Resolved
The meeting was adjourned, due to technical issues, without this matter determined.
Planning Committee decided this item on Wednesday 30 June 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
The meeting was adjourned, due to technical issues, without this matter determined.
Laing O’Rourke Murphy Joint Venture (LM) has sought consent on behalf of HS2 Ltd under Schedule 17 of the High Speed Rail (London-West Midlands) Act 2017 for the Bringing into Use of the Temporary Kenilworth Greenway Diversion which is a Schedule 1 work.
Bringing scheduled works into use are covered by Paragraph 9 of Schedule 17. The purpose of Bringing into Use approvals is to ensure that the nominated undertaker takes all reasonably practicable measures for the mitigation of the work.
Having regard to the parameters by which the local planning authority, as a qualifying authority, may consider arrangements for a bringing into use request for approval, the proposals are considered to be acceptable.
The temporary Kenilworth Greenway diversion is specified as a Schedule 1 work in the Act (Works Nos 2/183B and 3/1A).
The works subject of this submission are already in-situ on site.
BRINGING INTO USE Paragraph 9 of Schedule 17 to the Act requires the nominated undertaker to submit a Bringing Into Use request for most scheduled works and railway depots. Paragraph 9 (1) of Schedule 17 states:
“If the relevant planning authority is a qualifying authority, no work to which this paragraph applies may be brought into use without the approval of that authority.”
This requirement applies to all scheduled works, except to the extent that the work is underground and any depots constructed for or in connection with the maintenance of railway vehicles or track paragraph 9 (2). The purpose of Bringing Into Use approvals is to ensure that the nominated undertaker takes all reasonably practicable measures for the mitigation of the work.
Planning Forum Note 7 states that in most instances all practicable mitigation measures for temporary scheduled works will already have been imposed through the HS2 Phase One Code of Construction Practice (CoCP), in which case additional mitigation plans would not be required.
It also notes that Bringing Into Use applications would generally list relevant plans and submissions in relation to approvals or agreements previously obtained, which may be brought together on a consolidated mitigation plan where that mitigation is not already shown on a single set of approved drawings. However, because approval of plans and specifications is not required in respect of temporary works, in these instances there are no approved plans that can be included in any Bringing into use submission.
MAIN ISSUES
The High Speed Rail (London-West Midlands) Act 2017 received Royal Assent on 23rd February 2017. Section 20 of the Act grants deemed planning permission under Part 3 of the Town and Country Planning Act 1990 (TCPA) for HS2 Phase One and associated works between London and the West Midlands.
However, Schedule 17 of the Act puts in place a bespoke process for the approval of certain matters to the design and construction of the railway which requires that the nominated undertaker must seek approval of these matters from the relevant planning authority.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
PL/2020/02821/HS2DIS: Kenilworth Greenway Schedule 17Report | 552 KB | DownloadRead as text |
Follow Planning Committee at Solihull and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Jun 2026 | Birmingham Airport Night Flying Policy Sub-CommitteeRESOLVED That Councillors Bob Grinsell (Chairman), Jane Lamden and David Hoey were elected to sit on the Birmingham A... | Decided | Open |
| 27 May 2026 | Appointment of chairmanRESOLVED Councillor Bob Grinsell was elected Chairman for the Municipal Year 2026/27. | Decided | Open |
| 27 May 2026 | Appointment of vice-chairmanRESOLVED Councillor James Bradley was elected Vice-Chairman for the Municipal Year 2026/27. | Decided | Open |
| 21 May 2025 | Appointment of ChairmanRESOLVED Councillor Bob Grinsell was elected Chairman for the Municipal Year 2025/26. | Decided | Open |
| 21 May 2025 | Appointment of Vice-ChairmanRESOLVED Councillor Prish Sharma was elected Vice-Chairman for the Municipal Year 2025/26. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.