Transformation Partner Update

Decided Executive 1 paper

AI summarySlough Borough Council Cabinet agreed to procure a transformation partner across three lots, delegating award authority to the Chief Operating Officer. The £15.6m revenue programme supports £25m of MTFS savings, with Lot 1 contracts starting August 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedThree-Lot model with delegated authority
Money£15.6m revenue investmentPlus £20m capital, £2m HRA
What happens nextLot 1 award by July 2026Lot 2 follows in August 2026
Who it affectsThree-year transformation programmeAims to deliver £25m of MTFS savings

What was decided

Cabinet noted the February 2026 approval to procure a transformation partner and agreed the updated multi-Lot procurement approach set out in the report. Report P2, 2.10

Cabinet delegated authority to the Chief Operating Officer, in consultation with the Leader, to select bidders, negotiate contract documents and enter into contracts for Lot 1, Lot 2 and Lot 3. Report P3, P4

Why

The recommendations ensure the Council can move at the pace required to deliver the three-year MTFS-aligned transformation programme while maintaining strong governance, independence and assurance. Report P6

Delegating authority provides operational flexibility to run procurements efficiently, negotiate value, and deliver transformation without delay, while retaining political oversight and accountability. Report P6

What happens next

Formal tender process for Lots 1 and 2 to begin following approval, with Lot 1 specification issued on 01 June 2026 and Lot 2 specification on 15 June 2026. Report 2.21, P50

Lot 1 contract award is planned for the end of July 2026, with contract commencement on 03 August 2026; Lot 2 contract award is planned for mid-August 2026, with commencement on 17 August 2026. Report 2.12, P50

The money

  • £15.6m revenue investment across 2026/27, 2027/28 and 2028/29 agreed as part of the 2026/27 budget setting process Report P52
  • £25m of the overall £38m MTFS savings plan expected to be delivered through the transformation programme Report P52
  • £20m estimated once-off capital investment included within the Capital programme over the same three-year period Report P54
  • £2m investment in the NEC Housing system set out in the HRA Capital Programme Report P54

Options considered

  • Chosen: Multi-Lot procurement under Option D (lead partner with specialist Lots). Provides optimal balance of assurance, flexibility, service engagement and capability building over the three-year period Report 2.10, P13, 2.2
  • Rejected: Do Nothing. The Council lacks the internal capacity and independence required to validate and assure transformation activity without external support Report P15
  • Rejected: Single external delivery partner. Risk of overdependency and reduced service ownership; some council activities are better served by specialist partners Report P16
  • Rejected: Exclude organisational design and culture programme from Lot 1. Essential to securing a coherent, sustainable Target Operating Model; internal HR team lacks the required capacity Report P17
  • Rejected: Defer procurement of Lot 2 until after Lot 1 mobilisation. Would add 3 to 5 months to the critical path for delivery of change and involve intrinsic waste Report P18, 2.9, P21, P22

Implications

  • Financial: Budget of £15.6m revenue over three years, plus £20m capital and £2m HRA capital for the NEC Housing system, is expected to support £25m of the £38m MTFS savings plan. Report P52, P54
  • Legal: Council must comply with the Procurement Act 2023 and its Contract Procedure Rules, and operate under statutory directions made under Part 1 of the Local Government Act 1999. Report P55, P56
  • Risk: An 11-item risk register covers procurement readiness, specification ambiguity, commercial pricing, legal challenge, market capacity, mobilisation, contract management, data access, fraud, supplier due diligence and cyber security, each with mitigation controls. Report P58, P59, P60
  • Equalities: Equality Impact Assessments will be required on a project-by-project basis, with screening at initiation and full EIAs where adverse or differential impacts are identified; no project will progress without an approved EIA. Report P63
  • Staffing: Lot 1 will deliver a 24-month organisational design and culture programme, with phased capability transfer to internal HR by the end of Year 2 and a clear exit strategy to reduce long-term reliance on external resource. Report 2.17, P38, P39, P40, P41, P42, P43, P44
  • Other: Commissioners have reviewed the report and are content that it builds on the February 2026 Cabinet report, and are satisfied with the delegated decision and governance. Report P7, P8, P9

Who and where

  • Slough Borough Council staff, who will be subject to the 24-month organisational design and culture programme and capability transfer to internal HR Report 2.17, P43
  • Residents and service users, where transformation initiatives affect services including Adult Social Care, Children's Services and Housing Report 2.12
  • Potential bidders and suppliers in the transformation, digital/data/technology and specialist service markets Report 2.2, P50
  • Corporate Leadership Team, Commissioners and Members, who will receive portfolio-wide reporting under the Lot 1 governance model Report 2.14, 2.16, P36

Timeline

  • 01 June 2026: Issue Specification/documentation for Lot 1 Report P50
  • 15 June 2026: Issue Specification/documentation for Lot 2 Report P50
  • 23 June 2026: Deadline for receipt of Tenders for Lot 1 Report P50
  • 16 to July 2026: Standstill period for Lot 1 Report P50
  • 07 July 2026: Deadline for receipt of Tenders for Lot 2 Report P50
  • 08 July 2026: Evaluation report for Lot 1 Report P50
  • 16 July 2026: Issue Contract Award Notice for Lot 1 Report P50
  • 22 July 2026: Evaluation report for Lot 2 Report P50
  • 30 July 2026: Issue Contract Award Notice for Lot 2 Report P50
  • 03 August 2026: Contract commencement for Lot 1 Report P50
  • 30 July to 9 August 2026: Standstill period for Lot 2 Report P50
  • 17 August 2026: Contract commencement for Lot 2 Report P50

