CPH Environment and Infrastructure Decision Session noted this item on Thursday 14 April 2022. Below is the council's own wording, with the papers it was decided on.
The Cabinet Portfolio Holder:- (a) Noted progress against the Network Management Plan and its updated Action Plan, as detailed in the report and shown in Appendix A; (b) Endorsed the prioritisation framework for the Parking Displacement Programme, as set out in Appendix B; (c) Approved the proposed Parking Displacement Programme 2022/23, as set out in Appendix C; and (d) Agreed to receive annual updates as part of the Highway’s Asset Management Plan and Community Liveability Programme (CLP) priority setting processes.
Word for word from the decision Solihull published for this meeting.Source: democracy.solihull.gov.uk
Report to CPH Environment and Infrastructure Decision Session
Purpose of report
1.1To provide an update and opportunity to comment on the Council's statutory Network Management Plan (NMP) for the public highway.
1.2Consider and approve a prioritisation mechanism for the re-established Parking Displacement Programme (PDP), and agree the associated schemes to be taken forward to consultation and if supported, construction.
2. Decision(s) recommended
2.1The Cabinet Member is asked to:
(a) Note progress against the Network Management Plan and its updated Action Plan, as detailed in the report and shown in Appendix A.
(b) Endorse the prioritisation framework for the Parking Displacement Programme, as set out in Appendix B.
(c) Approve the proposed Parking Displacement Programme for 2022/23, as set out in Appendix C. (d) Agree to receive annual updates as part of the Highway’s Asset Management Plan and Community Liveability Programme (CLP) priority setting processes.
3. Matters for Consideration
Network Management Plan
3.1At the March 2020 Environment and Highways Cabinet Member meeting, the current statutory Network Management Plan (NMP) for the public highway in Solihull was approved, following consultation with stakeholders.
3.2The NMP sets out the network and traffic management priorities for the borough and has been developed using a “Plan on a Page” format. This format is now widely adopted, allowing information to be simplified and made more easily accessible.
3.3The current document, required by the Traffic Management Act 2004, runs from 2020 to 2026 and is kept under review and updated regularly to reflect emerging council priorities, alongside changes to the highway network and how it is being used.
3.4The last two years have seen unprecedented change in the way the network is used and operates. Whilst it is possible that many of these changes are temporary due to the covid pandemic, it is anticipated that the impact and effect will continue to influence how the transport network is used for some time.
3.5Whilst the impact has been clear, many of the work programmes identified within the NMP remain relevant and have continued throughout the last two years. It is appropriate, therefore, to provide an update and consider emerging priorities.
Parking Displacement Programme
3.6At the February 2022 Environment and Infrastructure Cabinet meeting, the Parking Displacement Programme (PDP) was re-established following support from the Stronger Communities and Neighbourhood Scrutiny Board.
3.7The PDP now forms part of a ring-fenced element of the annual Community Liveability Programme with a dedicated annual budget of £50,000.
3.8As part of the review process, draft criteria for a future PDP scheme were considered and formed the basis of the recommended approach to be adopted when considering where best to invest resources. Appendix B sets out the detail framework used to prioritise the 132 locations that came forward through the review process.
4. What options have been considered and what is the evidence telling us about them?
Network Management Plan
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow CPH Environment and Infrastructure Decision Session at Solihull and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.