Shirley Park Phase 2 Improvement Plan

Approved Committee 3 papers

CPH Community Cohesion and Partnerships Decision Session approved this item on Thursday 12 December 2013. Below is the council's own wording, with the papers it was decided on.

Item9

Resolved

RESOLVED The Cabinet Member: (i) Approved the Shirley Park Phase 2 Improvement Plan. (ii) Approved the recommendation not to reopen the former changing room facility car park as a future park user car park due to strong opposition from adjoining residents. (iii) Approved the recommendation to undertake a 6 month shared cycle provision trial so that feedback from this trial can be used to inform whether cycle access within the park should be made a permanent feature, revised or withdrawn.
Word for word from the decision Solihull published for this meeting. Source: democracy.solihull.gov.uk

Follow this further

Built from Solihull's papers

What the report saysPro

Report to CPH Community Cohesion and Partnerships Decision Session

Purpose of report

1.1To seek approval for the proposed Shirley Park Phase 2 Improvement Project plan.

2. Decision(s) Recommended

(a) Approve the Shirley Park Phase 2 Improvement Plan.

(b) Approve the recommendation not to reopen the former changing room facility car park as a future park user car park due to strong opposition from adjoining residents. (c) Approve the recommendation to undertake a 6 month shared cycle provision trial so that feedback from this trial can be used to inform whether cycle access within the park should be made a permanent feature, revised or withdrawn.

Background

3.1In 2011 the Heart of Shirley Development, renamed Shirley Parkgate Development received approval to proceed and the project has since continued to progress.

3.2In April 2012 Officers reported to the Cabinet Member for Safer Communities the results of the initial Shirley Park consultation carried out in 2007 and further consultation work carried out in 2012.

3.3In November 2012 Officers reported the Shirley Park Improvement Project design, which had been developed to incorporate 5 key improvement areas as identified following the 2007 and 2012 consultations. Appendix 1 outlines the approved Shirley Park Improvement Project Design, highlighting the new park layout and providing a brief description of the key areas for improvement.

3.4In July 2013 Cabinet Member for Community Cohesion and Partnerships approved the award of tender for the Shirley Park Improvement Project Work. The tender process provided a highly competitive tender cost which consequently resulted in a surplus fund of £182,356 on the £604,000 budget. Therefore Officers suggested that further works were undertaken to identify a phase 2 improvement project plan, creating further investment and value for Shirley Park. Using the information from the 2007 and 2012 consultations, Officers agreed to develop a phase 2 improvement plan for the £182,356 budget and present the plan to a future Community Cohesion and Partnerships Cabinet Decision Making Session for approval.

3.5Following the report to Cabinet Member for Community Cohesion and Partnerships in July 2013, as part of the phase 2 plan design, Officers were also asked to explore further improvements to the following areas:

o Reopening the original changing room car park to serve as a public car park for park users.

o Provision of segregated cycle route footpaths rather than the current proposed shared cycle route footpaths through the park.

Officers have since explored both areas for improvement and have added information and recommendations as part of this report.

4. Matters for Consideration

4.1The following three key sections provide information and proposed recommendations in terms of the proposed phase 2 plan, former changing room car park and segregated cycle routes.

Phase 2 Plan

4.2The consultation events undertaken in 2007 and 2012 outlined the following 5 key areas of improvement that the local and wider community wanted to see developed through the Shirley Park Improvement Project: o Improve nature conservation

o Youth facilities/climbing wall/trim trail

o Provision of cycle route

o Upgrade play equipment

o Enhanced security

4.3The 5 key areas for improvement and the 2007 and 2012 consultation information supporting this have been used to formulate the proposed additional improvements which form the phase 2 plan.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix 1Appendix 1 2.2 MB Download
PDF
Appendix 2Appendix 2 3.9 MB Download
PDF
Shirley Park Phase 2 Improvement PlanReport 103 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 10 attended
HA
Councillor Howard Allen Green Group SpokespersonSpokesperson, present
CB
Chris BarrOfficer, present
AB
Alan BrownOfficer, present
JH
Councillor Jean Hamilton Liberal Democrat Group SpokespersonSpokesperson, present
KH
Kathryn HemmingsOfficer, present
MD
Councillor Mrs Diana Holl-Allen MBE Cabinet Portfolio HolderCommittee Member, present
AN
Councillor Alan Nash Labour Group SpokespersonSpokesperson, present
SR
Sara RooneyOfficer, present
RS
Richard StaveleyOfficer, present
MT
Martin TaylorOfficer, present

On this subject at Solihull

Search all
  1. Shirley Park Phase 2 Improvement PlanThis decision
  2. Application for a premises licence - hideout, parkgate shopping centre, shirleyRefused

More from Solihull CPH Community Cohesion and Partnerships Decision Session

All decisions
MeetingDecisionOutcome
16 Apr 2014 Report to advise on food fraud in particular substitution of meat species e.g horse meatRESOLVED The Cabinet Member: (i) Approved the prioritisation of food authenticity sampling as part of the annual food... Approved Open
16 Apr 2014 Green spaces strategy reviewRESOLVED The Cabinet Member for Community Cohesion and Partnerships approved the 2014 Green Space Strategy Review doc... Approved Open
11 Feb 2014 Food hygiene rating schemeRESOLVED The Cabinet Member agreed to continue the operation of the National Food Hygiene Rating Scheme. Agreed Open
11 Feb 2014 Bereavement service "CODE OF BURIAL PRACTICE"RESOLVED The Cabinet Member approved the adoption of the ‘Code of Burial Practice.’ Approved Open
11 Feb 2014 Revenue and capital monitoring - quarter 3 2013/14RESOLVED The Cabinet Member endorsed the 2013/14 revenue and capital monitoring position as at Quarter 3 (to the end ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies