Budget Task and Finish Group Report

Agreed Scrutiny 2 papers

AI summarySlough scrutiny committee backs six recommendations to improve budget scrutiny and engagement, and will send them to Cabinet for approval.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedTo be directed to Cabinet for approval
MoneyNo direct financial implications stated
What happens nextRecommendations to CabinetTask and Finish Group to be set up for 2026/27
Who it affectsBudget scrutiny processLead Members, residents, businesses, stakeholders

What was decided

The Committee approved the six recommendations from the Budget Task and Finish Group and will forward them to Cabinet for approval, amended as needed. Report P11, P12

Budget-related executive decisions with a direct impact on the budget, taken outside the scrutiny timetable, should be considered by the scrutiny committee, with the format agreed with members, the Chair and finance colleagues. Report P12

A new Budget Task and Finish Group should be commissioned for the 2026/27 municipal year, scoped with scrutiny members and finance colleagues. Report P12

Why

The group was set up to give members a better chance to carry out financial scrutiny, suggest real-time improvements to the budget and the Medium Term Financial Strategy, and feed into future annual cycles. Report P12

Members wanted stronger political ownership by Lead Members, earlier and wider public engagement, and Equality Impact Assessments done at the start of the budget process rather than after decisions are made. Report P12

What happens next

The recommendations go to Cabinet for approval, with any changes the Committee makes at this meeting. Report P11

The 2026/27 Budget Task and Finish Group will be commissioned, with its work scoped with scrutiny members and finance colleagues. Report P12

The budget setting timeline and scrutiny involvement should be agreed and consulted on as early as practical in the municipal year. Report P12

Options considered

  • Chosen: Approve the Task and Finish Group recommendations and send to Cabinet. Committee noted and approved the recommendations in the report Report P11, P12

Implications

  • Financial: No direct financial implications from the report itself. Report P13
  • Legal: No known legal implications arising from the report. Report P13
  • Equalities: No known equalities implications from the report, though the recommendations call for Equality Impact Assessments at the earliest stage of the budget process. Report P12, P13
  • Risk: No known direct risk management implications. Report 4.5
  • Other: No known environmental or corporate parenting implications. Report P13, 4.6

Who and where

  • Lead Members holding budget portfolios, who are expected to take stronger ownership and attend budget scrutiny meetings regularly Report P12
  • Residents, businesses and key stakeholders, who are to be engaged earlier in budget setting Report P12
  • Scrutiny committee members and finance colleagues, who will shape the scrutiny format and timelines Report P12
  • Groups who may be adversely affected by budget decisions, who are to be considered through earlier Equality Impact Assessments Report P12

Timeline

  • 2025/26 municipal year: Budget Task and Finish Group convened as part of the Corporate Improvement Scrutiny Committee work programme Report P12
  • 28th April 2026: Report of the Task and Finish Group considered by the Corporate Improvement Scrutiny Committee Report P2, P3
  • 2026/27 municipal year: A new Budget Task and Finish Group is to be commissioned Report P12

Plain English for the jargon

  • MTFS: Medium Term Financial Strategy, the council's multi-year financial plan.
  • CISC: Corporate Improvement Scrutiny Committee, the Slough committee that considered this report.
  • Task and Finish Group: A temporary scrutiny group set up to look at a specific issue and report back with recommendations.
  • Equality Impact Assessment: An assessment of how a proposed policy or decision may affect different groups, particularly those at risk of disadvantage.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item62

Resolved

RESOLVED : that the Committee agreed the recommendations as in the report: · Any budget-related executive decisions or those that are considered outside of the budget scrutiny timetable that have a direct impact on the budget proposals (i.e. significant savings or reductions in services), should be considered by the scrutiny committee. The format of this scrutiny to be decided in consultation with Committee members, the Chair, and finance colleagues. · That the budget setting timeline and process, including scrutiny involvement be agreed and consulted on as early as is practical in the municipal year to ensure there is dedicated and sufficient opportunity for key stakeholders to engage with the budget setting. · Equality Impact Assessments to be undertaken and completed at the earliest stage in the process of the budget. This is with the aim of informing decisions made around the budget and to consider the impact of budget decisions on all residents, particularly those who might be adversely affected. This impact should always be considered as part of the budget-making process, not an afterthought once decisions have effectively already been made. · That public engagement and consultation is significantly strengthened and undertaken early on in the budget setting process, to allow for residents, business, and key stakeholders to feedback on the budget. This may require the council to consider new and innovative methods of engaging with residents to sharply improve participation rates. · That Lead Members have stronger oversight and ownership of their budget portfolios, demonstrate much stronger political ownership of their portfolios and that they attend budget scrutiny meetings regularly. · That the Budget Task and Finish Group be commissioned for the 2026/27 municipal year and that the work is thoroughly scoped with the involvement of scrutiny members and finance colleagues.
Word for word from the decision Slough published for this meeting. Source: democracy.slough.gov.uk

Follow this further

Built from Slough's papers

What the report saysPro

Report to Corporate Improvement Scrutiny Committee

Slough Borough Council

Report To: Corporate Improvement Scrutiny Committee

Date: 28th April 2026

Subject: Report of the Budget Task and Finish Group

Chief Officer: Sarah Wilson, Monitoring Officer

Contact Officer: Amy O’Brien, Scrutiny and Governance Officer

Ward(s): All

Exempt: No

Appendices Appendix A – Report of the Budget Task and Finish Group

1. Summary 1.1 This report summarises the work done by the Budget Task and Finish Group on scrutiny of the budget setting process for 2026/27, including recommendations from the group 1.2 It sets out the topics discussed by the group, what recommendations they gave, and reflections from members and officers.

