STREET LIGHTING - LED REPLACEMENT PROGRAMME FINANCIAL UPDATE

Agreed Committee 4 papers

CPH Transport & Highways Decision Session agreed this item on Thursday 11 September 2014. Below is the council's own wording, with the papers it was decided on.

Item6

Resolved

The Cabinet Member agreed to:- 1. Note the progress of the project to date; and 2. Approve the revised scheme costs and funding model.
Word for word from the decision Solihull published for this meeting. Source: democracy.solihull.gov.uk

Follow this further

Built from Solihull's papers

What the report saysPro

Report to CPH Transport & Highways Decision Session

Purpose of report

1.1To provide Cabinet Member with a financial update on the street lighting LED replacement programme.

2. Decision(s) Recommended

2.1Cabinet Member is asked to:- (a) Note the progress of the project to date (b) Approve the revised scheme costs and funding model

Background

3.1The Street Lighting Service is currently managing a programme to replace 6,083 obsolete Mercury Blended Filament Units (MBFUs) and other lamps with LEDs. The programme forms the first stage of the Council’s Street Lighting Strategy which was approved in 2012. 3.2 The LED replacement programme is expected to save £121,794 in energy costs per annum as well as 750 tonnes of carbon, equating to £9,000 in Carbon Reduction Commitment charges. This is in addition to £224,000 which the Street Lighting Service has contributed to the Council’s Medium Term Financial Strategy from 2014/15 and which has been achieved through a review of the service area’s budget allocation. 3.3 The programme commenced in Dorridge in May 2014. Given available funding, 3,588 lanterns have been programmed for replacement during the 2014/15 financial year across Dorridge, Knowle, St Alphege, Blythe, Shirley East, Shirley South and Shirley West wards. The remaining 2,495 units within other wards have been scheduled for replacement, using identified annual budget allowances up until 2020/21. A full budget profile from 2014 through to 2021 can be seen in Appendices A-C. 3.4 Since the commencement of the programme, £13,578 of the expected £121,794 of energy savings have been recorded along with 73 of the 750 tonnes of carbon, equating to just under £1,000.

4. Evaluation of Alternative Option(s)

4.1Various options for the Street Lighting Service were considered by the Neighbourhood Services Scrutiny Board at its November 2012 meeting. 4.2 The Board considered four main investment options based on achieving energy savings through the use of a Central Management System (CMS) and replacing older less energy efficient lighting, in particular the MBFUs which are to be phased out by 2015 due to EU legislation. The four options were as listed below:  Option 1 – Prepare for the introduction of CMS but focus primarily on introducing low energy lighting

 Option 2 - Carry out a phased implementation of CMS at beneficial locations

 Option 3 – Implement CMS to all street lighting within the Borough

 Option 4 – Take no further action on CMS but introduce dimming and trimming using alternative technology 5. Reasons for Recommending Preferred Option

5.1Following further analysis and consideration a “preferred option‟ was developed from the range put forward to Neighbourhood Services Scrutiny Board and which will see the phased upgrading of all street lighting in the Borough to LED technology. The preferred option was presented to Cabinet Member by way of a detailed report in December 2012 and authorisation was given to produce a business case to deliver the first stage of the option which will see the replacement of life expired MBFUs. 6. Scrutiny

6.1As detailed in Sections 4 and 5 of this report, investment options for the Street Lighting Service were considered by the Neighbourhood Services Scrutiny Board at its November 2012 meeting. As previously stated, as a result of comments received from the Scrutiny Board a “preferred option” was developed which will see the phased upgrading of all street lighting in the Borough to LED technology.

7. Implications

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix AAppendix A 38 KB Download
PDF
Appendix BAppendix B 50 KB Download
PDF
Appendix CAppendix C 51 KB Download
PDF
STREET LIGHTING: LED REPLACEMENT PROGRAMME FINANCIAL UPDATEReport 179 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 10 attended
TR
Councillor Ted Richards OBE Cabinet Portfolio HolderCommittee Member, present
KR
Councillor Ken Rushen Liberal Democrat Group SpokespersonCommittee Member, present
SH
Councillor Stephen Holt Green Group SpokespersonCommittee Member, present
EB
Edward BradfordOfficer, present
JH
Jim HarteOfficer, present
AM
Amrik MankuOfficer, present
AM
Adrian MatthewsOfficer, present
CM
Chris MortonOfficer, present
AP
Ashley PriorOfficer, present
JR
Jodie RobinsOfficer, present

On this subject at Solihull

Search all
  1. STREET LIGHTING - LED REPLACEMENT PROGRAMME FINANCIAL UPDATEThis decision
  2. Street LightingDecided
  3. Street Lighting – Service UpdateNoted
  4. Street lighting - led replacement programmeAgreed
  5. Street lighting - led replacement programmeApproved
  6. Street lighting - led replacement programmeAgreed

More from Solihull CPH Transport & Highways Decision Session

All decisions
MeetingDecisionOutcome
28 Mar 2019 Apologies and SubstitutionsApologies from Councillor D Cole. Decided Open
28 Mar 2019 Declarations of InterestNone. Decided Open
28 Mar 2019 Questions and DeputationsCouncillor T Hodgson attended and addressed the meeting in relation to Petitions 5 & 6 – Request to keep the 3 hours ... Decided Open
28 Mar 2019 Petition SummaryThe Cabinet Member: (a) Noted the petitions received and the proposed programme for investigating and responding to t... Noted Open
28 Mar 2019 Revenue & Capital Monitoring 2018/19 as at 31st December 2018The Cabinet Member: 1. Considered and endorsed the 2018/19 revenue and capital financial monitoring forecast as at 31... Decided Open