Deferred, against the recommendation, for further information to be provided regarding the siting and design of the clubhouse, lighting, and noise mitigation. [name removed] spoke against the application whilst [name removed] spoke in support.
Word for word from the decision Solihull published for this meeting.Source: democracy.solihull.gov.uk
This full planning application seeks consent for the demolition of the existing clubhouse and the construction of a re-sited replacement clubhouse, the provision of an all-weather sports pitch and the reconfiguration of two playing pitches at the existing Warwickshire Gaelic Athletic Association grounds on Catherine de Barnes Lane.
The principle of this proposal in the Green Belt is considered to be appropriate development. It involves the provision of appropriate facilities in connection with the existing use of the land for outdoor sport and it is considered that the facilities preserve the openness of the Green Belt and do not conflict with the purposes of including land within it in accordance with the requirements of the NPPF on this matter.
The design of the new clubhouse meets Sport England requirements and will allow for an element of community use which the current facilities do not provide. The layout is functional and the addition of the all-weather pitch will benefit both the applicant and the wider community.
In terms of amenity, the site lies in open countryside however it is acknowledged that there are sensitive residential receptors located to the east of the site and to south of the site. The Council’s Public Protection Officer is satisfied that the proposed development accords with Policy P14 in that the proposed development will not have an adverse impact on the amenity of existing occupiers subject to a number of conditions, some of which are pre-commencement.
The Lead Flood Authority are satisfied that following the submission of modelling of the proposed modifications to the watercourse that runs through the western part of the site, the proposal will not cause a greater risk of flooding upstream or downstream of the site.
In terms of ecology and biodiversity net gain, the Council’s Ecologist is mindful that the way in which net gain for the site has been calculated is unusual. It is considered that this proposal is unique given the fall-back position of the Proportionate Reconfiguration scheme and because the proposal is intrinsically linked to the M42 Junction 6 DCO consent. This is therefore a material planning consideration. It is considered that there would be an element of ‘double counting’ if this scheme was required to provide the full biodiversity net gain given that the Proportionate Reconfiguration scheme is already contributing to the gain provided by the wider DCO scheme. Overall there will be a 19% gain in biodiversity units with the DCO and this proposal combined. In this instance, it is accepted that the proposal accords with Policy P10 of the Solihull Local Plan 2013 in this regard.
The proposal is considered to be acceptable in all other aspects, subject to appropriate conditions, and is thus considered to comply with Policies P8, P10, P11, P14, P15, P17 and P20 of the Solihull Local Plan 2013.
Therefore, the proposal accords with the development plan as a whole and benefits from a presumption in favour of sustainable development in accordance with the Framework and it is for these reasons that the application should be approved.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.