CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Slough Borough Council
Cabinet Urgency procedure - Leader's Action, Monday 6 July 2026 at 1.45pm

Extra Care Housing Care and Support Service: Award of Contract to Hales Group Ltd

Approved Executive 1 paper

AI summarySlough Council awards Extra Care Housing care contract to Hales Group Ltd after Agincare withdrew, worth up to £0.946m a year for three years from 1 September 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedReplaces Agincare UK Ltd who withdrew
MoneyUp to £0.946m per yearTotal £2.838m over 3 years, up to £1.892m more if extended
What happens nextContract starts 1 September 2026Mobilisation under way, new award notice to be published
Who it affectsResidents at two Extra Care schemesThe Pines and Northampton Place, 126 units, 36 staff

What was decided

The Leader approved awarding the Extra Care Housing Care and Support Service contract at The Pines and Northampton Place to Hales Group Ltd on the same terms as the original Cabinet approval of 20 April 2026. Report P2, 2.1

Authority was delegated to the Executive Director People (Adults), with the Lead Member for Adult Social Care and the Section 151 Officer, to finalise contract terms and authorise mobilisation. Any extension decision needs a separate decision. Report P3

The decision was treated as urgent and exempted from the call-in process, on the basis that the existing contract ends 31 August 2026 and a new contract must be in place by 1 September 2026. Report P5, P7, 2.3, 2.10

Why

Agincare UK Ltd wrote on 22 May 2026 saying they could not accept the contract for financial reasons, leaving a gap before the current contract expires on 31 August 2026. Report 2.3, 2.4, P5

Hales Group Ltd was the second highest ranked bidder in the original 13-tender evaluation, which used Quality 60%, Price 35%, Social Value 5%, and Legal and Procurement advice confirmed award to the next ranked compliant bidder is appropriate under the Procurement Act 2023. Report 2.5, 2.6, P17

What happens next

A new contract award notice will be published on the In-Tend portal and formal award follows if no challenges are received. Report 2.9

Weekly mobilisation steering group meetings will run, with TUPE information passed from Care Outlook Ltd to Hales Group Ltd, safeguarding assurance required before go-live, and enhanced staffing monitoring in the first 12 weeks. Report P34, P35, P38, P39, P40, 3.7, P50

Future year uplifts and any additional flex costs must be confirmed as compliant with procurement regulations and managed within directorate cash limits, and any extension will need a separate value-for-money decision. Report P9, P3

The money

  • £0.946m Annual contract value, excluding VAT and approved uplifts, same as original approval Report P2, P24
  • £2.838m Estimated total contract value over the initial 3 year term, excluding VAT Report P24
  • £1.892m Potential additional value for the 2 year extension period, excluding VAT Report P24
  • £0.340m Approximate annual core block element of the contract Report P25
  • £0.606m Approximate annual flex (spot) element based on assessed care needs Report P25

Options considered

  • Chosen: Award to Hales Group Ltd (second ranked bidder). Legally compliant, preserves original evaluation, maintains 1 September 2026 start, within approved budget, strong quality evidence Report P22, 2.6, P24
  • Rejected: Do nothing and let the current contract expire. Immediate risk to residents, statutory Care Act 2014 breach, disruption to hospital discharge, reputational damage Report P22
  • Rejected: Re-negotiate with Agincare UK Ltd. Agincare has stated the contract is not financially viable; re-negotiation would likely require price or scope changes and delay commencement Report P22
  • Rejected: Run a full re-procurement before 1 September 2026. Insufficient time, would leave a gap in provision, would likely require an emergency extension of the current contract Report P22
  • Rejected: Short-term extension of the existing contract while re-procurring. Further extension risks procurement compliance, misses opportunity for service improvement, existing provider may not agree Report P22

Implications

  • Financial: Proposal is deliverable within existing approved resources and is consistent with the Medium Term Financial Strategy 2026/27 to 2028/29. Any TUPE related costs sit with Hales Group Ltd. Report P26, P27
  • Legal: Failure to have a contract in place from 1 September 2026 would place the Council in breach of its Care Act 2014 duties. Award to the next ranked compliant bidder is consistent with the Procurement Act 2023 and the Council's Contract Procedure Rules. Report P28, P29
  • Equalities: The Equality Impact Assessment from November 2025 remains valid, no negative equality impacts identified; ongoing monitoring will assess equality related commitments. Report P43
  • Risk: Key risks are reduced mobilisation timeline, possible legal challenge, resident distress, staff uncertainty, and quality and safeguarding during transition, each with named mitigations. Report P34, P35, P36, P37, P38, P39, P40
  • Staffing: The service is subject to TUPE. An anonymised employee liability dataset covering 36 staff was provided by Care Outlook Ltd and updated in June 2026; no direct workforce implications for Council employees. Report 3.7, P50, P51

Who and where

  • Tenants at The Pines and Northampton Place, 126 self-contained Extra Care Housing units in Slough Report 2.2
  • 36 staff currently delivering the service, subject to TUPE transfer to Hales Group Ltd Report 3.7, P50
  • Anchor Housing, which holds the 99 year lease on the schemes (entered 2007/08) Report 2.2, P53, P55
  • Bidders in the original procurement exercise (13 tenders received) Report 2.5

