CPH Environment and Infrastructure Decision Session noted this item on Monday 14 February 2022. Below is the council's own wording, with the papers it was decided on.
The Cabinet Member RESOLVED to: a) Note the findings of the consultation on the proposed Solihull Integrated Transport Hub scheme as set out in Appendix A and summarised in paragraphs 4.1 to 4.3. b) Note the additional design work that will be undertaken in response to the consultation, as set out in paragraphs 4.4 to 4.6. c) Approve the next steps set out in the report.
Word for word from the decision Solihull published for this meeting.Source: democracy.solihull.gov.uk
Report to CPH Environment and Infrastructure Decision Session
Purpose of report
1.1To present the findings of the public consultation on the proposed Solihull Station Integrated Transport Hub Scheme, and to set out the next steps for the project.
2. Decision(s) recommended
2.1The Cabinet Member is asked to
a) Note the findings of the consultation on the proposed Solihull Integrated Transport Hub scheme as set out in Appendix A and summarised in paragraphs 4.1 to 4.3.
b) Note the additional design work that will be undertaken in response to the consultation, as set out in paragraphs 4.4 to 4.6.
c) Approve the next steps set out in the report.
3. Matters for Consideration
Introduction
3.1Between July and September 2021, public consultation was held on the proposed conceptual design of the Solihull Integrated Transport Hub Scheme. 3.2 The consultation presented a preferred design option for the redevelopment of Solihull Station, with the following key features:
(a) The development of a single storey building with an elevated platform, with a similar layout as the existing station, but larger in scale. Generous internal public concourse space that includes ticketing facilities, public toilets, and commercial spaces.
(b) A new widened underpass, along with a new lift with twice the current capacity, and an additional stairway to platform level. Ticket gates at either side of the underpass and a new and improved rear entrance.
(c) The platform’s uncluttered design is achieved by centralising the accommodation facilities around the lift and stairways. The existing accommodation and canopy structure are replaced with a new building, which will be kept within the footprint width of the stairways to improve passenger circulation.
(d) Establishment of three distinct zones within the overall site. The new station forms the central zone, in approximately the same location as the existing station, this allows the overall site to be split into two halves either side of the station: one dedicated to the transport interchange which utilises the underused existing green space and the other to new public realm, with enhanced green space that can be enjoyed by station users.
(e) Design of the surrounding public realm, to allow intuitive access into and around the new station development. An abundance of green space and planting will be provided and pedestrian routes around the site are designed for easy, safe navigation and clear sight lines for both pedestrians and cyclists.
(f) The proposed station will be a landmark building which complements its surroundings.
(g) New canopies over the platform to ensure weather protection and improving safety and passenger comfort during inclement weather. The elevated nature of the platforms and track provide clear views for onward travel routes. Views directly into the new concourse space are provided through the station building's large glazed gable end.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow CPH Environment and Infrastructure Decision Session at Solihull and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.