Highway Services Priorities & Resources Plan for 2013-14
AgreedCommittee2 papers
CPH Transport & Highways Decision Session agreed this item on Thursday 3 October 2013. Below is the council's own wording, with the papers it was decided on.
The Cabinet Member agreed the Highway Services Priorities and Resources Plan for 2013/14 (as shown in Appendices A to D) and its quarterly review/approval of changes at standing Cabinet Member and Assistant Service Director meetings and to agree to support reviews of the Highways Service to ensure it can continue to deliver its priorities in future years.
Word for word from the decision Solihull published for this meeting.Source: democracy.solihull.gov.uk
Report to CPH Transport & Highways Decision Session
Appendix A (i) Highway Services Resource Plan 2013 ‐ 14 Team Safe & Active Travel Service Area Road Safety Engineering
Team Structure Productive Time Non‐Productive Time Hrs Days Hrs Days Principal Engineer 766 104 1158 154 Traffic Surveys Supervisor 1297 175 627 84 Management Support Officer 754 102 494 66 Road Safety Engineer 1432 194 492 66 Road Safety Engineer 1468 198 456 61 Cycling Officer 1515 205 409 55 Total Time Available 7232 977 3636 485
Duration % completed Priority Service Area / Project Description Working Apr ‐ Aug 13 Days
Road Safety Activity Road Safety Partnerships (1 monthly, 1 bi‐monthly, 1 bi‐annual meeting and 2 quarterly meetings ) 15.5 40% Road Safety Strategy ‐ Annual Action Plan (quarterly review and monitoring) 1.1 80% Road Safety Website (monthly maintenance) 6.0 40% Local Safety Scheme Identification & Development of Project Briefs (annual analysis) 26.3 60% Local Transport Plan Scheme Development (with Capital Team) 4.0 40% Local Transport Plan Minor Works Delivery 12.7 40% 20mph Speed Limit Trial (progession of trial in South Shirley and consideration of next area) 18.3 30% 34.5 60% Local Speed Limit Changes (budget of £30,000 for schemes in the Barston / Catherine de Barnes area) 20mph Outside Schools (budget of £28,000 for scheme outside Windy Harbour School) 3.3 30% School Travel Plans and Safer Routes to School Programme 34.3 10% Organisation of Traffic Surveys (budget of £35,762 for both automatic and manual counts) 19.9 40% Collision Data and Analysis (responding to one‐off requests for approximately 2.5 hours per week ) 14.4 40% 7.7 40% Speed Aware (10 Main SpeedVisor campaigns and 60 Mini SpeedVisors to include a maximum 10 2012/13 requests) Speed Watch (management and admin to enable 1 per month in each of the 3 Neighbourhood areas) 5.7 40% Other Local Safety Initiatives (help and support to ensure delivery of local initatives e.g. ETP) 6.5 40% Pedestrian Crossing Assessment (initial assessment at 16 sites) 10.7 95% Pedestrian Crossing Assessment (detailed investgation at 6 locations) 18.7 0% Highway Efficiency Minor Works (budget of £15,000 for new street furniture and road markings) 12.9 70% Vehicle Activated Signs (three new/re‐located VAS and maintenance of all existing) 13.5
Road Safety Audit Highway Authority Responses to Audits of Local Transport Plan (LTP) Schemes 14.4 20% Highway Authority Responses to Audits of European Regional Development Fund (ERDF) Schemes 6.4 50% Highway Authority Responses to Audits of Developer Schemes and Other Projects 12.8 150% Road Safety Audit Checklists 2.0 50% Undertake Road Safety Audits Alongside Consultants WSP (5 audits in Solihull) 2.4
Cycling Activity North Solihull Cycle Project (development and delivery of Strategic Cycle Network with Capital Team) 86.4 40% Steering Group Meetings (quarterly meetings) 2.7 40% Design and Input During Scheme Development 12.8 40% Park Routes Development (Tudor Grange and Shirley Parks only) 12.8 30% Borough Map and Guide (annual review and update) 1.6 50% Regional Meetings (quarterly meetings) 1.6 50% Cycle Network Maintenance (budget of £35,000 for maintenance and promotion) 4.8
Sustainable Travel Council Travel Plan (this year's priorities include CarShare and Council facilities) 50.4 40% School Parking issues 20.0 40% Solihull Station Travel Plan (delivery of sustainable travel improvements on behalf of Centro) 3.5 40% Customer Contact Petitions & Reporting (6 petitions and 2 miscellanous reports or briefing notes to T&H CDS) 23.3 40% CRM Requests & Processing Post 110.7 40% Emails (daily communication and responses to general requests and miscellaneous queries) 205.3 50%
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow CPH Transport & Highways Decision Session at Solihull and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.