Resolved
Resolved – That the minutes of the meetings held on 21 st January and 12 th February 2026 be approved as a correct record.
Audit and Corporate Governance Committee approved this item on Wednesday 11 March 2026. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved – That the minutes of the meetings held on 21 st January and 12 th February 2026 be approved as a correct record.
Extraordinary Audit and Corporate Governance Committee – Meeting held on Thursday, 12th February, 2026.
Present:- Councillors O’Kelly (Chair), Instone, Mohindra and Rana
Apologies for Absence:- Councillors Escott, Nazir, Satti and Tomar
Co-Opted Members:- Basant Chana, Rupa Sidpara and Jen Simpson
PART 1 65. Declarations of Interest
None received.
66. Statement of Accounts 2024/25
The Committee received the Statement of Accounts 2024/25 and were reminded that following their publication on 12th December 2025, the accounts were then subject to a 30-working day public inspection which closed on 28th January 2026. The Director of Finance and Commercial circulated an updated table for note 23 on page 92 of the statement of accounts and it was noted that this updated version would be included in the final set of accounts.
The Auditors had a short time frame in January 2026 following the delayed publishing of these accounts to undertake some audit work. The audit work focussed on in year transaction for 2024/25 with samples requested by the auditors and working papers returned by the Council. It was noted that the accounts would be issued a disclaimed audit opinion in line with previous years accounts due to the lack of assurance over the opening balances and the delays in production of the accounts which meant that a full audit was not possible.
Members asked a number of questions which included:
• Likelihood of achieving required asset sales and risks associated with this. The director of finance and commercial explained that the asset disposals programme was integral to the capitalisation directive and there was a clear timetable for the next three to five years to achieve these sales. Risk associated with this approach was achieving less than market value on assets and therefore less of an impact on reducing debt. Approximately £3220m asset sales were factored into the accounts. • A Member sought assurance that mistakes of the past such as funds from HRA being charged to the general fund would not be repeated. It was explained that there was a clear schedule of recharges which were actioned and checked on a quarterly basis to ensure there were no last-minute surprises at that level in future accounts. Regular Audit and Corporate Governance Committee - 12.02.26
monitoring was taking place to ensure costs were recorded in the proper place. • The Chair stated that a lack of governance had led to the current situation and sought assurance that the authority had moved beyond inadequate record keeping and weaknesses in audit trails. The Committee was reminded that external review had taken place by EY and although no further specific independent reviews planned, areas of improvement being assess were training and support to members re the overall accounts process, including understanding of the HRA, DSG and general fund. A detailed plan relating to lessons learnt in relation to the accounts process would be brought to the next committee meeting. It was also noted that internal audit would be conducting an audit of data record management and the Chair stated that it was reassuring that a plan was in place to move forward and lessons were learnt. • Responding to the partial assurance provided by external audit regarding contract management, officers explained that extensive work had been carried out in this area with the contract register now approximately 70% complete. The Procurement Improvement Plan would be discussed at the next meeting. • Questions relating to the authority’s levels of reserve were discussed and it was noted that the reserve levels in the 24/25 accounts were £23.5m and it was planned that these would be maintained at circa £20-25m.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Minutes , 12/02/2026Minutes | 87 KB | DownloadRead as text |
PDF |
Minutes of the Meetings held on 21st January and 12th February 2026.Minutes | 109 KB | Download |
Follow Audit and Corporate Governance Committee at Slough and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 11 Mar 2026 | Action Progress ReportIt was agreed that the Chair, on behalf of the Committee, would write to the Lead Members responsible for regeneratio... | Agreed | Open |
| 11 Mar 2026 | Annual Governance Statement 2024/25 – End of Year Progress UpdateIt was agreed that the Committee would receive at a future meeting, data relating to late reports. A Member asked wha... | Agreed | Open |
| 11 Mar 2026 | Closing of Accounts debrief 2024/25Resolved - That the findings of the Grant Thornton audit work review and Council’s response to this be noted. | Noted | Open |
| 11 Mar 2026 | Closing of Accounts Plan and Timetable 2025/26Resolved - That the closing plan and timetable for the production of the 2025/26 Statement of Accounts be noted. | Noted | Open |
| 11 Mar 2026 | Corporate Risk Report Quarter 3 2025/26Resolved - a) That the revised Corporate Risks and Sub-Risks as at Quarter 3 FY25/26 (February 2026) as set out in Ap... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.