2. Recommendations: This report recommends that: 2.1 The Committee notes and comments on the report in appendix A. 2.2 The Committee approves its recommendations made by the Task and Finish Group in section 3.3 2.3 The Committee subsequently directs these recommendations to Cabinet for approval amended as necessary by any points emerging from the Corporate Improvement Scrutiny Committee meeting.

3. Report 3.1 The Budget Task and Finish Group was convened as part of the 2025/26 Corporate Improvement Scrutiny Committee (CISC) Work Programme, with the aim of ensuring that the CISC, and members of the Task Group are given the opportunity to carry out better financial scrutiny, propose real-time improvements to the budget and MTFS development and feed into subsequent annual cycles. 3.2 The report is attached as Appendix A. 3.3 As a result of the work of the Task and Finish Group, the following recommendations have been made: - Any budget-related executive decisions or those that are considered outside of the budget scrutiny timetable that have a direct impact on the budget proposals (i.e. significant savings or reductions in services), should be considered by the scrutiny committee. The format of this scrutiny to be decided in consultation with Committee members, the Chair, and finance colleagues. - That the budget setting timeline and process, including scrutiny involvement be agreed and consulted on as early as is practical in the municipal year to ensure there is dedicated and sufficient opportunity for key stakeholders to engage with the budget setting. - Equality Impact Assessments to be undertaken and completed at the earliest stage in the process of the budget. This is with the aim of informing decisions made around the budget and to consider the impact of budget decisions on all residents, particularly those who might be adversely affected. This impact should always be considered as part of the budget-making process, not an afterthought once decisions have effectively already been made. - That public engagement and consultation is significantly strengthened and undertaken early on in the budget setting process, to allow for residents, business, and key stakeholders to feedback on the budget. This may require the council to consider new and innovative methods of engaging with residents to sharply improve participation rates. - That Lead Members have stronger oversight and ownership of their budget portfolios, demonstrate much stronger political ownership of their portfolios and that they attend budget scrutiny meetings regularly - That the Budget Task and Finish Group be commissioned for the 2026/27 municipal year and that the work is thoroughly scoped with the involvement of scrutiny members and finance colleagues.

4. Implications 4.1 Financial implications This is not a decision-making report, therefore there are no direct financial implications. 4.2 Legal implications There are no known legal implications arising from this report 4.3 Equalities There are no known equalities implications arising from this report 4.4 Corporate Parenting There are no known corporate parenting implications arising from this report

4.5Risk management implications There are no known direct risk management implications arising from this report.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
App A: Budget TAF final 1.1Appendix 244 KB Download
PDF
Budget Task and Finish Group ReportReport 81 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 12 attended
NK
Councillor Nadeem KhawarChair, present
CH
Councillor Christine HulmeVice-Chair, present
ZA
Councillor Zaffar AjaibCommittee Member, present
PK
Councillor Pavitar Kaur MannCommittee Member, apologies
FA
Councillor Fiza A. MatloobCommittee Member, apologies
SM
Councillor Subhash MohindraCommittee Member, present
FO
Councillor Frank O’KellyCommittee Member, present
DT
Councillor Dhruv TomarCommittee Member, apologies
TO
Thomas OverendOfficer, expected
AO
Amy O'BrienDemocratic Services Officer, expected
SM
Shilpa ManekDemocratic Services Officer, expected
NC
Natalie CarrOfficer, expected

On this subject at Slough

Search all
  1. Budget Task and Finish Group ReportThis decision
  2. Commissioning of the Budget Task and Finish Group for the 2026-27 municipal yearAgreed
  3. Recommendations to Cabinet from CISC meeting on 4th February 2026 - Budget Task & Finish Group ReportDecided
  4. Report on the Budget Task and Finish GroupNoted
  5. Budget Task and Finish GroupAgreed
  6. Launching a Task and Finish Panel to scrutinise in-year budget management and planning budget for 2025/26Approved

More from Slough Corporate Improvement Scrutiny Committee

All decisions
MeetingDecisionOutcome
21 Jul 2026 Minutes of the last meetingThat the minutes of the last meeting held on 30 June 2026 were approved as a true and correct record. Approved Open
21 Jul 2026 Youth Justice Improvement PlanThat the progress made within the service is acknowledged. 2. That the service develops the Improvement Plan to also ... Decided Open
21 Jul 2026 Budget TAF MembershipThat the committee appoint Councillors Instone, Mohammad and Qaseem to the Budget task and finish group. Decided Open
30 Jun 2026 Minutes of the last meeting - 28 April 2026that the minutes of the last meeting held on 28 April 2026 were approved as a true and accurate record. Approved Open
30 Jun 2026 Commissioning of the Budget Task and Finish Group for the 2026-27 municipal yearthat the Committee agreed to commission the Budget Task and Finish Group for 2026/27 municipal year and appoint Counc... Agreed Open