Plain English for the jargon

  • MTFS: Medium Term Financial Strategy, the Council's three-year savings and budget plan
  • PMO: Portfolio Management Office, providing portfolio-wide oversight and assurance
  • DDaT: Digital, Data and Technology, the scope covered by Lot 2
  • TOM: Target Operating Model, the future organisational design the transformation programme aims to deliver
  • CLT: Corporate Leadership Team, the Council's senior officer group
  • EIA: Equality Impact Assessment, required on a project-by-project basis
  • HRA: Housing Revenue Account, the ringfenced account for council housing
  • NEC Housing system: The Council's housing management IT system, with £2m of investment in the HRA Capital Programme
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item4

Resolved

View the decision text for item 4.
Word for word from the decision Slough published for this meeting. Source: democracy.slough.gov.uk

Follow this further

Built from Slough's papers

What the report saysPro

Report to Cabinet

Recommendations

Cabinet is recommended to:

1) Note the previous approval by Cabinet in February 2026 to procure a transformation partner and approve the updated procurement approach set out in this report

2) Delegate Authority to the Chief Operating Officer, in consultation with the Leader, to select a bidder(s), negotiate the contract documents and enter into the contract for Transformation Partner Lot 1 (Core/Portfolio Office, PMO & Specialist Advisory)

3) Delegate Authority to the Chief Operating Officer, in consultation with the Leader, to approve select a bidder(s), negotiate the contract documents and enter into the contract for, Transformation Partner Lot 2 (Specialist Digital, Data and Technology Enabled Change). 4) Delegate Authority to the Chief Operating Officer, in consultation with the Leader, to approve select a bidder(s), negotiate the contract documents and enter into the contracts for, Transformation Partner Lots 3 (Specialists for Service Transformation e.g. Adults, Children’s, Housing).

Reason

The recommendations ensure the Council can move at the pace required to deliver the three-year MTFS-aligned transformation programme while maintaining strong governance, independence and assurance. Cabinet is asked to note the updated procurement approach so that the programme can proceed on a compliant and defensible basis, reflecting the February 2026 approval and the refined multi-Lot model. Delegating authority for bidder selection and contract award for Lot procurement to the Chief Operating Officer, in consultation with the Lead Member for Assets and Transformation, provides the necessary operational flexibility to run the procurements efficiently, negotiate value, and deliver Transformation without delay, while retaining clear political oversight and accountability.

Commissioner Review

Commissioners have reviewed the report and are content that it builds upon the February 2026 Cabinet report. They are satisfied with the delegated decision and governance.

Commissioners are content for this report to be considered.

2. Report

Introductory paragraph

2.1At the Cabinet meeting in February 2026, it was agreed that the Council should procure an external delivery partner(s) with some in-house co-ordination and delivery, with the option to appoint specialist partners for specific projects. Following further analysis of the need, it is proposed that this should be effected by establishing a structured multi-Lot arrangement, each Lot being a separate procurement.

Options considered

Recommended Option

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Transformation Partner UpdateReport 160 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 14 attended
WC
Councillor Wal ChahalChair, present
EA
Councillor Ejaz AhmedVice-Chair, present
IA
Councillor Iftakhar AhmedCommittee Member, present
PB
Councillor Puja BediCommittee Member, apologies
NK
Councillor Nadeem KhawarCommittee Member, present
GM
Councillor Gurcharan MankuCommittee Member, present
ZS
Councillor Zafar SattiCommittee Member, apologies
IS
Councillor Ishrat ShahCommittee Member, present
MS
Councillor Mabu ShaikCommittee Member, present
AW
Councillor Anna WrightCommittee Member, present
NP
Nicholas PontoneDemocratic Services Officer, expected
SA
Councillor Sabia AkramGuest, in attendance

All 14 on the meeting page

On this subject at Slough

Search all
  1. Transformation Partner UpdateThis decision
  2. Frimley Health and Care Sustainability and Transformation PartnershipNoted
  3. Frimley Health and Care Sustainability and Transformation PartnershipNoted
  4. Frimley Health and Care Sustainability and Transformation PartnershipNoted

More from Slough Cabinet

All decisions
MeetingDecisionOutcome
19 Oct 2026 Declarations of InterestView the decision text for item 1. Decided Open
19 Oct 2026 Minutes of the Meeting held on 21st September 2026View the decision text for item 2. Decided Open
19 Oct 2026 2026-27 Q1 Corporate Performance ReportView the decision text for item 3. Decided Open
19 Oct 2026 Slough Children First - Inspection of Local Authorities Children's Services (ILACS) 06 to 17 July 2026 outcomeView the decision text for item 4. Decided Open
19 Oct 2026 Regulation of Investigatory Powers Act (RIPA) record of use of powersView the decision text for item 5. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies