges set by apportionment Report 3.3, 8.10
- Council and private tenants renting HRA garages, including 1,000+ garages marked for disposal by end of 2026/27 Report 8.13, 8.14
- Households on the housing register and people in temporary accommodation, who may benefit from £26m of new affordable homes funding over 5 years Report 5.13, 6.1
Timeline
- 20 January 2026: Residents Board consulted on the proposed 4.8% rent and service charge increases Report 15.3
- 28 January 2026: Government confirmed rent convergence policy for years after 2026/27 Report 4.2
- 16 February 2026: Cabinet considered the HRA 30-year business plan, MTFS and 2026/27 rent setting
- March 2026: Full Council expected to approve the HRA business plan, revenue budget and capital programme Report 1.6
- April 2026: Re-procurement of the Repairs and Maintenance contract commences; bids open for new Social and Affordable Homes Programme Report 5.6, 4.5
- 6 April 2026: New rents, service charges and garage rents take effect after at least 28 days' notice Report P2, P3, P4, 1.8
- October 2026: Competence and Conduct Standard for social housing comes into force Report 5.10
- 2027/28: Target date for full recovery of service charge costs from tenants and leaseholders Report 2.2, 8.6
Plain English for the jargon
- HRA: Housing Revenue Account, a ringfenced local authority account for income and spending on council housing, required under the Local Government and Housing Act 1989.
- CPI: Consumer Prices Index, the inflation measure used as the basis for annual social rent increases.
- RTB: Right to Buy, the statutory right for secure council tenants to purchase their home at a discount.
- MRR: Major Repairs Reserve, an HRA reserve funded by depreciation and used for capital works on existing stock.
- TSM: Tenant Satisfaction Measures, performance indicators used by the Regulator of Social Housing to assess landlord services.
- LAHF R4: Local Authority Housing Fund Round 4, a government grant programme for temporary accommodation and homelessness, starting April 2026.
- PWLB: Public Works Loan Board, a government body that lends to local authorities.