ICT Capital Project Update
The purpose of this report is to update the Cabinet Member for Resources on the current status of the Capital ICT Projects Programme. The report also seeks approval to allocate the full funding amount to the Oracle exploitation project as originally stated in the report to the Leaders cabinet meeting in July 2012.
Decision: The Cabinet Member: ( i ) noted the current status of the Capital ICT Projects Programme for approval and comment; (ii) approved the recommendation to reallocate £160,000 from the ICT Projects fund to enable the full Oracle exploitation programme to be delivered; and (iii) approved the balance of £58,000 from completed projects to be transferred to the ICT Projects fund. Decision page