CPH Environment & Highways Decision Session approved this item on Tuesday 23 June 2020. Below is the council's own wording, with the papers it was decided on.
The Cabinet Member RESOLVED to: 1. Approve the Procurement Strategy for procuring the new Strategic Environment Contract. 2. Request that the Cabinet Member and Opposition Spokespersons would be kept updated on the procurement process, and would report back to the Decision Session.
Word for word from the decision Solihull published for this meeting.Source: democracy.solihull.gov.uk
Report to CPH Environment & Highways Decision Session
Purpose of report
1.1To provide the Cabinet Member with details of the Councils proposed approach to procuring a new Strategic Environment Contract.
2. Decision(s) recommended
2.1That the Cabinet Member approves the Procurement Strategy for procuring the new Strategic Environment Contract.
3. What is the issue?
3.1The current Strategic Environment Contract is delivered by Amey. The current contract term ends on 31 March 2022.
3.2A report was presented to the Cabinet in October 2019, which gave options for the future provision of the services provided through the Strategic Environment Contract.
3.3The options presented to the Cabinet were to retender the contract or to establish a Local Authority Company.
3.4The Cabinet selected the option to retender the Contract and provided an instruction to Officers to start the procurement process to deliver a new Strategic Environment Contract to start on 01 April 2022.
3.5To oversee the delivery of the contract a robust Project Management and Governance structure has been put in place – this is summarised in the following figure.
SEC 22- Programme Board Legal, Finance, Procurement, Operations, Chaired by Assistant Director Highways & Environment
SEC 22 - Project Team Eunomia Finance, Procurement, Operations, Technical Consultants Legal and Project Support
Workstream Workstream Workstream Workstream Streetcare and Kerbside HWRC and Forestry Grounds Collections Transfer facility
3.6Through a competitive tendering process, Technical Consultants Eunomia have been appointed to support the delivery of the Contract. Eunomia have a proven track record of supporting local authorities to deliver contracts of this type – particularly in times of uncertainty which is critically important given the current position with Covid- 19 and uncertain impacts on policy and contract delivery.
4. What options have been considered and what is the evidence telling us about them?
4.1Prior to starting the tendering process it is essential to understand what is required from the procurement process and to convey this to prospective bidders. The approach to the procurement process will determine the level of interest in the tender and will also influence the detailed content of the specification and final contract.
4.2To provide direction for the tender and information to bidders a Procurement Strategy has been developed. The Strategy covers the following key areas
The Procurement procedure Contract Nature Contract Length Contract Award Criteria Approach to deselecting bidders Key areas of service design Contractual risk Key Strategic Performance Indicators 4.3 Each Strategy element will be considered in more detail in the following sections with a brief summary of the rationale for the approach to each element.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Councillor Ken Hawkins Cabinet Portfolio HolderCommittee Member, expected
CD
Councillors DiaryOfficer, expected
TH
Councillor Tim Hodgson Green Group SpokespersonCommittee Member, expected
DC
Councillor David Cole Labour Group SpokespersonCommittee Member, expected
AB
Alan BrownOfficer, expected
KT
Councillor Kathryn Thomas Liberal Democrat Group SpokespersonCommittee Member, expected
JS
Joe SuffieldDS Officer, expected
Hear about the next one first
Follow CPH Environment & Highways Decision Session at Solihull and we tell you when its next papers are published, before the meeting rather than after it.
Flood Risk Management - Annual UpdateThe Cabinet Member RESOLVED to: a) Note the contents of the report relating to work carried out during 2020/21 b) App...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.