Revenue & Capital Monitoring 2020/21 as at 31st December 2020
AgreedCommittee2 papers
CPH Growth & Infrastructure Delivery Decision Session agreed this item on Thursday 4 March 2021. Below is the council's own wording, with the papers it was decided on.
The Cabinet Member agreed to: 1. Consider and endorse the 2020/21 revenue and capital financial monitoring forecast as at 31st December 2020. 2. Consider the Portfolio’s progress against the latest 3 year savings targets in the Medium Term Financial Strategy (MTFS) as at 31st December 2020. 3. Approve in conjunction with the Cabinet Member for Resources, a new reserve for Small Habitats Grants Programme uncommitted funding in order to mitigate against potential delivery and contractual risks resulting from the overall Wildlife Ways programme for up to 5 years post-delivery.
Word for word from the decision Solihull published for this meeting.Source: democracy.solihull.gov.uk
Report to CPH Growth & Infrastructure Delivery Decision Session
Appendix A Growth and Infrastructure Delivery Quarter 3 2020/21 Financial Position
Economy and Infrastructure Directorate Position
The context of this Cabinet portfolio position is taken into account with the whole of the Economy and Infrastructure Directorate which is currently forecasting an adverse variance of £1.713million due to the impact of Covid-19 and £919,000 attributable to other factors which is offset by use of reserves (£919,000).
1. 2020/21 Revenue Position Current Forecast - £266,000 Favourable Variance
Quarter 3 2019/20 Revenue Forecast by Service Area £000s 1,000
0 0 0 0 (13) (76) (200) (253) (400) UK Central Growth & Development Directorate Management and Support - Growth and Infrastructure Delivery
2. Explanations for significant Revenue Variances
COVID-19 Non COVID- Total Budget Forecast Forecast 19 Forecast Forecast Service Area Comments £000's £000's Variance Variance Variance £000's £000's £000's
UK Central 0 0 0 0 0 The UK Central service area is wholly externally funded therefore there is no net budget.
COVID-19 Adverse variance due to lower than expected rental income from the Chelmund's Cross Enterprise Growth & Development 847 834 42 (55) (13) Centre. Non COVID-19 Favourable variance due to salary savings as consequence of temporary vacancies.
Directorate Management and Support Early delivery of savings re-invested in the Directorate as part of MTFS and use of Directorate reserve towards 177 (76) 0 (253) (253) - Growth and Infrastructure Delivery funding an overall variance of nil for the Economy and Infrastructure Directorate.
Chelmunds Cross Enterprise Centre 35 35 0 Reconfiguration of reception area and vacant units at Chelmunds Cross Enterprise Centre.
Warm Homes Fund (Council Installation of central heating in SCH properties. 283 11 (272) Properties) Variance due to fewer than originally expected installations having been completed within the prescribed period.
Wildlife Ways Green Corridors 24 24 0 Funding to support non-ERDF green corridor elements of the Wiildlife Ways programme. Support
Greening The Grey (Landscapes) 3,172 3,172 0 Funding for landscape elements of the Greening The Grey programme.
Greening The Grey (Small Grants) 50 50 0 Funding to provide small grants to partners to provide additional works as part of the Greening The Grey programme.
Woodside Industrial Unit 2 2 0 Final works and retention payment for works refurbishing industrial units. Refurbishment Project provides funding for the acquisition of properties as part of wider regeneration of Kingshurst Village Centre. Kingshurst Village Centre 385 949 564 Variance as consequence of some aquisitions being completed earlier than envisaged (during 2021/22). The forecast expenditure is within the total budget for the project which is fully funded by the WMCA thus variance has no net impact on SMBC.
UGC HS2 NEC Longabout 40 40 0 Capital elements of works on the NEC longabout as part of the wider UKC HS2 Interchange programme being delivered by the UGC.
UGC HS2 NEC Roundabout Over Capital elements of works on the NEC roundabout over the trace as part of the wider UKC HS2 Interchange programme being delivered by the 15,862 15,862 0 Trace UGC.
Old Damson Lane Travellers Phase 2 1 1 0 Final works and retention payment for works developing travellers pitches.
Langley Hall Park ERDF Small 39 39 0 ERDF Small Habitat grant funded project with match funding from parks commuted sums. Habitats Project
Bees And Tress - ERDF Small 61 61 0 ERDF Small Habitat grant funded project with match funding from section 106 contributions. Habitats Grant
Damsels And Dragons 98 98 0 ERDF Small Habitat grant funded project with match funding from the Environment Agency.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow CPH Growth & Infrastructure Delivery Decision Session at Solihull and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.