Timeline

  • 14 April 2025: Cabinet approved procurement of the Extra Care Housing Care and Support Service via pipeline report Report 2.1
  • 23 January 2026: Deadline for the 13 tenders in the competitive open procedure Report 2.5
  • 20 April 2026: Cabinet approved original contract award to Agincare UK Ltd at up to £0.946m per year Report 2.1
  • 22 May 2026: Agincare UK Ltd formally notified the Council they cannot proceed for financial reasons Report 2.3
  • 10 June 2026: Council issued formal written response to Hales Group Ltd's clarification questions Report 2.10
  • 31 August 2026: Existing contract expires Report 2.2, P5
  • 1 September 2026: New contract with Hales Group Ltd starts, for an initial 3 year term Report P2

Plain English for the jargon

  • Extra Care Housing: Self-contained accommodation with on-site care and support, designed to help tenants live independently.
  • Light Touch Rules: Procurement rules under the Procurement Act 2023 that apply to health and social care services, with a more flexible procedure.
  • TUPE: Transfer of Undertakings (Protection of Employment) Regulations, which transfer staff and their terms from the old provider to the new provider.
  • Most Advantageous Tender (MAT): The bid that best meets the published award criteria, used as the basis for compliant award under procurement rules.
  • In-Tend portal: The Council's e-tendering system where contract notices are published.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item2

Resolved

Resolved – 1. Approved the award of the contract for the Extra Care Housing Care and Support Service at The Pines and Northampton Place to Hales Group Ltd, in place of the originally awarded provider Agincare UK Ltd, who have confirmed that they are unable to accept the contract award. The contract would be for an initial term of 3 years from 1 September 2026, with the option to extend for a further 2 years, at an annual contract value not exceeding £0.946m (exc. VAT and approved uplifts). 2. Delegated authority to the Executive Director, People (Adults), in consultation with the Lead Member for Adult Social Care and the Section 151 Officer, to finalise the terms of the contract with Hales Group Ltd and authorise all necessary mobilisation and implementation activity. This delegation did not extend to the exercise of any contract extension options; any decision to extend the contract would be subject to a separate decision, taken in accordance with procurement compliance requirements, the Council's key decision thresholds, and an assessment of value for money at that time.
Word for word from the decision Slough published for this meeting. Source: democracy.slough.gov.uk

Follow this further

Built from Slough's papers

What the report saysPro

Report to Cabinet Urgency procedure - Leader's Action

Recommendations

Cabinet is recommended to:

1. Approve the award of the contract for the Extra Care Housing Care and Support Service at The Pines and Northampton Place to Hales Group Ltd, in place of the originally awarded provider Agincare UK Ltd, who have confirmed that they are unable to accept the contract award. The contract will be for an initial term of 3 years from 1 September 2026, with the option to extend for a further 2 years, at an annual contract value not exceeding £0.946m (exc. VAT and approved uplifts).

2. Delegate authority to the Executive Director, People (Adults), in consultation with the Lead Member for Adult Social Care and the Section 151 Officer, to finalise the terms of the contract with Hales Group Ltd and authorise all necessary mobilisation and implementation activity. This delegation does not extend to the exercise of any contract extension options; any decision to extend the contract will be subject to a separate decision, taken in accordance with procurement compliance requirements, the Council's key decision thresholds, and an assessment of value for money at that time.

Reasons

To ensure that a compliant contract for care and support across both Extra Care Housing schemes is in place upon expiry of the existing contract on 31 August 2026, following the withdrawal of the originally awarded provider post tender.

Commissioner Review

The commissioners note the decision proposed is being treated as a matter of urgency, with the justification outlined and as such exempted from the call-in process. This should be used rarely and in exceptional circumstances.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Extra Care Housing Care and Support Service: Award of Contract to Hales Group LtdReport 168 KB DownloadRead as text

At this meeting

Whole meeting
2Extra Care Housing Care and Support Service: Award of Contract to Hales Group LtdThis decision

Who was there

1 of 2 attended
WC
Councillor Wal ChahalCommittee Member, present
AW
Councillor Anna WrightGuest, in attendance

On this subject at Slough

Search all
  1. Extra Care Housing Care and Support Service: Award of Contract to Hales Group LtdThis decision
  2. Notification of decision taken under Urgency Procedure - Leader's Action: Extra Care Housing Care and Support Service: Award of Contract to Hales Group LtdDecided
  3. Approval to Award Contract: Extra Care Housing Care and Support Services at The Pines and Northampton PlaceDecided
  4. Re-procurement of Adult Social Care Extra Care ContractsDecided
  5. Re-procurement of Adult Social Care Extra Care ContractsDecided
  6. Re-Procurement of Extra Care ContractNoted

More from Slough Cabinet Urgency procedure - Leader's Action

All decisions
MeetingDecisionOutcome
26 Mar 2026 Upton Hospital DevelopmentResolved – That it be agreed to: (a) Lease the site within Upton Hospital for the purpose of development of a new nei... Agreed Open
23 Oct 2025 Collection Fund Income Maximisation Partner - Contract AwardResolved – (a) That the award of the contract to Inform Holdings Ltd, trading as Analyse Local for a period of 3-year... Approved Open
11 Apr 2025 Mandatory licencing of Houses in Multiple Occupation feeResolved – That the changes to the mandatory Houses in Multiple Occupation (HMOs) licence fee as set out in Appendix ... Approved Open
30 Oct 2023 Procurement of Replacement of Fleet VehiclesResolved – (a) Approved entering into a new one-year vehicle contract lease with the new supplier Dawson Group Enviro... Approved Open
31 Mar 2023 Extension of Contract for Shared Legal Service with Harrow CouncilResolved – That the Monitoring Officer be authorised to extend the Inter-Authority agreement between Slough BC and Ha... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies