Conditional approval and subject to the applicant entering into a Section 106 Agreement to mitigate the impact of the proposal on safeguarded land identified to deliver HS2, enhance the landscape character of the site, and accord with the guidance in the NPPF.
Word for word from the decision Solihull published for this meeting.Source: democracy.solihull.gov.uk
The principle of this application is clearly supported by both Government Policy set out in the NPPF and Local Plan Policy P1. The proposal will deliver support for sustainable economic growth that diversifies the uses at the National Exhibition Centre, which carries significant weight in the planning balance.
The change of use and external structures respect the existing design style of the exhibition building/leisure facilities at the NEC. The scale and massing of the new external elements are in keeping with the surrounding context, whilst the innovative design of the outdoor elements of the attraction will create an active frontage that will enhance the sense of place at the NEC as a key visitor destination in the region. The proposal therefore, accords with Policy P15 of the Solihull Local Plan and weight can be attributed to the matter.
The proposed new visitor attraction would have no adverse impact on the local highway network. The impact of the proposed development therefore has been shown not to be severe in the context of paragraph 32 of the NPPF. Further the proposal accords with Policy P8 of the Local Plan and neutral weight can be attributed to the matter in the planning balance.
The proposal will cause no material harm to neighbour amenity or the landscape setting subject to off-site mitigation within the NEC, which can be secured through a S106 Agreement. Neutral weight should be given to these elements in the planning balance.
The HS2 Bill has now gained Royal Assent on 23rd February, paving the way for a new rail line that will increase capacity on our railways.Part of the application site is identified as falling within the limits of land that is the subject of a formal Safeguarding Direction (required for the People Mover) and is therefore required for the construction and operation of the HS2 scheme. Subject to the Council, Developer and Landowner enter into a legal agreement on terms satisfactory to HS2 Ltd to secure the proposed working arrangements in respect of the development including the layout of the works and zoning of the development land, the timings of construction of the works, the removal of works at HS2 Ltd’s request and any other necessary terms, the land can be safeguarded to deliver the project. Neutral weight therefore, can be attributed to the matter.
The application should be approved subject to conditions and the applicant entering into a S106 Agreement.
KEY PLANNING ISSUES
The following key planning issues are material to the determination of this application:
• Principle of Development/Economic Benefits; • Impact on the character and appearance of the area; • Impact on highway safety; • Impact on neighbour amenity/business premises; • Landscape impact; • HS2; and • Section 106 Agreement.
CONSULTATION RESPONSES
Statutory Consultees - The following Statutory Consultee responses have been received:
Bickenhill Parish Council – No comments received.
Highways England – No objection.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.